Wholesale: Products & Services

Archived System CR SCR102209-1EX Detail

 
Title: IMA V25 in Production Support
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR102209-1EX Denied
11/18/2009
-   3/ Pre-Order and Ordering
Originator: Burley, David
Originator Company Name: Verizon Business
Owner: Stecklein, Lynn
Director:
CR PM:
Description Of Change
IMA v25 is scheduled to be sunset 4/10/10. Verizon Business is requesting that IMA v25 continue to be supported for an additional 30 calendar days (May 16, 2010). Verizon Business would like to upgrade from IMA v25 (our current OSS interface version) to IMA v27 in late April or early May 2010.

Status History

Date Action Description
10/22/2009 CR Submitted CR Submitted 
10/23/2009 CR Acknowledged CR Acknowledged 
11/18/2009 Discussed at Monthly CMP Meeting Discussed at the November Systems CMP Meeting - See attachment C in the distribution package 
11/18/2009 Status Changed Status changed to Denied 

Project Meetings

11/18/09 Systems CMP meeting

Dave Burley-Verizon Business said they are requesting that IMA v25 continue to be supported for an additional 30 calendar days (May 16, 2010). Verizon Business would like to upgrade from IMA v25 (our current OSS interface version) to IMA v27 in late April or early May 2010. There are requesting this so that it fits into their 2010 planning. Lynn Stecklein-Qwest conducted the vote for this request. A vote of 'Yes' will indicate a preference that IMA 25.0 continue to be supported for an additional 30 calendar days (From April 10, 2010 to May 16, 2010) A vote of 'No' will indicate a preference that IMA 25.0 NOT be extended an additional 30 calendar days (From April 10, 2010 to May 16, 2010) Section 16.4 of the CMP document, this vote will be held to a unanimous standard because the request seeks a change to the established CMP timelines for a Qwest originated systems timeline change. E-mail votes received: Integra, Comcast, Home Town Solutions, tw telecom, PAETEC – All voted Yes Velocity Telephone and Liberty Bell Telecom – Abstained Lynn asked if anyone else on the bridge wanted to cast their vote. Verizon Business – Yes Covad – Yes Qwest - No. Bonnie Johnson-Integra asked why Qwest voted No. Dawn Beck-Qwest said that due to resource constraints, Qwest can’t support the extension of IMA 25.0. Lynn Stecklein-Qwest said as stated earlier, a unanimous vote was required, therefore, this request will not be granted. A vote disposition will be sent within 5 days. 11/24/09 Comments received from Jim Hickle, Velocity Telephone Inc. Please add the following comments to the meeting minutes for this CMP Vote and send to all participants: The result of this vote is the type of vote results that makes the entire CMP process look like a complete waste of time for all concerned. A true wholesale provider would have found a way to work with its wholesale customer rather than being the ONLY entity to vote no and responding with a short and non-responsive “due to resource restraints” as you did. A compromise by both parties would have been appropriate or at least a response that Verizon would have the option to provide reasonable compensation to Qwest for requesting the delay would have been more appropriate.

CenturyLink Response

Information Current as of 1/11/2021