Archived System CR SCR090606-01 Detail |
Title: Retirement of IMA EDI | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR090606-01 |
Completed 11/14/2007 |
- | 2/ | Preordering, Ordering | All IMA Products |
Originator: McKenzie, Carol |
Originator Company Name: Qwest Corporation |
Owner: McKenzie, Carol |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
Qwest will be retiring the existing IMA EDI interface on October 27, 2007. As an alternative option for submitting electronic Local Service Requests, Qwest is introducing a new XML application to application interface. Qwest is providing a window of time (greater than 12 months) from the deployment of the IMA XML interface until the retirement of IMA EDI to allow adequate time for IMA EDI CLECs to migrate to the XML interface. During December of 2005, Qwest introduced SCR121305-01, Implement XML Interface for IMA EDI that will be implemented in Production with the IMA 20.0 release scheduled to deploy on October 16, 2006. The new IMA XML interface will simplify versioning and reduce development costs.
With the retirement of IMA EDI, remaining references to IMA EDI will be removed from the Qwest Operations Support System (OSS) Release Calendar. Other related Wholesale web documentation will be updated following the appropriate CMP notification process.
Expected Deliverables/Proposed Implementation Date (if applicable): Retirement of IMA EDI will occur more than two hundred and seventy (270) days after the submission this SCR. Qwest will provide a two hundred and seventy (270) day Initial Retirement notification announcing the retirement of IMA EDI, a two hundred twenty eight (228) day Final Retirement Notification including responses to CLEC comments, and a thirty (30) day confirmation systems notification of the retirement announcing IMA EDI’s discontinued availability.
Timeline: *Issue Initial Retirement Notification and Retirement Plan - January 30, 2007 *CLEC Comment Cycle begins - January 30, 2007 *CLEC Comment Cycle ends - 5:00 p.m. MST, February 14, 2007 *Final Notification issued - March 13, 2007 *Courtesy Reminder Notice Issued - September 27, 2007 *Targeted Retirement Date - October 27, 2007
|
Status History |
Date | Action | Description |
9/6/2006 | CR Submitted | |
9/7/2006 | CR Acknowledged | |
9/11/2006 | Status Changed | Status changed to clarification |
9/11/2006 | Clarification Meeting Held | |
9/20/2006 | Status Changed | Status changed to Presented |
9/20/2006 | Discussed at Monthly CMP Meeting | Discussed in the September systems CMP Meeting - See attachment C in the distribution package |
1/31/2007 | Communicator Issued | SYST.01.30.07.F.04499.IMAEDIRetireInitPlan |
3/14/2007 | Communicator Issued | SYST.03.13.07.F.04579.FNL_NoticeIMAEDIRetiremt |
9/27/2007 | Communicator Issued | SYST.09.27.07.F.04936.IMAEDIRetireCourtesyNotc |
9/28/2007 | Status Changed | Status changed to Development |
10/17/2007 | Discussed at Monthly CMP Meeting | Discussed at the October Systems CMP Meeting - See Attachment K in the Distribution Package |
11/1/2007 | Status Changed | Status changed to CLEC Test |
11/14/2007 | Status Changed | Status changed to Completed |
11/14/2007 | Discussed at Monthly CMP Meeting | Discussed at the November Monthly CMP Systems Meeting - See Attachment G in the Distribution Package |
6/17/2008 | Communicator Issued | PROS.06.17.08.F.05413.OSSElectronicAccessV48 |
Project Meetings |
11/14/07 Sytems CMP Meeting Susan Lorence-Qwest stated that this CR was implemented on 10/27/07 and asked if there was any objection to the closure of this CR. This CR will move to a Completed status. 10/17/07 Sytems CMP Meeting Mark Coyne-Qwest reviewed the following change requests and associated implementation dates. SCR090606-01 Retirement of IMA EDI - Implementation Date - 10/27/07 9/20/06 Systems CMP Meeting Carol McKenzie-Qwest stated that Qwest will be retiring the existing IMA EDI interface on October 27, 2007. As an alternative option for submitting electronic Local Service Requests, Qwest is introducing a new XML application to application interface. Qwest is providing a window of time (greater than 12 months) from the deployment of the IMA XML interface until the retirement of IMA EDI to allow adequate time for IMA EDI CLECs to migrate to the XML interface. Carol said that with the retirement of IMA EDI, remaining references to IMA EDI will be removed from the Qwest Operations Support System (OSS) Release Calendar and other related Wholesale web documentation will be updated following the appropriate CMP notification process. Carol said that the Retirement of IMA EDI will occur more than two hundred and seventy (270) days after the submission of this SCR. She said Qwest will provide a two hundred and seventy (270) day Initial Retirement notification announcing the retirement of IMA EDI, a two hundred twenty eight (228) day Final Retirement Notification including responses to CLEC comments, and a thirty (30) day confirmation systems notification of the retirement announcing IMA EDI’s discontinued availability. Carol asked if there were any questions. There were no questions. 9/11/06 Clarification Meeting Attendees: Carol Mckenzie - Qwest, Lynn Stecklein - Qwest Qwest will be retiring the existing IMA EDI interface on October 27, 2007. As an alternative option for submitting electronic Local Service Requests, Qwest is introducing a new XML application to application interface. Qwest is providing a window of time (greater than 12 months) from the deployment of the IMA XML interface until the retirement of IMA EDI to allow adequate time for IMA EDI CLECs to migrate to the XML interface. During December of 2005, Qwest introduced SCR121305-01, Implement XML Interface for IMA EDI that will be implemented in Production with the IMA 20.0 release scheduled to deploy on October 16, 2006. The new IMA XML interface will simplify versioning and reduce development costs.
|
CenturyLink Response |
|
Information Current as of 1/11/2021