Archived System CR SCR062702-06 Detail |
Title: USOC's and description by product for IMA GUI | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR062702-06 |
Completed 11/17/2005 |
1275 - 2150 | 1/18 | Ordering | Resale Centrex 21, LNP, Resale, UNE-P POTS, UNE-P CTX 21 |
Originator: Walker, Jon |
Originator Company Name: Complete Telecommunications Inc. |
Owner: Winston, Connie |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
Add available USOC's menu when product selected in IMA
|
Status History |
Date | Action | Description |
6/27/2002 | CR Submitted | |
6/27/2002 | CR Acknowledged | |
6/27/2002 | Info Requested from CLEC | Sent email to Jon Walker asking if June 26th CLEC Meeting served as the Clarification Call for this CR. |
7/2/2002 | Info Received From CLEC | Received email from Jon Walker concurring with the 6/26 CLEC Mtg as the Clarification Call. |
7/9/2002 | LOE Issued | LOE issued |
7/18/2002 | Discussed at Monthly CMP Meeting | SCR062702-06 discussed at July Systems CMP Monthly meeting; please see Systems CMP Distribution Package July CMP -- Attachment B |
7/22/2002 | Status Changed | Status changed to pending prioritization |
7/26/2002 | Release Ranking | Ranking for Release 12.0 following the July 2002 Systems CMP Meeting. SCR062702-06 ranked number 35 |
10/30/2002 | Status Changed | SCR062702-06 status updated to 'Pending Prioritization' based upon outcome of release 12.0 packaging effort |
12/19/2002 | Discussed at Monthly CMP Meeting | SCR062702-06 discussed at December Systems CMP Monthly meeting; please see Systems CMP Distribution Package December CMP -- Attachment O |
12/31/2002 | Release Ranking | Ranked #36 for IMA 13.0 Release |
1/23/2003 | Release Ranking | Rnaked #39 for IMA 13.0 after exception request SCR011303-02EX |
3/13/2003 | Status Changed | Status changed to Pending Prioritization after Packaging of 13.0 |
4/7/2003 | Release Ranking | 14.0 Prioritization- Ranked #36 out of 53 |
4/29/2003 | Release Ranking | Rank changed due to Late Adders- Ranked #38 |
5/30/2003 | Release Ranking | Rank changed due to Late Adders- Ranked #39 |
7/9/2003 | Status Changed | Status changed to pending prioritization with the release of IMA 14.0 Packaging. |
9/2/2003 | Release Ranking | 15.0 Prioritization- Ranked #39 out of 57 |
9/29/2003 | Release Ranking | 15.0 Revised Prioritization, due to Late Adder - Ranked #40 out of 58 |
11/5/2003 | Status Changed | Status changed to pending prioritization |
2/4/2004 | Release Ranking | 16.0 Prioritization- Ranked #12 out of 50 |
3/1/2004 | Release Ranking | IMA 16.0 Revised Prioritization, Late Adder Ranking - #12 out of 51 |
8/3/2004 | Release Ranking | 17.0 Prioritization- Ranked #25 out of 41 |
7/5/2005 | Additional Information | QPP will benefit with the implementation of this CR |
9/29/2005 | Communicator Issued | SYST.09.29.05.F.03330.IMA18.0ChgDeployDate |
10/17/2005 | Status Changed | Status Changed to CLEC Test Due to 10/17/05 Deployment |
10/19/2005 | Discussed at Monthly CMP Meeting | Discussed at the October Systems CMP Meeting - See Attachment G in the Distribution Package |
11/18/2005 | Discussed at Monthly CMP Meeting | Discussed at the November Systems CMP Meeting - See Attachment G in the Distribution Package |
11/23/2005 | Status Changed | Status changed to Completed |
Project Meetings |
E-mail Received from Vail Resorts (Jon Walker) You may close the CR. Jon Walker Vail Resorts Information Technology 137 Benchmark Road, MS71 Avon, Colorado 81620 970.477.8588 - Office 970.331.1617 - Cell 11/22/05 E-mail Sent to Complete Telecommunications Jon, The purpose of this e-mail is to let you know that the attached CMP change request deployed on October 17, 2005 with the IMA 18.0 Release. In the November Systems CMP Meeting, it was agreed that I would contact you to determine if this CR can be closed. Please let me know if you concur. Thanks for your help. Lynn Stecklein Qwest Wholesale CRPM 303 382-5770 Lynn.Stecklein@qwest.com
11/16/05 Systems CMP Meeting Jill Martain/Qwest stated that this CR deployed on 10/17/05. She said that we will work off line with Complete Telecommunications to determine if this CR can be closed.
10/19/05 Systems CMP Meeting This CR deployed on 10/17/05 and will remain in CLEC Test.
Combined Overview and IMA EDI Disclosure Documentation Walkthrough for IMA EDI Release 18.0 August 10, 2005 8:00 am Location: CONFERENCE BRIDGE ONLY Conference Bridge: 1-888-725-8686 Conference ID: 4317009 Attendees List* Anders Ingemarson - Qwest Angela Stewart - Qwest Angie Thompson - Weiser Anne Robberson - Qwest Brian Caywood - Qwest Chris Terrell - AT&T Chuck Anderson - Qwest Cim Chambers - Qwest Dave Schleicher - Qwest Denise Martinez - Qwest Diane Burt - AT&T Dianne Friend - Time Warner Gary Berroa - Qwest John Sanclaria - Qwest Judy DeRosier - Qwest Lynn Stecklein - Qwest Mark Coyne - Qwest Mark Haynes - Qwest Michael Lopez - Qwest Michelle Thacker - Qwest Pat Bratetic - Qwest Russ Urevig - Qwest Sandie Tekavec -Qwest Shon Higer - Qwest Stephanie Prull - Eschelon *List may be incomplete. 1. Introductions Kyle Kirves began the meeting by taking attendance and announcing the meeting purpose. The meeting notice included copies of the agenda and the candidate overview document. Kyle explained that the walkthrough would cover the candidates, the candidate impacts to the associated documentation, and the IMA EDI Disclosure Documentation overview. SCR #062702-06 USOCs and Description By Product for IMA GUI Anne Robberson reviewed the information provided in the candidate overview document circulated with the meeting agenda and the meeting notification announcement. Kyle opened the floor to Questions. There were no questions. Kyle asked about documentation updates. Gary Berroa and Dave Schleicher covered the changes. There were no additional questions. Kyle asked if there were any more questions about any of the candidates or this portion of the walkthrough. There were no questions. 2/16/05 Systems CMP Meeting - IMA 18.0 Candidate Discussion There was no discussion on this CR. 7/22/04 Systems CMP Meeting Jill Martain/Qwest stated that Qwest would distribute the ballot on July 27th, it is due back to Qwest on July 30th, and Qwest would email the initial prioritization list to the CLECs on August 3rd. There were no questions. The CR Originator was not on the conference bridge. There were no questions 7/18/02 Systems CMP meeting SCR062702-06 USOC's and description by product for IMA GUI (Originated by Complete Telecommunications Inc) Michael Buck/Qwest said that no one from Complete Telecommunications Inc is in attendance to discuss this request. He asked everyone to review the description associated with this change request. Liz Balvin/WorldCom asked how this would look. Jeff Thompson/Qwest said that it would be listed by Product with the applicable USOCs. The status of this change request will be changed to Pending Prioritization. The LOE is provided in the CR response and the CR eligible for the 12.0 vote. 6/26/02 Clarification Meeting Request that a list of Features (USOCs) be provided by Product. The scenario described was that they wanted a list of the USOCs that would drop down after they provided the product information and when they select the particular USOC it is removed from the list. Referenced a Sprint GUI that did this. The GUI currently provides a drop down list of the most common USOCs for Resale POTS (there are about 27). The way the GUI works is that the features are in a separate tab and the tab allows you to add features, so from the drop down list you can only choose one USOC. If you needed another USOC you would need to add another feature section. The list of USOCs is not available for UNE-P POTS. UBL and LNP do not require CLECs to enter USOCs so this would not apply.
|
CenturyLink Response |
DRAFT Response July 9, 2002 RE: SCR062702-06 USOCs and desciption by product for IMA GUI Qwest has reviewed the information submitted as part of Change Request (SCR062702-08). Based upon the scope of this CR as agreed to in the Clarification Meeting (held June 26, 2002) Qwest is able to provide an estimated Level of Effort (LOE) of 1275 to 2150 hours for this IMA Change Request. At the next Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest's further evaluation of this Change Request. This Change Request is an eligible candidate for the 12.0 IMA Release. Sincerely, Qwest
|
Information Current as of 1/11/2021