Archived System CR SCR061003-01 Detail |
Title: Change DUF to provide 202409 and 202410 in all regions | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR061003-01 |
Completed 10/8/2004 |
2200 - 5200 | 11/ | Billing | UNE-P, Resale |
Originator: Balvin, Liz |
Originator Company Name: MCI |
Owner: Winston, Connie |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
REVISED CR: Description of Change/Exception: Qwest currently uses 202109 and 202110. This CR requests the use of 202409 and 202410 in all regions.
ORIGINAL CR: Description of Change/Exception:
While Qwest’s Eastern & Western regional files appropriately populate the Billing Company NPA/NXX field on a 202109 and 202110 record (cols 28-33), the Central region file changes this field with each file. In doing so, MCI cannot identify the headers as being in a specific invoice sequence.
Example of Qwest/Central: TOL.#CO.R730.BJ97M02Z(0)
An example of data populated:
20210903052025361537229722948078600000000000000000 ^^^^^^ 20210903052026361537229722930366600000000000000000 ^^^^^^
NOTE: Data discrepancy ^^^^^^
Example of Qwest/Eastern:
AK.#EN.ACCESS.C0M02.LSP(0)
An example of data populated:
202109030519773112696317424402422000000000000000000 ^^^^^^ 202109030520793112696317424402422000000000000000000 ^^^^^^
Expected Deliverables/Proposed Implementation Date (if applicable): That Qwest consistently populate Billing Company NPA/NXX field on a 202109 record with the same value.
Note: 202110 was added in the Clarification Meeting.
|
Status History |
Date | Action | Description |
6/10/2003 | CR Submitted | |
6/11/2003 | CR Acknowledged | |
6/18/2003 | Clarification Meeting Held | |
7/7/2003 | Qwest Response Issued | |
7/17/2003 | Discussed at Monthly CMP Meeting | |
3/4/2004 | Discussed at Monthly CMP Meeting | Discussed at February CMP Systems Meeting - See attachment G |
4/28/2004 | Discussed at Monthly CMP Meeting | Discussed at the April CMP Systems Meeting - See attachment G |
6/25/2004 | Communicator Issued | SYST.06.25.04.F.01825.AugCRISRelFinTechSpecs |
8/9/2004 | Status Changed | Status Changed to CLEC Test due to August 9, 2004 deployment. |
9/16/2004 | Discussed at Monthly CMP Meeting | Discussed at the September CMP Systems Meeting - See Distribution Package - Attachement G |
10/11/2004 | Status Changed | Status changed to completed |
Project Meetings |
10/8/04 Systems CMP Meeting Lynn, We had our folks check to ensure the change has taken place and they have confirmed it has. Therefore, we can go ahead and close this change request. LeiLani Hines MCI Carrier Relations 303-217-7340 --Original Message-- From: Stecklein, Lynn [mailto:Lynn.Stecklein@qwest.com] Sent: Monday, October 04, 2004 2:50 PM To: Leilani.Hines@mci.com Subject: SCR061003-01 Change DUF to provide 202409 and 202410 in all regions Hi Leilani, During the September CMP Systems meeting you stated that you wanted to check further to determine whether or not you were okay with closing the attached CR. Have you been able to do so? Let me know if you have made a decision or have further questions. Thanks,
Lynn Stecklein CRPM – Systems 303 382-5770
9/16/04 Systems CMP Meeting Leilani Hines/MCI stated that she needed to check further to see if this CR can be closed. Jill Martain/Qwest stated that this request will remain in CLEC Test. 6/23/04 E-Mail sent to MCI Liz, During the June CMP Systems Meeting, you asked about the implementation date on SCR061003-01 Change DUF to Provide 202409 and 202410 in all Regions. This is to let you know the implementation date is August 9, 2004. Call me with any questions. Thanks, Lynn Stecklein 303 382-5770 CRPM Systems Lynn.Stecklein.qwest.com 6/17/04 CMP Systems Meeting Liz Balvin/MCI asked if Line # 107, SCR061003-01 Change DUF to Provide 202409 and 202410 in all Regions, was scheduled. Lynn Stecklein/Qwest stated that she would check for the targeted implementation date. 4/22/04 CMP Systems Meeting Connie Winston/Qwest stated that the targeted date for this request is August 5, 2004. 2/19/04 CMP Monthly Meeting Connie Winston/Qwest stated that we are looking to reschedule this candidate. 9/18/03 CMP Monthly Meeting Lynn Notarianni/Qwest provided the targeted implementation of March 2004. This Action Item is closed. CMP Monthly Meeting July 17, 2003 SCR061003-01 Change DUF to provide 202409 and 202410 in all regions (originated by MCI) Liz Balvin/MCI stated that the CR had been changed from the original request. She stated that MCI wanted the change to be consistent across all regions. Lynn Notarianni/Qwest stated that Qwest had provided an LOE and that they were looking into scheduling. From: Chad Warner [mailto:chad.warner@mci.com] Sent: Friday, June 27, 2003 9:26 AM To: mmschae@qwest.com Cc: lnolan@qwest.com; kthomte@qwest.com; 'Liz Balvin'; 'Beverly Lambert' Subject: FW: SCR061003-01 Per EMI OBF, that Qwest provide Billing Company NPA/NXX on a 202109 record (cols 28-33) in the Central Region) Mimi, On our DUF call yesterday Judd had mentioned the possible option of using the 202409/10 records. As you will see below Bev Lambert has confirmed that this is an acceptable option for MCI. How do we handle with current CR? Chad Warner MCI Carrier Management (Qwest Region) 303-217-4214 V 625-4214 Clarification Meeting June 18, 2003 Meeting attendees: Chad Warner-MCI, Beverley Lambert-MCI, Kerri Waldner-Qwest, Carl Sear-Qwest, Carrie Stirman-Qwest, Cathy Stacy-Qwest, Brian Whiteside-Qwest, Mark Heline-Qwest Review of CR: Nolan-Qwest stated that she would read the description of the change and that MCI could add at any point. Nolan-Qwest reviewed the CR. Lambert-MCI stated that the soft copy of the CR she received had the carrotts in the wrong space. Nolan-Qwest stated that she copied it out of access and that she would check on why it was incorrect. Lambert-MCI stated that she also wanted to add 202110 records to the CR. Nolan-Qwest stated that she would add it. Nolan-Qwest then asked if Qwest had any questions. Whiteside-Qwest asked about the zeros listed in the Western region and Sear-Qwest stated that he would explain offline. Sear-Qwest stated that he believed that Qwest was in compliance and that these were optional fields. Nolan-Qwest reviewed the products and interfaces. She stated that this CR would be available for presentation at the July meeting and explained that Qwest would work to provide a response. She asked if there were any other questions or concerns. None. Meeting adjourned.
|
CenturyLink Response |
DRAFT RESPONSE July 7, 2003 RE: SCR061003-01 Change DUF to provide 202409 and 202410 in all regions Qwest has reviewed the information submitted as part of Change Request SCR061003-011. Based upon research that has been conducted following the Clarification Meeting (held June 18, 2003) Qwest is able to provide the LOE of 2,200 - 5,200 hours for this Wholesale Billing change. At the July Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Qwest is interested in the experiences of the CMP community as relates to this issue. Qwest will incorporate any feedback received at the next Monthly Systems CMP Meeting into further evaluation of this Change Request. Sincerely, Qwest
|
Information Current as of 1/11/2021