Archived System CR SCR050503-01 Detail |
Title: Create IMA BPL Edit to Require CLECs to Provide USOC PGO2N When Ordering a 2 Line resale POTS package. | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR050503-01 |
Withdrawn 4/22/2004 |
800 - 1250 | 3/ | Ordering | Resale POTS |
Originator: Paxton, Mallory |
Originator Company Name: Qwest Corporation |
Owner: Winston, Connie |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
When a CLEC tries to order a 2-line Resale POTS package, a BPL edit will prompt them to add the USOC PGO2N to their request. This will enable the CLEC to submit their LSR correctly rather than receive a reject. This CR is related to PC 042303-4, which introduces the new USOC and provides for a reject for requests without it beginning August 9, 2003. Impacted packaged for this systems CR are: 2-Line Preferred Choice with Voice Mail (PGOFA), 2-Line Preferred Choice (PGOFB), and 2-Line Value Choice (PGOVB). Grandfathered packages are not impacted, since they can’t be added new.
|
Status History |
Date | Action | Description |
5/5/2003 | CR Submitted | |
5/5/2003 | CR Acknowledged | |
5/9/2003 | Clarification Meeting Held | |
6/10/2003 | Status Changed | Status changed to clarification |
6/19/2003 | Status Changed | Status changed to evaluation |
6/19/2003 | Discussed at Monthly CMP Meeting | Discussed at the June CMP Systems Meeting- See Distribution Package - Attachment C |
7/9/2003 | Draft Response Issued | |
7/10/2003 | Status Changed | Status changed to Presented |
7/17/2003 | Status Changed | Status changed to pending prioritization |
7/17/2003 | Discussed at Monthly CMP Meeting | Discussed at the July CMP Systems Meeting- See Distribution Package - Attachment I |
9/2/2003 | Release Ranking | 15.0 Prioritization- Ranked #44 out of 57 |
9/29/2003 | Release Ranking | 15.0 Revised Prioritization, due to Late Adder - Ranked #45 out of 58 |
11/5/2003 | Status Changed | Status changed to pending prioritization |
2/4/2004 | Release Ranking | 16.0 Prioritization- Ranked #29 out of 50 |
3/1/2004 | Release Ranking | IMA 16.0 Revised Prioritization, Late Adder Ranking - #30 out of 51 |
4/22/2004 | Status Changed | Status changed to withdrawn |
4/28/2004 | Discussed at Monthly CMP Meeting | Discussed at the April CMP Systems Meeting - See attachment G |
Project Meetings |
4/22/04 CMP Sytems Meeting Jill Martain/Qwest stated that Qwest is withdrawing this CR and will continue with the current manual process. There was no dissent to withdraw. This CR is in Withdrawn Status. 8/21/03 CMP systems meeting Connie Winston/Qwest stated that Qwest was moderate. 7/17/03 CMP Systems Meeting Connie Winston/Qwest provided the LOE for this Change Request. The LOE is 800 to 1250 hours and is eligible for the IMA 15.0 vote. 6/19/03 CMP Systems Meeting Connie Winston/Qwest presented the CR and stated that this is an edit for a USOC that has had some fallout. Connie noted that Qwest would provide the LOE at July CMP. There were no questions or comments.
|
CenturyLink Response |
DRAFT RESPONSE July 9, 2003 RE: SCR050503-01 Qwest has reviewed the information submitted as part of Change Request SCR050503-01 Based upon the scope of this CR as agreed to in the Clarification Meeting (held May 9, 2003) Qwest is able to provide an estimated Level of Effort (LOE) of 800 to 1250 hours for this IMA Change Request with 0 SATE impacts. At the July Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request. This Change Request is eligible for the IMA 15..0 Prioritization. Sincerely, Qwest DRAFT RESPONSE June 6, 2003 RE: SCR050503-01 Qwest has reviewed the information submitted as part of Qwest's Change Request SCR050503-01. Based upon research that has been conducted following the Clarification meeting (held May 9, 2003) Qwest is still examining the issue. Qwest will continue to research the problem and provide an updated response at the June Systems CMP Meeting. At the June Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Qwest is interested in the experiences of the CMP community as relates to this issue. Qwest will incorporate any feedback received into further evaluation of this Change Request. Sincerely, Qwest
|
Information Current as of 1/11/2021