Wholesale: Products & Services

Archived System CR SCR120409-1IG Detail

 
Title: ASOG 40 Industry Release/QORA and ASR Gateway Enhancements
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR120409-1IG Closed
4/21/2010
-   24/ Pre-Ordering
Originator: Whaples, Kim
Originator Company Name: Qwest Corporation
Owner: Whaples, Kim
Director:
CR PM: Lorence, Susan
Description Of Change
The QORA ASR Gateway application needs to be updated to support changes for ASOG 40, including ASOG, Mech Spec and UOM-ASR Schema changes as mandated by OBF.

Details of the ASOG 40 industry changes can be found at: http://www.atis.org/

Qwest Specific Edits: The following changes that are customer affecting are also being implemented.

New QORA Pre-Order Validations

No new edits for this release

New QORA GUI and ASR Gateway Validations

ECCKT Validation – The system will allow circuits that were built with 8-characters for both the A and Z locations and perform a busy check on all product specific forms for original submission of the ASR and SUP 3, 4. If the ECCKT is invalid the ASR will be rejected.

FACTL Validation – The system will validate the first 8 characters of the FACTL CLLI code on the Trunking Form matches the first 8 characters of the ACTL CLLI on the ASR form. If they do not match the ASR will be rejected.

PSL/CSL/PSLI Validation – The system will validate that the PSLI field is populated correctly based on the CSL and PSL LATAs. If the CSL and PSL are the same LATA then PSLI must = F, CSL and PSL are not in the same LATA then ASR.PSLI must = E. If the PSLI is incorrect the ASR will be rejected.

PSL Validation – The system will validate the PSL field is populated with a correct CLLI based on LERG6. If the PSL is incorrect, the ASR will be rejected

NPA/NXX for PSL Validation for End Office and Local Tandems– The system will validate that the NPA/NXX on the TQ form are valid for the PSL CLLI. If not, the ASR will be rejected.

TSC and ECCKT Validation – The system will validate that the TSC is valid for the ECCKT on the ASR form. If the TSC is invalid, the ASR will be rejected.

TCIC Validation – The existing TCIC validation will now run on SUP type 3 and 4.

QORA GUI Report enhancements

No new edits for this release

Upgrade for ASOG 40 industry related changes with additional edits to provide upfront editing and validation of ASR entries.

New options to be available in the QORA GUI March 20, 2010

Status History

Date Action Description
12/4/2009 CR Submitted CR Submitted 
12/4/2009 CR Acknowledged CR Acknowledged 
12/16/2009 Discussed at Monthly CMP Meeting Discussed in the December System meeting - See Attachment C in the Distribution Package 
1/8/2010 Communicator Issued System release notice issued - SYST.QORA.01.08.10.F.07407.QORARel15.0DftTchSpec 
1/8/2010 Status Changed Status changed to Development 
1/21/2010 Communicator Issued System notice issued with updated info and comment cycle extended SYST.QORA.01.21.10.F.07453.QORA15.0DraftGWTchSpcUpda 
2/5/2010 Communicator Issued Final Release Notice issued - See notice SYST.QORA.02.05.10.F.07517.QORA15.0FinalTechSpecs 
2/22/2010 Communicator Issued Draft GUI notice issued - see SYST.QORA.02.22.10.F.07566.QORAGUI_15.0_DraftRelDoc 
3/1/2010 Communicator Issued Final GUI release notice issued - see SYST.QORA.03.01.10.F.07567.QORAGUI_15.0_FNLRelDoc 
3/17/2010 Discussed at Monthly CMP Meeting Discussed at the March Monthly Systems CMP Meeting - See Attachment K in the Distribution Package 
3/20/2010 Status Changed Status Changed to CLEC test 
4/21/2010 Status Changed Status changed to Closed 
4/21/2010 Discussed at Monthly CMP Meeting Discussed at the April Systems CMP Meeting - See Attachment G in the Distribution Package 

Project Meetings

4/21/10 System CMP Meeting Mark Coyne – Qwest asked if there were any objections to closing this SCR that went in on March 20. There were none so Qwest will close this CR.

03/17/10 System CMP Meeting On the list for deployment prior to next CMP meeting.

01/20/10 System CMP Meeting Mindy Chapman – Neustar had a question on the QORA ASR Gateway Draft Tech specs listed on the OSS calendar. Mindy relayed that the info has not been received and that Neustar is trying to finalize the specifications. Mindy said the specs are one week late and they are needed to know what is changing in ASOG 40. Mark Coyne-Qwest said we would have an answer shortly. NOTE: System notice SYST.QORA.01.21.10.F.07453.QORA15.0DraftGWTchSpcUpda was sent on January 21 with the correct version of the QORA ASR Gateway Draft Tech specs. Qwest included an extension to the comment cycle.

12/16/09 System CMP Meeting Kim Whaples – Qwest presented this CR associated with the QORA ASR Gateway application to be updated to support changes for ASOG 40, including ASOG, Mech Spec and UOM-ASR Schema changes as mandated by OBF. Kim shared that the details of the ASOG 40 industry changes can be found at: http://www.atis.org/ . Kim identified that there are no new QORA Pre-Order Validations. The new QORA GUI and ASR Gateway Validations are: ECCKT Validation, FACTL Validation, PSL/CSL/PSLI Validation, PSL Validation, NPA/NXX for PSL Validation for End Office and Local Tandems, TSC and ECCKT Validation, and TCIC Validation. Kim relayed that the CR has the details listed about these validations. There is no new reporting associated with this CR for the release. The release install will occur March 19-21 with the planned effective date to be March 22, 2010. Kim relayed that Training information would be provided via a notification in January.

Bonnie Johnson – Integra questioned whether the training would be online or via phone.

Kim Whaples – Qwest identified that the training would be online plus a presentation.

Brenda Bloemke – Comcast questioned how long the training would take.

Kim Whaples – Qwest thought training would be approximately an hour.

CenturyLink Response

Information Current as of 1/11/2021