Archived System CR SCR120716-1IG Detail |
Title: ASOG 54 – Industry Release / EASE ordering system and ASR gateway | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR120716-1IG |
Completed 4/19/2017 |
- | 28/ | Forum ATIS-OBF |
Originator: Walker, Letty |
Originator Company Name: CenturyLink |
Owner: Walker, Letty |
Director: |
CR PM: Lorence, Susan |
Description Of Change |
The EASE ASR Gateways are being updated to support changes for ASOG 54, including ASOG and UOM-ASR Schema changes as mandated by ATIS-OBF. Details for the ASOG 54 industry changes can be found at http://www.atis.org/. New or changed fields and forms being added to the ASOG form package are as follows:
CN/R practice: Modification to the General text to add this is a augment of existing error notification procedures. ECI practice: Removal of the following fields:
CPHD, PEND ORD, SM, SM2, SM3, SM4, SM5, SM6, SM7, QOPT, PCT, EASPEED, EA TYPE, CONFIG REMARKS, ACPON, ACAT, TNT, ACCESSID, ACCESSORD, PORTID, PORTORD, ACCID, ACORD, SOPTCON, SUBNET MASK, TRM, VPN NM, IPAI, IP ADDRESS, ICID, EXDI, EGRESS, EAID, ASN
• REQTYP field (Form:ASR): Modification to valid entries to add (ASR) abbreviation to step 1 and 3a, change of verbiage from Service Request to Service Inquiry in Step 3A an 3B. • IWBAN (Form:ASR): Modification to Usage Note 1 to add value of ‘H’. • SITE CON (Form:ASR): Creation of new field – Site Contact – Identifies the site contact name for access when the customer utilizes a Carrier Hotel as the primary location. • TEL NO (SITE CON) (Form:ASR): Create of new field - Site Contact Telephone Number – Identifies the telephone number of the Site Contact. • SITE EMAIL (Form: ASR): Creation of new field - Site contact Electronic Mail Address – Identifies the electronic mail address of the Site Contact. • GETO (Form: Transport, SES, EUSA): Addition of valid entry for ‘H’, modification of valid entries notes 4. • GETO (Form: MSL): Addition of valid entry for ‘F’ and ‘H’. • GBTN (Form:SES, EUSA): Modification of Usage Note 1 to add values of ‘F’ and ‘H’. • JK NUM (Form: SALI): Modification of Definition Note 1; When the jack identification is unknown, enter 99 in this field. • OTC (Form: EVC): Modification of Usage Note 1 to require when ASC-EC field on the ASR Form is populated.
|
Status History |
Date | Action | Description |
12/7/2016 | CR Submitted | CR Submitted for December meeting. |
12/8/2016 | CR Acknowledged | CR Acknowledged. |
12/14/2016 | Status Changed | Status changed to Presented. |
12/14/2016 | Discussed at Monthly CMP Meeting | Discussed in the December Systems CMP Meeting - See Attachment D in the Distribution Package. |
12/27/2016 | Status Changed | Status changed to Development. |
1/6/2017 | Communicator Issued | See notification number SYST.EASE.01.06.17.F.15225.EASE_ASR2.0DraftTechSpecs. |
1/16/2017 | Communicator Issued | See notification number SYST.EASE.01.16.17.F.15272.Second_EASE_R2.0Walkthru. |
1/16/2017 | General Meeting Held | Draft Technical Specifications walkthrough conducted. See Wholesale calendar for meeting minutes. |
1/18/2017 | General Meeting Held | Draft Technical Specifications walkthrough conducted. See Wholesale calendar for meeting minutes. |
1/18/2017 | Discussed at Monthly CMP Meeting | Discussed in the January Systems CMP Meeting - See Attachment J in the Distribution Package. |
2/3/2017 | Communicator Issued | See notification number SYST.EASE.02.03.17.F.15226.EASE_ASR2.0FinalTechSpecs. |
2/15/2017 | Discussed at Monthly CMP Meeting | Discussed in the February Systems CMP Meeting - See Attachment J in the Distribution Package. |
2/20/2017 | Communicator Issued | See notification number SYST.EASE.02.20.17.F.15351.EASE_GUI2.0_Drft_RelNotes. |
2/21/2017 | Communicator Issued | See notification number SYST.EASE.02.21.17.F.15372.EASEGUI2.0DrftRelNotesREV. |
2/27/2017 | Communicator Issued | See notification number SYST.EASE.02.27.17.F.15390.EASEGUI_2.0FNLRelDocs. |
3/2/2017 | Communicator Issued | See notification number SYST.EASE.03.02.17.F.15381.EASE_ASR2.0REVFnlTchSpcs. |
3/15/2017 | Discussed at Monthly CMP Meeting | Discussed in the March Systems CMP Meeting - See Attachment K in the Distribution Package. |
3/20/2017 | Status Changed | Status changed to CLEC Test. |
3/20/2017 | Communicator Issued | See notification number SYST.EASE.03.20.17.F.15432.ASR_EASE_R2DeplymtSuppDoc. |
4/19/2017 | Status Changed | Status changed to Completed. |
4/19/2017 | Discussed at Monthly CMP Meeting | Discussed in the April Systems CMP Meeting - See Attachment G in the Distribution Package. |
Project Meetings |
4/19/17 System CMP Meeting Mark Coyne – CenturyLink said this CR became effective on March 20, 2017 when the EASE Release 2.0 was installed. The CR is in CLEC Test. Mark said we would like to move this CR to a Completed Status and asked if there were any objections. There were none. 3/15/17 System CMP Meeting Mark Coyne – CenturyLink relayed that the EASE system Release 2.0 will be installed during the upcoming weekend and has a planned effective date of March 20, 2017. 2/15/17 System CMP Meeting Mark Coyne – CenturyLink said testing with CenturyLink for EASE Release 2.0 for this CR will be available February 18, 2017. The Draft GUI Release Notes will be posted for customer comment on February 20, 2017 and the Final GUI Release Notes will be issued February 27, 2017 with a planned effective date of March 20, 2017. 1/18/17 System CMP Meeting Mark Coyne – CenturyLink said this CR was presented by Letty Walker – CenturyLink in the December monthly meeting. The Draft Technical Specifications were issued January 6, 2017. There was a Draft Tech Spec walkthrough conducted on January 16 but with the holiday for some customers on that day, CenturyLink will be conducting an additional walkthrough later today, January 18. The EASE Release 2.0 effective date is March 20, 2017. 12/14/16 System CMP Meeting Letty Walker – CenturyLink presented this new CR for the EASE ASR gateway. Letty reviewed the new or changed fields and form changes included in the CR Description to support ASOG 54, including ASOG and UOM-ASR Schema changes, as mandated by ATIS-OBF. Kim Isaacs - Electric Lightwave asked what the date is for the EASE release. Letty Walker – CenturyLink said the release is scheduled to be effective the weekend of March 18, 2017. NOTE: The CenturyLink OSS Interface Release calendar shows the EASE Release 2.0 Production effective date as March 20, 2017.
|
CenturyLink Response |
|