Wholesale: Products & Services

Archived System CR SCR100101-2 Detail

 
Title: Flow through indicator on FOCs.
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR100101-2 Completed
7/18/2002
-   3/10 Unbundled Loop, UNE-P
Originator: Dickinson Pardee, Carla
Originator Company Name: AT&T
Owner: Winston, Connie
Director:
CR PM: Esquibel-Reed, Peggy
Description Of Change
Currently Qwest does not have a flow through indicator on Firm Order Completion notices. (FOCs). It would be helpful for CLECs to know whether an order flows through or falls out for manual handling.

Status History

Date Action Description
10/1/2001 Info Sent to CLEC Sent Updated CR to Donna Osborne-Miller, Tim Bessey and Lydell Peterson 
10/1/2001 CR Submitted CR was received, and logged. This CR will be presented at the Oct. Systems CMP meeting by AT&T 
10/8/2001 Clarification Meeting Scheduled Qwest received email from Carla asking for meeting to be rescheduled due to an unexpected mandatory AT&T meeting. 
10/12/2001 Clarification Meeting Held Clarification Meeting Held (see minutes) 
10/18/2001 Discussed at Monthly CMP Meeting Presented and discussed at the October CMP Meeting (see minutes) 
10/25/2001 Status Changed Prioritization list sent to all CLECs for IMA 10.0 ranking, status changed to prioritization 
10/29/2001 Draft Response Issued Draft response posted to CMP database 
10/31/2001 Release Ranking Ranking for Release 10.0 occurred at October, 2001 CMP Meeting. SCR100101-2 ranked 19 
11/15/2001 Discussed at Monthly CMP Meeting Discussed at November CMP Meeting. 
1/17/2002 Discussed at Monthly CMP Meeting CR # SCR100101-2 discussed during 10.0 Packaging Presentation 
1/17/2002 Status Changed CR # SCR100101-2 status updated to 'Packaged' for 10.0 
3/13/2002 Status Changed Status updated from 'Packaged' to 'Development 
3/21/2002 Discussed at Monthly CMP Meeting SCR100101-2 discussed at March Systems CMP Monthly meeting during IMA Release 10.0 Commitment Discussion (Attachment I) 
6/20/2002 Discussed at Monthly CMP Meeting SCR100101-2 discussed at June Systems CMP Monthly meeting; please see Systems CMP Distribution Package June CMP -- Attachment N 
6/20/2002 Discussed at Monthly CMP Meeting SCR100101-2 discussed at June Systems CMP Monthly meeting; please see Systems CMP Distribution Package July CMP -- Attachment G 
6/25/2002 Status Changed Status updated to CLEC Test based upon discussion at June Systems CMP Meeting and IMA 10.0 Deployment on June 17, 2002 
7/18/2002 Discussed at Monthly CMP Meeting SCR100101-2 discussed at July Systems CMP Monthly meeting; please see Systems CMP Distribution Package July CMP -- Attachment G 

Project Meetings

July 18, 2002 CMP Meeting Discussion: This CR was completed with the IMA 10.0 Release. No CMP participants disagreed with the proposal to update this CR to Completed.

11/15/01 November CMP Discussion: Connie clarified that the request was for did it flow through or was it flow through eligible. CLEC's advised request was for did it flow through. Connie will get the definition corrected. Connie & Jeff advised that due to the low ranking from the vote, this may not make 10.0 but would be back on the list for 11.0 or could be a spillover for a point release.

Alignment/Clarification Meeting 10:00 a.m. (MDT) / Friday 12th August 2001

Attendees: Carla Dickinson Pardee / AT&T Joseph J. Bradley / Qwest Peggy Esquibel-Reed / Qwest Melva Harris / Qwest Shon Higer / Qwest

AT&T requesting a yes/no indicator on flow through to identify if FOC was Flow Through eligible. Requesting only for original FOC, not for subsequent FOCs. Interfaces - IMA Deliverables - Provide a yes/no indicator on flow through to identify if an original FOC was flow through eligible.

10/18/01 - Discussed at the October CMP Meeting. AT&T is requesting a non-standard (per OBF) indicator to identify if FOC was Flow Through eligible. No questions from the CLEC community. Level of Effort is medium.

CenturyLink Response

Discussion at November CMP Meeting DRAFT RESPONSE October 29, 2001

Carla Dickinson Pardee Manager - LSAM A T & T

CC: Connie Winston John I Gallegos Joseph J. Bradley Shon Higer Melva Harris

This letter is in response to your CLEC Change Request Form, number SCR100101-2, dated October 1, 2001, CR Title: Flow Through Indicator on FOCs.

CR Description: Currently Qwest does not have a flow through indicator on Firm Order Completion notices (FOCs). It would be helpful for CLECs to know whether an order flows through or falls out for manual handling.

Additional clarification was received from Carla in the Clarification Meeting that was held on October 12, 2001. AT&T is requesting a yes/no indicator on flow through to identify if the FOC was flow through eligible. This request is only for the original FOC, not for subsequent FOCs.

Qwest Response: Based on the information from the Clarification meeting, the level of effort for this request is medium. This CR is an eligible voting candidate for Release 10.0.

Sincerely, John I. Gallegos Information Technologies Manager

Information Current as of 1/11/2021