Wholesale: Products & Services

Archived System CR SCR051304-01 Detail

 
Title: Request for Line Loss Notification to notify CLECs if the customer was lost to a Wireless Carrier
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR051304-01 Completed
6/2/2006
3500 - 5100   3/19 UNE-P
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Coyne, Mark
Director:
CR PM: Stecklein, Lynn
Description Of Change
AT&T requests that Qwest provide a Wireless Indicator on the Line Loss File as notification to CLECs in the event that the customer moves to Wireless Carrier. The Wireless Indicator should be provided on 836 transactions as well as on the Line Loss File.

Expected Deliverables/Proposed Implementation Date (if applicable):

That Qwest notify CLECs of Line Loss(es) to Wireless Carriers by way of a wireless indicator on the Line Loss file.

Status History

Date Action Description
5/13/2004 CR Submitted  
5/14/2004 CR Acknowledged  
5/20/2004 Discussed at Monthly CMP Meeting Discussed at the May Systems CMP Meeting - See Attachment F 
5/21/2004 Info Requested from CLEC Pending AT&T availability for clarification call 
5/28/2004 Clarification Meeting Scheduled  
6/2/2004 Clarification Meeting Held  
6/4/2004 Status Changed Status changed to presented 
6/17/2004 Status Changed Status changed to pending prioritization 
6/17/2004 Discussed at Monthly CMP Meeting Discussed at the June Monthly CMP Meeting - See June Systems Distribution Package 
7/16/2004 LOE Issued  
8/3/2004 Release Ranking 17.0 Prioritization- Ranked #31 out of 41 
7/7/2005 Additional Information QPP will benefit with the implementation of this CR 
8/1/2005 Release Ranking 19.0 Prioritization- Ranked #3 out of 26 
11/11/2005 Status Changed Status Changed to Packaged Due To IMA 19.0 Packaging 
1/18/2006 Discussed at Monthly CMP Meeting Discussed at the January Systems CMP Meeting - See Attachment G in the Distribution Package 
2/8/2006 General Meeting Held IMA 19.0 Walkthrough Held 
2/20/2006 Status Changed Status changed to Development 
3/3/2006 Communicator Issued SYST.02.24.06.F.03703.IMAEDI19.0SuppDocuments 
3/3/2006 Communicator Issued SYST.02.24.06.F.03704.IMAEDI19.0.FinalTechSpecs 
3/24/2006 Communicator Issued SYST.03.24.06.F.03804.IMAEDRel19.0SmplLineLoss 
4/10/2006 Status Changed Status changed to CLEC Test 
5/4/2006 Discussed at Monthly CMP Meeting Discussed at the April Systems CMP Meeting - See Attachment G in the Distribution Package 

Project Meetings

6/2/06 E-mail from AT&T

Sorry Peggy for not following up with you sooner. I've checked with Leo Dimitriatis and he is OK with closing this, as well as SCR051304-01 Request for Line Loss Notification to notify CLECs if the customer was lost to a Wireless Carrier.

5/17/06 Systems CMP Meeting

Jill Martain - Qwest stated that this CR was implemented on April 10, 2006 and asked if AT&T was ok to close. Kathy Lee - AT&T said that she will check internally and close offline.

4/19/06 Systems CMP Meeting

Jill Martain-Qwest stated that this was just deployed in the IMA 19.0 Release and would remain in CLEC Test.

3/15/06 Systems CMP Meeting

Jill Martain - Qwest stated that this CR will deploy on April 10, 2006.

February 8, 2006 Combined Overview and IMA EDI Disclosure Documentation Walkthrough for IMA EDI Release 19.0 (facilitated by Qwest IT) Attendees List (may be incomplete): Kyle Kirves-Qwest, Anders Ingemarson-Qwest, Angela Stewart-Qwest, Annelyn Aficial-AMS, Carol McKenzie-Qwest, Chris Terrell-AT&T, Chuck Anderson-Qwest, Curt Anderson-Qwest, Dawn Beck-Qwest, Denise Martinez-Qwest, Diane Burt-AT&T, Dianne Friend-Time Warner, Ellen McArthur-Qwest, Gary Berroa-Qwest, Jeff Yeager-Accenture, Judy DeRosier-Qwest, Lee Gomez-Qwest, Linda Birchem-Comcast, Lynn Stecklein-Qwest, Maria Aquino-AT&T, Mark Haynes-Qwest, Michael Lopez-Qwest, Nancy Thompson-Wisor, Orbit.com Representatives, Peggy Esquibel-Reed-Qwest, Roslyn Davis-Verizon Business, Shonna Pasionek-Qwest, Stephanie Prull-Eschelon Walkthrough Discussion: Introductions Kyle Kirves began the meeting by taking attendance and announcing the meeting purpose. The meeting notice included copies of the agenda, the candidate overview document, and a summary sheet of changes that customers can expect to see in the final version of the tech specs that do not appear in the draft. Kyle explained that the walkthrough would cover the candidates, the candidate impacts to the associated documentation, and the IMA EDI Disclosure Documentation overview. Kyle introduced Ellen McArthur to go over the first candidate, SCR051304-01- Request for Line Loss Notification to notify CLECs if the customer was lost to a Wireless. CANDIDATE REVIEWS: SCR051304-01a Wireless Ellen McArthur reviewed the information provided in the candidate overview document circulated with the meeting agenda and the meeting notification announcement. Kyle opened the floor to Questions. Stephanie Prull asked if the customer does not code for 18.0, and the candidate is multirelease, will it cause fallout? Dawn Beck answered that there will be no fallout on the Qwest side if the customer does not code to the candidate in 18.0. Test is still recommended to see if the CLEC’s translator will ignore the transaction when received or if it will fail translation. Stephanie asked how this will look on the Line Loss Report, Anders Ingemarson stated that, the NPDI field will be added to the Line Loss Report but the details have yet to be worked out. Stephanie asked if an example of the Line Loss report will be made available. Kyle stated he would try to include an example with the minutes. NOTE: At time of publication of the minutes, the report sample was not available. Qwest will, however, provide a sample as soon as it is available, and will notify on its availability accordingly. There were no other questions. Kyle asked about other documentation updates. Mark Haynes covered the changes to the Error Messages that will occur once the candidate is implemented. Kyle asked if there were any other questions. No questions, so Kyle moved discussion to the next candidate.

1/18/06 Systems CMP Meeting

Connie Winston - Qwest stated that there is only 1 map for line loss notification. She said that when we make changes to a field, the map has to change so that they can accept the feed. Connie said that this impacts 17.0, 18.0 and 19.0 and we just wanted to remind the CLECs that everyone needs to be ready to cut with us on the release for the changes associated to this CR. Cim Chamber - Qwest stated the PN = Provider Notification field was the field that had changes. Sharon Van Meter - AT&T asked when this was going in. Connie Winston - Qwest said that it is scheduled in the April 19.0 Release

2/16/05 Systems CMP Meeting - IMA 18.0 Candidate Discussion

Sharon Van Meter-AT&T stated that this CR is a low priority for AT&T. Connie Winston-Qwest stated that the interface should be IMA Common.

7/22/04 Systems CMP Meeting

Jill Martain/Qwest stated that Qwest would distribute the ballot on July 27th, it is due back to Qwest on July 30th, and Qwest would email the initial prioritization list to the CLECs on August 3rd. There were no questions.

Donna Osborne-Miller/AT&T stated that this is medium for AT&T. This CR is for IMA Common.

6/17/04 Systems CMP Meeting

Kit Thomte/Qwest stated that this CR was a walk on in the May CMP Systems Meeting. Kit asked if there were any questions or comments and stated that the status would move to Pending Prioritization.

5/20/04 Systems CMP Meeting

Carla Pardee/AT&T stated that AT&T is requesting that Qwest provide a Wireless Indicator on the Line Loss File as notification to CLECs in the event that the customer moves to a Wireless Carrier. Carla stated that the Wireless Indicator should be provided on 836 transactions as well as on the Line Loss File.

Connie Winston/Qwest stated that this is a complicated request because of the port out that is generally a disconnect order. Connie stated that we had a request in CMP to put LNP on the Loss Report.

Revision to Minutes from Eschelon 6/1/04 - Bonnie Johnson/Eschelon asked AT&T why they would need to know why the loss was to a Wireless Carrier vs. a local service provider.

Carla Pardee/AT&T said that she didn’t know.

Connie Winston/Qwest stated that we would not know the identity of the Wireless Carrier.

Peggy Esquibel-Reed/Qwest stated that the status of this CR will remain in Submitted Status until the clarification meeting is held.

6/3/04 Clarification Call

Attendees: Donna Osborne-Miller - AT&T, John Daugherty - AT&T, John Gallegos - Qwest, Angela Stewart - Qwest, Connee Moffatt - Qwest, Dusti Bastian - Qwest, Jim Recker - Qwest, Lynn Stecklein - Qwest

Review Description of Change Lynn Stecklein - Qwest reviewed AT&T's request. AT&T is requesting that Qwest provide a Wireless Indicator on the Line Loss File as notification to CLECs in the event that the customer moves to Wireless Carrier. AT&T would like the Wireless Indicator be provided on 836 transactions as well as on the Line Loss File.

Discussion Dusti Bastian - Qwest asked if AT&T wanted a letter indicator. John Daugherty - AT&T stated that they were looking for a letter indicator. John Gallegos - Qwest asked if AT&T was looking for the indicator on wireless only. Donna Osborne-Miller - AT&T said yes. Dusti Bastian - Qwest asked if this would be when the service was ported to wireless. Donna Osborne-Miller - AT&T agreed. John Gallegos - Qwest asked if AT&T wanted this information included in the 836 EDI functionality. Donna Osborne-Miller - AT&T stated that they want it consistent.

Confirm Areas and Products Impacted The Product impacted is UNE-P and the interface is IMA EDI.

Identify/Confirm CLECs Expectation AT&T is requesting that Qwest notify CLECs of Line Loss(es) to Wireless Carriers by way of a wireless indicator on the Line Loss file.

Establish Action Plan AT&T will present this change request in the June 17, 2004 Systems CMP Meeting.

CenturyLink Response

July 16, 2004

RE: SCR051304-01 Request for Line Loss Notification to notify CLECs if the customer was lot to a Wireless Carrier

Qwest has reviewed the information submitted as part of Change Request (SCR051304-01). Based upon the scope of this CR as agreed to in the Clarification Meeting (held June 2, 2004) Qwest is able to provide an estimated Level of Effort (LOE) of 3500 to 5100 hours for this IMA Change Request.

At the next Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest's further evaluation of this Change Request.

This Change Request is an eligible candidate for the IMA 17.0 prioritization vote.

Sincerely, Qwest

Information Current as of 1/11/2021