Module 7: Forecasting

Quarterly Cycles

main display page
Local Interconnection Services (LIS)
 
          Quarterly Cycles
 
What to Submit?

The Quarterly Forecast cycle (for years 1 and 2) requires that you submit a quarterly forecast seven (7) months in advance of the quarter when the facilities are needed.

Why a 7 Month Interval?

This cycle is required to allow CenturyLink one (1) month to determine network needs and place vendor orders, and then a minimum of six (6) months to complete the network build.

Seven (7) months after submission of the your initial forecast, CenturyLink will have the necessary capacity in place to meet your forecast.



Click here to view the two-year Forecasting schedule.