Archived System CR SCR071309-1 Detail |
Title: Malheur entity consolidation into Qwest Corp. | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR071309-1 |
Completed 1/20/2010 |
- | 1/ | Pre-Order, Ordering, Provisioning | ANC, AIN, DA, Opr Svcs, CTX, Collo, LNP, PLT, Resale, Switched, UDIT, UBL, UNE, LIS/Interconnect |
Originator: Van Dusen, Janean |
Originator Company Name: Qwest Corporation |
Owner: Van Dusen, Janean |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
Qwest will be consolidating Malheur entity into Qwest Corp. IMA edits associated with Malheur will be eliminated and GUI drop down menu for address check updated to include MAL.
Expected Deliverables/Proposed Implementation Date: Disclosed in October 19, 2009 release but will not be implemented until December 14, 2009.
|
Status History |
Date | Action | Description |
7/13/2009 | CR Submitted | CR Submitted |
7/13/2009 | CR Acknowledged | CR Acknowledged |
7/27/2009 | Discussed at Monthly CMP Meeting | Discussed at the June Systems CMP Meeting - See Attachment F in the Distribution Package |
7/27/2009 | Status Changed | Status changed to Presented |
8/11/2009 | Status Changed | Status changed to development |
11/23/2009 | Communicator Issued | Product/Process notifications sent PROD.RESL.11.16.09.F.06842.Multpl_Malheur_Consldatn PROS.MISC.11.16.09.F.07053.CMP-GeoDeaveragingV27 System Release Notifications sent SYST.IMAS.11.16.09.F.07200.IMAGUI_Rel26.1_DrftAnncmt SYST.IMAS.11.23.09.F.07237.IMAGUIRel26.1_FinalAnncmt |
12/16/2009 | Discussed at Monthly CMP Meeting | Discussed at the December System Meeting - See Attachment K |
12/16/2009 | Status Changed | Status Changed to CLEC Test. |
1/20/2010 | Discussed at Monthly CMP Meeting | Discussed at the January CMP meeting - See Attachment G in the Distribution package. |
1/20/2010 | Status Changed | Status changed to Completed |
Project Meetings |
01/20/10 Systems CMP Meeting Mark Coyne-Qwest said the CR was effective 12/14/09 and asked if it was OK to close. There were no objections. 12/16/09 Systems CMP Meeting Mark Coyne-Qwest said this CR went into effect on 12/14/09 and that we would move this CR to CLEC Test. 7/15/09 Systems CMP Meeting Janean Van Dusen-Qwest said Qwest will be consolidating Malheur entity into Qwest Corp. IMA edits associated with Malheur will be eliminated and GUI drop down menu for address check updated to include MAL. She said that this will be disclosed in the October 19, 2009 release but will not be implemented until December 14, 2009. Janean said Qwest will be invoking the SCRP process as outlined in Section 10.4 of the CMP document. Kim Isaacs-Integra asked since Qwest is invoking SCRP, will anything be bumped in the October release. Mark Coyne-Qwest said we will not bump anything in the release.
|
CenturyLink Response |
|
Information Current as of 1/11/2021