Description Of Change
As a standard practice with each CABS BOS version change, customers are sent test data 30 days prior to the change in production. The test data is sent either via NDM or tape cartridge (for those customers not set up for NDM).

Due to elimination of tape production, IABS will not longer be able to provide the test data for the CABS BOS version changes in a tape cartridge. Tape will not be offered to customers effective with CABS BOS Version 47, which will be implemented 3rd QTR 2007. In place of tape, customers will be provided the option to download the test data from web via Qwest’s QPID. Production data can currently be downloaded from the web via Qwest’s QPID.

Status History

Date Action Description
11/1/2006 CR Submitted  
11/2/2006 CR Acknowledged  
11/15/2006 Status Changed Status Changed to Presented 
11/30/2006 Discussed at Monthly CMP Meeting Discussed at the November Systems CMP Meeting - See Attachment D in the Distribution Package 
12/5/2006 Status Changed Status Changed to Evaluation to Determine if System Impacts or Cross Over to Product Process. 
12/14/2006 Discussed at Monthly CMP Meeting Discussed at the December Systems CMP Monthly Meeting; please see the December Systems CMP Distribution Package, Attachment I 
1/17/2007 Discussed at Monthly CMP Meeting Discussed at the January Systems CMP Monthly Meeting; please see the January Systems CMP Distribution Package, Attachment I 
3/9/2007 Communicator Issued PROS.03.09.07.F.04545.Billing_Info_IABS_V15 (Level 2) 
3/9/2007 Additional Information Phase 1 is to remove references to Magnetic Tape as an option in LSOG & PCAT. Effective Date 4/6/07 
3/9/2007 Additional Information Phase 2 is for the System Changes to allow downloading of test data via QPID. Targeted 9/15/07 
3/21/2007 Discussed at Monthly CMP Meeting Discussed at the March Systems CMP Monthly Meeting; please see the March Systems CMP Distribution Package, Attachments I & k 
9/15/2007 Status Changed Status Changed to CLEC Test Due to September 15, 2007 Deployment. 
9/19/2007 Discussed at Monthly CMP Meeting Discussed at the September Systems CMP Monthly Meeting; please see the September Systems CMP Distribution Package, Attachment G 
10/17/2007 Discussed at Monthly CMP Meeting Discussed at the October Systems CMP Monthly Meeting; please see theOctober Systems CMP Distribution Package, Attachment G 

Project Meetings

October 17, 2007 Systems CMP Meeting Discussion: Mark Coyne-Qwest stated that this request was implemented on September 15th, and it has been over a month. Mark stated that Qwest is looking to close this CR and asked if there were any objections to the closure. There were none. This CR moves to Completed status.

--

September 19, 2007 Systems CMP Meeting Discussion: Mark Coyne-Qwest stated that this was implemented on September 15th and is currently in CLEC Test. Mark stated that this would remain open until the October CMP Meeting.

March 21, 2007 Systems CMP Meeting Discussion: Peggy Esquibel Reed-Qwest stated that this CR was revised to also include production data. Peggy stated that the word “Test” was removed from the CR Title, that there was a verbiage change for the implementation from 4th Quarter 2007 to 3rd Quarter 2007, and that there was a sentence added in the CR Description in order to include Production Data. Peggy also noted that the CR now has 2 Phases. Phase 1 is to remove references to the magtape in PCAT, and is effective April 6, 2007. Phase 2 is to provide test data via QPID (production already utilizes QPID) and is targeted for September 15, 2007. Mark Coyne-Qwest stated that the Process piece of this CR is effective April 6th and that the systems portion would then be implemented in September.

- January 17, 2007 Monthly Systems CMP Meeting Discussion: Mark Coyne-Qwest stated that the Level of Effort for this CR is 300 to 450 hours. Mark then stated that the action item is closed. The CR is in presented Status.

- December 14, 2006 Monthly Systems CMP Meeting Discussion: Mark Coyne-Qwest stated that Qwest is still evaluating this request and that an LOE may be provided in the next few weeks. There were no questions or comments.

- 11/15/06 Systems CMP Meeting Mark Coyne-Qwest presented this CR on behalf of Jamie Larson (Qwest). He said that this CR is a standard practice with each CABS BOS version change, customers are sent test data 30 days prior to the change in production. The test data is sent either via NDM or tape cartridge (for those customers not set up for NDM). Mark said that due to elimination of tape production, IABS will no longer be able to provide the test data for the CABS BOS version changes in a tape cartridge. He said that the tape will not be offered to customers effective with CABS BOS Version 47, which will be implemented 4th QTR 2007. Mark said that in place of tape, customers will be provided the option to download the test data from web via Qwest’s QPID. Mark asked if there were any questions. There were no questions or comments brought forward. This CR will move to a Presented Status.

CenturyLink Response

REVISED RESPONSE

January 5, 2007

RE: SCR110106-01IG Provide Test Data for CABS BOS Version Changes via Webdata Media Option in IABS

Qwest has reviewed the information submitted as part of this Change Request and is able to provide an estimated Level of Effort (LOE) of 300 to 450 hours for this Wholesale Billing Change Request.

Qwest will review release schedules and development timetables in an effort to evaluate options for the potential scheduling of SCR110106-01IG.

Sincerely, Qwest Corporation

DRAFT RESPONSE

December 5, 2006

RE: SCR110106-01IG Provide Test Data for CABS BOS Version Changes via Webdata Media Option in IABS

Qwest has reviewed the information submitted as part of Change Request SCR110106-01IG. Based upon research that has been conducted, Qwest is still examining the issue in order to determine Systems impacts or if a cross over to Product Process is warranted. Qwest will continue to analyze this request and will provide an updated response at the next Systems CMP Meeting.

At the December Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Qwest is interested in the experiences of the CMP community as relates to this issue. Qwest will incorporate any feedback received at the next Monthly Systems CMP Meeting into further evaluation of this Change Request.

Sincerely, Qwest Corporation

Information Current as of 1/11/2021