Archived System CR SCR120503-01IG Detail |
Title: CABS BOS Version 41 | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR120503-01IG |
Completed 6/18/2004 |
1200 - 1800 | 11/ | Billing | All |
Originator: Larson, Jami |
Originator Company Name: Qwest Corporation |
Owner: Winston, Connie |
Director: |
CR PM: Esquibel-Reed, Peggy |
Description Of Change |
Implement Telcordia's CABS BOS Version 41 for bill and CSR data - IABS.
Expected Deliverable: 5/8/2004
|
Status History |
Date | Action | Description |
12/5/2003 | CR Submitted | |
12/8/2003 | CR Acknowledged | |
12/9/2003 | Clarification Meeting Held | |
1/22/2004 | Discussed at Monthly CMP Meeting | Discussed at the January Systems CMP Monthly Meeting; please see January Systems CMP Distribution Package, Attachment D |
2/19/2004 | Discussed at Monthly CMP Meeting | Discussed at the February Systems CMP Monthly Meeting; please see the February Systems CMP Distribution Package, Attachments H & J |
2/27/2004 | Communicator Issued | SYST.02.27.04.F.01393.IABS_Drft_Tech_Specs |
3/3/2004 | Qwest CR Review Meeting | Tech Spec Walk-Thru Held |
3/26/2004 | Communicator Issued | SYST.03.26.04.F.01506.IABSMayRel_Finaltechspecs |
4/22/2004 | Discussed at Monthly CMP Meeting | Discussed at the April Systems CMP Monthly Meeting; please see April Systems CMP Distribution Package, Attachment K |
5/11/2004 | Status Changed | Status Changed to CLEC Test due to May 10, 2004 Deployment. |
5/20/2004 | Discussed at Monthly CMP Meeting | Discussed at the May Systems CMP Monthly Meeting; please see May Systems CMP Distribution Package, Attachment G |
6/17/2004 | Discussed at Monthly CMP Meeting | Discussed at the June Systems CMP Monthly Meeting; please see June Systems CMP Distribution Package, Attachment G |
6/24/2004 | Communicator Issued | SYST.06.24.04.F.01818.BOSDiffListVers41&42Upd |
Project Meetings |
June 17, 2004 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that Qwest is ready to close this CR. Carla Pardee/AT&T stated that AT&T was agreeable to the CR closing. This CR moves to Completed Status.
- May 20, 2004 Systems CMP Meeting Discussion: Cheryl Peterson/AT&T stated that AT&T would like to leave this CR in CLEC Test for another month.
-- April 22, 2004 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR is scheduled to deploy on May 10, 2004. There were no questions or comments.
- March 3, 2004 Qwest/CLEC Walk-Thru Held: Attendees: Lynn Loftus-Qwest, Jami Larson-Qwest, Peggy Esquibel-Reed-Qwest There was no CLEC participation. The bridge was closed at 11:20 a.m. MT
-- February 19, 2004 Systems CMP Meeting Discussion Excerpt (Attachments H & J): Judy Schultz/Qwest stated that she wanted to provide an update to the funding approval process that was discussed in the January CMP Systems Meeting. Judy referred everyone to Attachment J in the Distribution Package. She stated that all CRs are being re-evaluated and must be approved. Judy said that CRs could not be scheduled without approval. Judy noted that the status of this CR is that it is being reviewed at the Qwest CEO level.
-- January Systems CMP Meeting Discussion: Jami Larson/Qwest reviewed the CR description. Lynn Notarianni/Qwest stated that this is a normal BOS upgrade and noted that the targeted implementation date is May 8, 2004. Jami Larson/Qwest stated that information is posted on the Wholesale web site, including where the system will be standard and where it will deviate. There were no questions or comments.
-- December 9, 2003 Clarification Meeting: Qwest understands the request to update the IABS bill/CSR BDT (bill data tape) record output to be compliant w/CABS-BOS Version 41.
|
CenturyLink Response |
REVISED DRAFT RESPONSE January 22, 2004 RE: SCR120503-01IG (CABS BOS Version 41) Qwest has reviewed the information submitted as part of Change Request SCR120503-01IG. Based upon the scope of this CR, Qwest is able to provide an estimated Level of Effort (LOE) of 1200 to 1800 hours for this Wholesale Billing Interface Change Request. Qwest has reviewed release schedules and development timetables and is targeting this Industry Guideline request, SCR120503-01IG, for deployment on May 8, 2004. Sincerely, Qwest
DRAFT RESPONSE January 9, 2004 RE: SCR120503-01IG CABS BOS Version 41 Qwest has reviewed the information submitted as part of Change Request SCR120503-01IG. Based upon research that has been conducted following the Clarification Meeting (held December 9, 2003) Qwest is still examining the issue. Qwest will continue to research the problem and provide an updated response at the January Systems CMP Meeting. At the January Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Qwest is interested in the experiences of the CMP community as relates to this issue. Qwest will incorporate any feedback received at the next Monthly Systems CMP Meeting into further evaluation of this Change Request. Sincerely, Qwest
|
Information Current as of 1/11/2021