Archived System CR SCR081203-01 Detail

 
Title: Resale Page Conditional
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR081203-01 Completed
12/12/2007
1468 - 2490   3/22 Ordering, Provisioning UNE-P, Centrex, Resale
Originator: Prull, Stephanie
Originator Company Name: McLeodUSA
Owner: Coyne, Mark
Director:
CR PM: Stecklein, Lynn
Description Of Change
Mcleod requests a change that would make the resale page conditional when not needed. Example: Currently if the only need is to change a hunt sequence and not change the USOCs involved the CLEC must input unnecessary information on that page to meet the system requirements.

Expected deliveryable:

Mcleod is requesting that the resale page become conditional to support the business needs of Qwest and the CLECs without causing unnecessary or bogus information from being sent. Mcleod request this be implemented with an IMA release.

Status History

Date Action Description
8/12/2003 CR Submitted  
8/13/2003 CR Acknowledged  
8/14/2003 CR Posted to Web  
8/20/2003 Clarification Meeting Held  
8/20/2003 Status Changed Status changed to clarification 
9/10/2003 Draft Response Issued  
9/10/2003 Status Changed Status changed to evaluation 
9/17/2003 LOE Issued  
9/17/2003 Status Changed Status changed to presented 
9/18/2003 Discussed at Monthly CMP Meeting Discussed at Sept CMP Systems Meeting - See Attachment B 
2/4/2004 Release Ranking 16.0 Prioritization- Ranked #25 out of 50 
3/1/2004 Release Ranking IMA 16.0 Revised Prioritization, Late Adder Ranking - #26 out of 51 
8/3/2004 Release Ranking 17.0 Prioritization- Ranked #18 out of 41 
7/7/2005 Additional Information QPP will benefit with the implementation of this CR 
8/1/2005 Release Ranking 19.0 Prioritization- Ranked #15 out of 26 
2/27/2006 Release Ranking 20.0 Prioritization- Ranked #16 out of 21 
7/7/2006 Status Changed Status Changed to Pending Prioritization, for 21.0 Release. 
11/27/2006 Release Ranking IMA 21.0 Late Adder Ranking - #19 out of 20 
4/2/2007 Release Ranking IMA 22.0 Prioritization- Ranked #07 out of 18 
7/18/2007 Status Changed Status changed to packaged 
10/29/2007 Discussed at Monthly CMP Meeting Discussed at the October Systems CMP Meeting - See Attachment K in the Distribution Package 
11/14/2007 Status Changed Status changed to CLEC Test 
11/14/2007 Discussed at Monthly CMP Meeting Discussed at the November Systems CMP Meeting - See Attachment K in the Distribution Package 
12/12/2007 Discussed at Monthly CMP Meeting Discussed at the December CMP Monthly Meeting - See Attachment G in the Distribution Package 
12/13/2007 Status Changed Status changed to Completed 

Project Meetings

11/14/07 Sytstems CMP Meeting

Susan Lorence-Qwest stated that the following CRs would move to a CLEC Test status by the end of the week - Implementation Date 11/12/07

10/17/07 Systems CMP Meeting

Mark Coyne-Qwest reviewed the following change requests and associated implementation dates. SCR081203-01 Resale Page Conditional (originated by McLeod USA) - Implementation Date- 11/12/07

2/16/05 CMP Systems Meeting - IMA 18.0 Candidate List Discussion

There was no discussion on this CR.

7/22/04 CMP Systems Meeting Jill Martain/Qwest stated that Qwest would distribute the ballot on July 27th, it is due back to Qwest on July 30th, and Qwest would email the initial prioritization list to the CLECs on August 3rd. There were no questions.

The CR Originator was not on the conference bridge. There were no questions.

September 18, 2003 CMP Systems Meeting

Stephanie Prull/McLeod reviewed the CR description. McLeod is requesting a change that would make the resale page conditional when it is not needed. Stephanie provided an example of a change to a hunt sequence and not changing the USOCs involved. The CLEC is required to input unnecessary information on that page to meet the requirement. Connie Winston/Qwest stated that the LOE is 1700 to 2100 hours and is available for the next vote. The status of this CR will be changed to presented.

August 20, 2003 Clarification Meeting

Meeting attendees: Donna Osborne-Miller-AT&T, Stephanie Prull-McLeod, Liz Balvin-MCI, Bonnie Johnson-Eschelon, John Gallegos-Qwest, Mallory Paxton-Qwest, Laurel Nolan- CRPM Qwest

Description of change: Nolan-Qwest reviewed the stated title, description of change, and the expected deliverable. She asked Prull-Mcleod if there were any changes to this. Prull stated that there were not. Paxton-Qwest asked about the product set that this would apply to. Prull stated that anything that had a resale page would be within scope. Paxton-Qwest stated that it would be UNE-P and POTS Centrex, PBX, and resale. Gallegos-Qwest asked if Prull-McLeod had examples other than hunting. Prull-McLeod stated Directory Listings. She ctoninued that it was LNA and doesn't need to be C. Paxton-Qwest asked if it applied why trying to convert and the CLEC didn't have a CSR yet. She stated that Qwest experience an issue with IMA wanting a trunk number, but it wasn't needed on the order.

Nolan-Qwest stated the products and asked if there were any changes to the interface.

CenturyLink Response

DRAFT RESPONSE September 17, 2003 RE: SCR081203-01

Qwest has reviewed the information submitted as part of Change Request SCR081203-01. Based upon the scope of this CR as agreed to in the Clarification Meeting (held August 20, 2003) Qwest is able to provide an estimated Level of Effort (LOE) of 1700 to 2100 hours for this IMA Change Request and SATE impacts of 0.

At theSeptember Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request.

This Change Request is eligible for the IMA 16.0 Prioritization.

Sincerely, Qwest

DRAFT RESPONSE September 10, 2003 RE: SCR081203-01

Qwest has reviewed the information submitted as part of McLeod's Change Request SCR081203-01. Based upon research that has been conducted following the Clarification meeting (held August 20, 2003) Qwest is still examining the issue. Qwest will continue to research the problem and provide an updated response at the September Systems CMP Meeting.

At the September Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Qwest is interested in the experiences of the CMP community as relates to this issue. Qwest will incorporate any feedback received into further evaluation of this Change Request.

Sincerely, Qwest

Information Current as of 1/11/2021