Archived System CR SCR103003-02IG Detail |
Title: ASOG 28 QORA Upgrade | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR103003-02IG |
Completed 4/22/2004 |
- | 24/ | Ordering | All |
Originator: Veik, Gary |
Originator Company Name: Qwest Corporation |
Owner: Winston, Connie |
Director: |
CR PM: Esquibel-Reed, Peggy |
Description Of Change |
The QORA application needs to be updated to support ASOG 28 changes as mandated by OBF.
Draft Release Notes Issued will be January 9, 2004 Comment Cycle will start on January 9, 2004 Comment Cycle will end January 27, 2004 Final Release Notes will be Issued on February 6, 2004 Planned Release Production Date of March 22, 2004
Details of this release could be found at: http://www.atis.org/atis/clc/obf/obfhom.htm
Expected Deliverable: Upgrade QORA Application to support ASOG 28 Changes. Implementation Date of 03/22/04
|
Status History |
Date | Action | Description |
10/30/2003 | CR Submitted | |
11/3/2003 | CR Acknowledged | |
11/3/2003 | Clarification Meeting Scheduled | |
11/5/2003 | Clarification Meeting Held | |
11/20/2003 | Discussed at Monthly CMP Meeting | Discussed at the November Systems CMP Monthly Meeting; please see November Systems CMP Distribution Package, Attachment D |
1/9/2004 | Communicator Issued | SYST.01.09.04.F.01228.ASR_Draft_Tech_Specs |
2/19/2004 | Discussed at Monthly CMP Meeting | Discussed at the February Systems CMP Monthly Meeting; please see the February Systems CMP Distribution Package, Attachments H & J |
3/18/2004 | Discussed at Monthly CMP Meeting | Discussed at the March Systems CMP Monthly Meeting; please see March Systems CMP Distribution Package, Attachment H |
3/22/2004 | Status Changed | Status Changed to CLEC Test due to the March 22, 2004 Deployment |
4/22/2004 | Discussed at Monthly CMP Meeting | Discussed at the April Systems CMP Monthly Meeting; please see April Systems CMP Distribution Package, Attachment G |
Project Meetings |
April 22, 2004 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR deployed on March 22nd and Qwest is okay to close it. Connie asked if there were any concerns for this CR. There was no dissent to close. This CR moves to Completed Status.
March 18, 2004 Systems CMP Meeting Discussion, in association with AI021904-03 Funding Approved CRs: Susie Bliss/Qwest provided status of an 3/22/04 Implementation Date.
- February 19, 2004 Systems CMP Meeting Discussion Excerpt (Attachments H & J): Judy Schultz/Qwest stated that she wanted to provide an update to the funding approval process that was discussed in the January CMP Systems Meeting. Judy referred everyone to Attachment J in the Distribution Package. She stated that all CRs are being re-evaluated and must be approved. Judy said that CRs could not be scheduled without approval. Judy noted that the status of this CR is: This CR has been Approved.
- November 20, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that the ASOG 28 QORA Upgrade is due to take place on March 22, 2004. There were no questions or comments. This CR was moved to Presented Status.
Clarification Meeting - November 5, 2003 ATTENDEES: Gary Veik/Qwest, Christy Turton/Qwest, Peggy Esquibel-Reed/Qwest REVIEW CR DESCRIPTION: Peggy Esquibel-Reed/Qwest reviewed the CR description, as stated on the submitted CR: The QORA application needs to be updated to support ASOG 28 changes as mandated by OBF. Expected Deliverable is that Qwest will upgrade the QORA Application to support ASOG 28 Changes, implementation date of 03/22/04. Peggy Esquibel-Reed/Qwest asked Gary Veik (Qwest) for addition information/dates. Gary Veik/Qwest and Christy Turton/Qwest provided the information, targeted dates of: Draft Release Notes Issued will be January 9, 2004 Comment Cycle will start on January 9, 2004 Comment Cycle will end January 27, 2004 Final Release Notes will be Issued on February 6, 2004 Planned Release Production Date of March 22, 2004 Gary Veik/Qwest stated that details of this release could be found at: http://www.atis.org/atis/clc/obf/obfhom.htm Peggy Esquibel-Reed/Qwest agreed to revise the CR with the information. CONFIRM IMPACTED PRODUCTS: All CONFIRM IMPACTED INTERFACES: QORA ACTION PLAN: This CR will be presented at the November Systems CMP Meeting
|
CenturyLink Response |
Draft Response November 6, 2003 This is a Telcordia development effort. Qwest will implement this change on March 22, 2004 to support the Industry Standards through OBF. Information is available on the OBF website (http://www.atis.org) for use by all interested parties. Sincerely, Qwest
|
Information Current as of 1/11/2021