Archived System CR SCR082806-02 Detail |
Title: User Activity Report for CEMR (See Original CR SCR082806 01) | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR082806-02 |
Completed 4/18/2007 |
300 - 450 | 5/ |
Originator: Hines, LeiLani |
Originator Company Name: Verizon Business |
Owner: Coyne, Mark |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
Verizon Business IT does a system application audit for all applications we support on a monthly basis. If a user has not logged on to the system in 30 days, the user profile is set to inactive and if not logged on in 90days, the profile is deleted automatically. We would like to receive user activity reports from Qwest to assist us in user management
|
Status History |
Date | Action | Description |
8/28/2006 | CR Submitted | |
8/28/2006 | CR Acknowledged | |
9/7/2006 | Clarification Meeting Held | |
10/19/2006 | Status Changed | |
10/24/2006 | Status Changed | Status changed to evaluation |
10/24/2006 | Additional Information | This CR was created to separate IMA and CEMR Systems (See original CR - SCR082806-01) |
11/2/2006 | Status Changed | Status changed to Presented |
11/17/2006 | Discussed at Monthly CMP Meeting | Discussed at the November Systems CMP Meeting - See Attachment I in the Distribution Package |
2/9/2007 | Status Changed | Status changed to Development |
2/21/2007 | Discussed at Monthly CMP Meeting | Discussed at the February Systems CMP Meeting - See Attachment I in the Distribution Package |
3/5/2007 | Communicator Issued | SYST.03.02.07.F.04543.CEMR_Rel_Draft_Rel_Notes |
3/28/2007 | Communicator Issued | SYST.03.28.07.F.04599.CEMR_FNLRelAnn_Onl_Hlp |
4/3/2007 | Discussed at Monthly CMP Meeting | Discussed at the March Systems CMP Meeting - See Attachment K in the Distribution Package |
4/11/2007 | Status Changed | Status changed to CLEC Test |
4/18/2007 | Status Changed | Status changed to Completed |
4/18/2007 | Discussed at Monthly CMP Meeting | Discussed at the April Systems CMP Meeting - See Attachment G in the Distribution Package |
Project Meetings |
4/18/07 Systems CMP Meeting Mark Coyne-Qwest stated that this request was completed on 4/1/07 and asked if there was any objection in closing this CR. There were no objections. 2/21/07 Systems CMP Meeting Mark Coyne-Qwest stated that the implementation date of this Verizon Business CR is 4/01/07. 11/15/06 Systems CMP Meeting Mark Coyne-Qwest stated that the LOE for this CR is 300 to 450 hours and that this action item will be closed. 10/17/06 Systems CMP Meeting Susan Lorence-Qwest stated that this CR is in an evaluation status. She said that Qwest will provide a response in the November CMP Systems Meeting 9/20/06 Systems CMP Meeting Leilani Hines-Verizon Business stated that this request is asking for a user report that will determine which users have been accessing these systems or not. She said that after 30 days, if the user has not accessed the system, the user profile is made inactive. She said that in 90 days, the profile gets deleted. Leilani said that they had the clarification call last week and was told that this type of report already exists for CEMR. She said that per Steve Kast (Service Manager) that after researching this report that it does not exist. She said they are requesting this report for IMA, CEMR and HEET. Mark Coyne-Qwest stated that we will provide a response in the October Meeting. Bonnie Johnson-Eschelon asked if Qwest is still posting clarification meetings on the CMP calendar. Lynn Stecklein-Qwest said that we are but that sometimes it becomes a timing issue. She said that the CRPMs will start posting the clarification meetings immediately instead of weekly. Steph Prull-Eschelon asked if some type of flag could be sent to notify them when the calendar has been updated. (9/27/06 - Comments to minutes received from Eschelon - Qwest agreed to take that idea back to review. Bonnie Johnson-Eschelon stated that they would check the calendar daily. 9/11/06 Clarification Meeting Attendees: Pat Webb - Verizon Business, LeiLani Hines - Verizon Business, Kim Snagley - Verizon Business, Denise Martinez - Qwest, Carol McKenzie - Qwest, Chuck Anderson - Qwest, Randy Owen - Qwest, Travis Horton - Qwest, Connie Overly - Qwest, Lynn Stecklein - Qwest Review Description of Change Lynn Stecklein - Qwest stated that Verizon Business IT does a system application audit for all applications we support on a monthly basis. If a user has not logged on to the system in 30 days, the user profile is set to inactive and if not logged on in 90days, the profile is deleted automatically. Verizon Business would like to receive user activity reports from Qwest to assist us in user management. Discussion Lynn Stecklein - Qwest summarized the discussion from the clarification meeting held 9/7/06. She said that CEMR provides usage reports that are available and could be requested throught their service manager. She said that these reports identified all users who have logged into CEMR and are sent out weekly. LeiLani Hines - Verizon Business stated that their service manager , Steve Kast (Qwest) advised that these reports were not available and to issue the CMP CR. She said that she would talk with him again regarding the CEMR report to determine if that would meeting their needs. She said that if it met their needs, she would revise the CR to exclude the request for CEMR. Connie Overly - Qwest that HEET is the Held Escalated Expedite Tool and allows customers to access the Web to obtain a current status on service orders that have delayed due facility shortages or other issues. She said that there is no existing user activity report. Lynn Stecklein - Qwest stated that Qwest will need to review this CR internally to be determine if this request can be met. Establish Action Plan Lynn Stecklein - Qwest stated that this request will be presented by Verizon Business in the September 20th Systems CMP Meeting. 9/7/06 Clarification Meeting Attendees: Pat Webb - Verizon Business, Denise Martinez - Qwest, Dawn Pak - Qwest, Carol McKenzie - Qwest, Arun Rajendiran - Qwest, Chuck Anderson - Qwest, Jamal Boudhaouia - Qwest, Randy Owen - Qwest, Marla Jones - Qwest, Justin Sewell - Qwest, Lynn Stecklein - Qwest Review Description of Change Lynn Stecklein - Qwest stated that Verizon Business IT does a system application audit for all applications we support on a monthly basis. If a user has not logged on to the system in 30 days, the user profile is set to inactive and if not logged on in 90days, the profile is deleted automatically. Verizon Business would like to receive user activity reports from Qwest to assist us in user management. Discussion Justin Sewell - Qwest asked if Verizon Business was looking for a report that would show users that have logged into the system to track business functions. Pat Webb - Verizon Business stated that they were looking for a user activity report. She said that the SMEs from Verizon Business needed to be on this call but could not be reached Cathy Garcia - Qwest stated that usage reports for CEMR are available and could be requested throught their service manager. She said that these reports identified all users who have logged into CEMR and are sent out weekly. Denise Martinez - Qwest stated that she was not aware of any usage reports that existed for IMA or HEET and that IMA would have to make changes to accommodate this request. Lynn Stecklein - Qwest stated that the resource for HEET could not attend this meeting. She said that another meeting would be scheduled to further discuss this request.
|
CenturyLink Response |
Response October 31, 2006 RE: SCR082806-01 User Activity Report for CEMR Qwest has reviewed the information submitted as part of Change Request (SCR082806-02). Based upon the scope of this CR, Qwest is able to provide an estimated Level of Effort (LOE) of 300 to 450 hours for this CEMR Change Request. At the next Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest's further evaluation of this Change Request. Sincerely, Qwest
|