Archived System CR SCR052202-03 Detail |
Title: CEMR status emails sent to initiator of ticket as well as general mailbox | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR052202-03 |
Completed 5/22/2003 |
500 - 1000 | 5/ | All |
Originator: Stichter, Kathy |
Originator Company Name: Eschelon |
Owner: Winston, Connie |
Director: |
CR PM: Esquibel-Reed, Peggy |
Description Of Change |
Currently Qwest sends an email to a general email box for all CEMR ticket status changes. Eschelon asks Qwest to allow the initiator of the CEMR ticket to enter their specific email address as well as the general email address for Qwest to deliver the CEMR ticket status changes to both addresses.
Expected Deliverable: The capability for Eschelon to enter 2 email addresses for Qwest to send all CEMR ticket status changes.
|
Status History |
Date | Action | Description |
5/22/2002 | CR Submitted | |
5/22/2002 | CR Acknowledged | |
5/22/2002 | Info Requested from CLEC | Sent email to kathy Stichter/Eschelon, asking for availability for Clarification Meeting. |
5/23/2002 | CLEC Provided Information | Received email with Eschelon's availability. |
5/24/2002 | Clarification Meeting Scheduled | Clarification Meeting Scheduled For May 28, 2002. |
5/28/2002 | Clarification Meeting Held | |
6/20/2002 | Discussed at Monthly CMP Meeting | SCR052202-03 discussed at June Systems CMP Monthly meeting; please see Systems CMP Distribution Package June CMP -- Attachment B |
1/16/2003 | Discussed at Monthly CMP Meeting | SCR052202-03 discussed at January Systems CMP Monthly meeting; please see Systems CMP Distribution Package January CMP - Attachment I. |
2/17/2003 | Communicator Issued | SYST.02.17.03.F.04250.CEMRRlse10309DrftNts |
2/17/2003 | Communicator Issued | SYST.02.17.03.F.04256.CEMRRlse10309DrftNts |
2/24/2003 | Communicator Issued | SYST.02.24.03.F.04259.CEMRFinalRelNotes |
3/17/2003 | Communicator Issued | SYST.03.17.03.F.04277.CEMRRel |
3/18/2003 | Status Changed | Status Changed to CLEC Test due to 3/17/03 Deployment. |
3/20/2003 | Discussed at Monthly CMP Meeting | SCR052202-03 discussed at March Systems CMP Monthly meeting; please see Systems CMP Distribution Package March CMP. |
4/17/2003 | Discussed at Monthly CMP Meeting | SCR052202-03 discussed at April Systems CMP Monthly meeting; please see April Systems CMP Distribution Package, Attachment G. |
5/22/2003 | Discussed at Monthly CMP Meeting | Discussed at the May Systems CMP Monthly meeting; please see May Systems CMP Distribution Package, Attachment G |
Project Meetings |
May 22, 2003 Systems CMP Meeting Discussion: Bonnie Johnson/Eschelon stated that this CR could be closed.
April 17, 2003 Systems CMP Meeting Discussion: Bonnie Johnson/Eschelon stated that they would like to leave this CR in CLEC Test for one more month.
- January 16, 2003 Systems CMP Meeting Discussion: Dan Busetti/Qwest stated that this CMP CR is targed for implementation on March 17, 2003. There were no questions or comments.
- June 20, 2002 CMP Meeting Discussion: Kathy Stichter (Eschelon) reviewed what Eschelon is looking for with this CR. Michael Buck (Qwest) asked if there were any other comments. There were no other CLEC comments. Jeff Thompson (Qwest) stated that this is another straightforward CR. He indicated that it is a little bit larger effort. The issue is getting the work scheduled. Michael Buck (Qwest) stated that this would be updated to ‘Presented’.
-- Clarification Meeting Notes: May 28, 2002 Attendees: Kathy Stichter/Eschelon, Dan Busetti/Qwest, Cathy Garcia/Qwest, Lynn Stecklein/Qwest, Peggy Esquibel-Reed/Qwest The CR description was reviewed. Kathy Stichter/Eschelon stated that the request is for an additional space that would allow a user to input their own email address. There were no other questions. Dan Busetti/Qwest stated that he would work on getting the level of effort.
|
CenturyLink Response |
DRAFT RESPONSE June 12, 2002 RE: SCR052202-03 (CEMR status emails sent to initiator of ticket as well as general mailbox) Qwest has reviewed the information submitted as part of Change Request SCR052202-03. Based upon the scope of this CR as agreed to in the Clarification Meeting (held May 28, 2002) Qwest is able to provide an estimated Level of Effort (LOE) of 500 to 1000 hours for this CEMR Change Request. At the next Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request. Upon obtaining consensus from CMP participants as to the appropriate direction for Qwest to take on this Change Request, Qwest will review release schedules and development timetables in an effort to evaluate options for potential scheduling of Change Request SCR052202-03. Sincerely, Jeff Thompson Qwest, Information Technologies
|