Title: ASOG 28 TELIS Upgrade
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR103003-04IG Completed
5/20/2004
-   8/ Ordering All
Originator: Veik, Gary
Originator Company Name: Qwest Corporation
Owner: Winston, Connie
Director:
CR PM: Esquibel-Reed, Peggy
Description Of Change
The TELIS application needs to be updated to support ASOG 28 changes as mandated by OBF.

Draft Release Notes Issued will be January 9, 2004

Comment Cycle will start on January 9, 2004

Comment Cycle will end January 27, 2004

Final Release Notes will be Issued on February 6, 2004

Planned Release Production Date of March 22, 2004

Details of this release could be found at:

http://www.atis.org/atis/clc/obf/obfhom.htm

Expected Deliverable:

Upgrade TELIS Application to support ASOG 28 Changes. Implementation Date of 03/22/04

Status History

Date Action Description
10/30/2003 CR Submitted  
11/3/2003 CR Acknowledged  
11/3/2003 Clarification Meeting Scheduled  
11/5/2003 Clarification Meeting Held  
11/20/2003 Discussed at Monthly CMP Meeting Discussed at the November Systems CMP Monthly Meeting; please see November Systems CMP Distribution Package, Attachment D 
2/19/2004 Discussed at Monthly CMP Meeting Discussed at the February Systems CMP Monthly Meeting; please see the February Systems CMP Distribution Package, Attachments H & J 
2/23/2004 Communicator Issued SYST.02.23.04.F.01389.ASOG_28_TELIS_Drft_Rls_Nt 
3/1/2004 Communicator Issued SYST.03.01.04.F.01428.ASOG_28_TELIS_Fin_Rls_Nt 
3/18/2004 Discussed at Monthly CMP Meeting Discussed at the March Systems CMP Monthly Meeting; please see March Systems CMP Distribution Package, Attachments H & K 
3/22/2004 Status Changed Status Changed to CLEC Test due to the March 22, 2004 Deployment 
4/22/2004 Discussed at Monthly CMP Meeting Discussed at the April Systems CMP Monthly Meeting; please see April Systems CMP Distribution Package, Attachment G 
5/20/2004 Discussed at Monthly CMP Meeting Discussed at the May Systems CMP Monthly Meeting; please see May Systems CMP Distribution Package, Attachment G 

Project Meetings

May 20, 2004 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR can be closed.

April 22, 2004 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR just deployed on March 22nd and asked if there were any concerns. Liz Balvin/MCI asked that this remain open for another month. This CR remains in CLEC Test.

March 18, 2004 Systems CMP Meeting Discussion, in association with AI021904-03 Funding Approved CRs: Susie Bliss/Qwest provided status of an 3/22/04 Implementation Date. Connie Winston/Qwest stated that this CR is due to deploy on March 22, 2004. There were no questions or comments.

-- COMMUNICATOR ISSUED: Announcement Date: March 1, 2004 Effective Date: March 1, 2004 Notification Number: SYST.03.01.04.F.01428.ASOG28TELISFinRlsNt Notification Category: systems Notification Target Audience: CLECs, Resellers, IXCs Subject: CMP - ASOG 28 Release for TELIS - Final Release Notes Associated CR # or System Name and Number: SCR103003-04IG

The Qwest TELIS application will be enhanced to support ASOG 28 changes to conform to Industry Standards. These standards are set by the OBF Committee under the direction of ATIS. Information on this release can be found at http://www.atis.org/atis/clc/obf/obfhom.htm. The User Guide, as created and managed by Cap Gemini, and Ernst and Young can be found at: https://troom.tmn.cgey.com/telis/. When you input this URL into your browser you may receive a pop-up for a New Certificate. Continue through the pop-up to accept the New Certificate. When finished with this you will receive a log-in screen. The UserID is: telis Password: user The User Guide was available beginning February 23, 2004. Comment Cycle: There were no CLEC comments received, therefore there is no Qwest response to comments. If you have any questions on this subject, please submit comments through the following link: http://www.qwest.com/wholesale/cmp/comment.html.

Timeline: Final Release Notice: March 1, 2004 Targeted Release Production Date: March 22, 2004

Sincerely, Qwest

February 19, 2004 Systems CMP Meeting Discussion Excerpt (Attachments H & J): Judy Schultz/Qwest stated that she wanted to provide an update to the funding approval process that was discussed in the January CMP Systems Meeting. Judy referred everyone to Attachment J in the Distribution Package. She stated that all CRs are being re-evaluated and must be approved. Judy said that CRs could not be scheduled without approval. Judy noted that the status of this CR is: This CR has been Approved.

- November 20, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that the ASOG 28 TELIS Upgrade is also due to take place on March 22, 2004. There were no questions or comments. This CR was moved to Presented Status.

Clarification Meeting - November 5, 2003 ATTENDEES: Gary Veik/Qwest, Christy Turton/Qwest, Peggy Esquibel-Reed/Qwest REVIEW CR DESCRIPTION: The TELIS application needs to be updated to support ASOG 28 changes as mandated by OBF. Expected Deliverable is that Qwest will upgrade the TELIS Application to support ASOG 28 Changes, implementation Date of 03/22/04 Peggy Esquibel-Reed/Qwest asked Gary Veik (Qwest) for addition information/dates. Gary Veik/Qwest and Christy Turton/Qwest provided the information, targeted dates of: Draft Release Notes Issued will be January 9, 2004 Comment Cycle will start on January 9, 2004 Comment Cycle will end January 27, 2004 Final Release Notes will be Issued on February 6, 2004 Planned Release Production Date of March 22, 2004 Gary Veik/Qwest stated that details of this release could be found at: http://www.atis.org/atis/clc/obf/obfhom.htm Peggy Esquibel-Reed/Qwest agreed to revise the CR with the information. CONFIRM IMPACTED PRODUCTS: All CONFIRM IMPACTED INTERFACES: TELIS ACTION PLAN: This CR will be presented at the November Systems CMP Meeting

CenturyLink Response

November 6, 2003 Implementation Date: March 22, 2004

This is a Cap Gemini Ernst & Young development effort. Qwest will implement this change on August 5, 2002 to support the Industry Standards through OBF.

The changes to the UNIX-TELIS application as utilized by Qwest to support customer activity involving Access Service Requests are the result of decisions made at OBF (Ordering and Billing Forum). Details regarding field changes can be found in ASOG 28 (Access Service Ordering Guide). This can be found at the http://www.atis.org/atis/clc/obf/obfdocs.htm website.

Details involving the use of TELIS (TELIS User Manual) can be obtained from the Cap Gemini, Ernst & Young Website at http://vroom.capgemini.fr. You must be an existing TELIS user in order to acquire the information regarding this release.

Qwest, under agreement with ATIS (Alliance for Telecommunication Industry Solutions), cannot provide the ASOG document directly to our customers. All standards document associated with the ASR must be obtained from ATIS.

Information Current as of 1/11/2021