Archived System CR SCR042604-01IG Detail |
Title: ASOG 29 EXACT Upgrade | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR042604-01IG |
Completed 10/20/2004 |
- | 6/ | N/A |
Originator: Veik, Gary |
Originator Company Name: Qwest Corporation |
Owner: Winston, Connie |
Director: |
CR PM: Esquibel-Reed, Peggy |
Description Of Change |
The EXACT application needs to be updated to support ASOG 29 changes as mandated by OBF.
Draft Release Notes Issued will be July 9, 2004 Comment Cycle will start on July 9, 2004 Comment Cycle will end July 27, 2004 Final Release Notes will be Issued on August 6, 2004 Planned Release Production Date of September 20, 2004
Details of this release could be found at: http://www.atis.org/atis/clc/obf/obfhom.htm
Expected Deliverable: Upgrade EXACT Application to support ASOG 29 Changes. Implementation Date of 09/20/04
|
Status History |
Date | Action | Description |
4/26/2004 | CR Submitted | |
4/26/2004 | CR Acknowledged | |
4/29/2004 | Clarification Meeting Held | |
5/20/2004 | Discussed at Monthly CMP Meeting | Discussed at the May Systems CMP Meeting - See Attachment D |
5/20/2004 | Status Changed | Status changed to Development |
7/9/2004 | Communicator Issued | SYST.07.09.04.F.01861.ASRRel3.0DrftTechSpecs |
7/9/2004 | Communicator Issued | SYST.07.09.04.F.01861.ASRRel3.0DrftTechSpecs_Correction |
8/6/2004 | Communicator Issued | SYST.08.06.04.F.01949.ASRFinalTechSpecsSuppDocs |
9/16/2004 | Discussed at Monthly CMP Meeting | Discussed at the September Systems CMP Monthly Meeting; please see the September Systems CMP Distribution Package, Attachment K |
9/20/2004 | Status Changed | Status Changed to CLEC Test due to September 20, 2004 Deployment. |
10/20/2004 | Discussed at Monthly CMP Meeting | Discussed at the October Systems CMP Monthly Meeting; please see the October Systems CMP Distribution Package, Attachment G |
Project Meetings |
October 20, 2004 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR was deployed and asked if there was any dissent to close the CR. Connie noted that she is not aware of any issues. There was no dissent to close the CR.
-- September 16, 2004 Systems CMP Meeting Discussion: Jill Martain/Qwest stated that this CR will deploy prior to the next monthly CMP Meeting.
- 5/20/04 Systems CMP Meeting Peggy Esquibel-Reed/Qwest stated that this request is a standard upgrade for ASOG and is targeted for 9/20/04. Liz Balvin/MCI asked if Qwest was looking at anymore XML enhancements. Connie Winston/Qwest said no. Liz Balvin/MCI said that she thought that the Industry may be going that way. Bonnie Johnson/Eschelon confirmed that TELIS is not included because TELIS is being retired. Peggy Esquibel-Reed/Qwest stated that the status of this CR is in Development Status. Clarification Meeting - April 29, 2004 ATTENDEES: Gary Veik/Qwest, Peggy Esquibel-Reed/Qwest REVIEW CR DESCRIPTION: The EXACT application needs to be updated to support ASOG 29 changes as mandated by OBF. Draft Release Notes Issued will be July 9, 2004 Comment Cycle will start on July 9, 2004 Comment Cycle will end July 27, 2004 Final Release Notes will be Issued on August 6, 2004 Planned Release Production Date of September 20, 2004 Details of this release could be found at: http://www.atis.org/atis/clc/obf/obfhom.htm Expected Deliverable is that the EXACT Application will be upgraded to support ASOG 29 Changes. Implementation Date of 09/20/04 Peggy Esquibel-Reed/Qwest asked Gary Veik (Qwest) if there was additional information. Gary Veik/Qwest stated that there is no additional information. There were no additional questions or comments. CONFIRM IMPACTED PRODUCTS: NA CONFIRM IMPACTED INTERFACES: EXACT ACTION PLAN: This CR will be presented at the May CMP Meeting
|
CenturyLink Response |
May 13, 2004 QWEST RESPONSE: This is a Telcordia development effort. Qwest will implement this change on September 20, 2004 to support the Industry Standards through OBF.
|
Information Current as of 1/11/2021