SCR041604-01 Completed
11/19/2004
500 - 600   20/16 UNE-P PBX Designed Trunks and UNE-P PBX DID In only Trunks
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Winston, Connie
Director:
CR PM: Stecklein, Lynn
Description Of Change
Request that Trunk Products (i.e. UNE-P PBX Designed Trunks and UNE-P PBX DID In Only Trunks ) be added into SATE. AT&T Business will be introducing UNE-P Trunks later this year and would like to test this product in the same test environment as other Qwest Product testing. Trunk Products currently reside in the Interoperability Test Environment which would require AT&T to initiate testing efforts in 2 test environments. This would require that digital certificates and IP addresses be maintained in 2 separate environments rather than 1.

Status History

Date Action Description
4/16/2004 CR Acknowledged  
4/16/2004 CR Submitted  
4/16/2004 Additional Information AT&T requested that this CR be processed as a late adder and presented as a walk on in the April Meeting 
4/22/2004 Discussed at Monthly CMP Meeting Discussed at the April CMP Systems Meeting - See attachment F 
4/26/2004 Clarification Meeting Held  
4/27/2004 LOE Issued  
5/6/2004 Communicator Issued CMPR.05.06.04.F01655.Vote_Disposition 
5/25/2004 Discussed at Monthly CMP Meeting Discussed at the May CMP Systems Meeting - See attachment B 
6/4/2004 Status Changed Status changed to packaged 
9/16/2004 Discussed at Monthly CMP Meeting Discussed at the September CMP Meeting - See Distribution Package - Attachment K 
9/18/2004 Status Changed Status Changed to CLEC Test Due to September 18, 2004 Deployment. 
10/20/2004 Discussed at Monthly CMP Meeting Discussed at the October Systems CMP Meeting - See Distribution Package - Attachment G 
11/17/2004 Discussed at Monthly CMP Meeting Discussed at the November Systems CMP Meeting - See Distribution Package - Attachment G 

Project Meetings

11/17/04 CMP Systems Meeting Woldey Assefa/Qwest said that AT&T has indicated that these two products will not be tested. Sharon Van Meter/AT&T agreed that this CR could be closed.

10/22/04 CMP Systems Meeting

Connie Winston/Qwest stated that this CR was deployed with the IMA 16.0 Release and will remain in CLEC Test.

9/16/04 CMP Systems Meeting

Jill Martain/Qwest stated that this CR will be deployed prior to the next monthly CMP Meeting.

5/20/04 Systems CMP Meeting

Woldey Assefa/Qwest stated that SCR041604-01 Add Trunk Products to SATE submitted by AT&T is packaged for the SATE 16.0 release. Regina Mosley/AT&T asked what products were included in this CR. Woldey Assefa/Qwest stated that UNE-P PBX Designed Trunks and UNE-P PBX DID In only Trunks were included

4/22/04 CMP Sytems Meeting

Donna Osborne-Miller/AT&T stated that AT&T is requesting that Trunk Products (I.e. UNE-P PBX Designed Trunks and UNE-P PBX DID in Only Trunks) be added into SATE. Donna stated that AT&T Business will be introducing UNE-P Trunks later and would like to test this product in the same test environment as other Qwest Product Testing. Liz Balvin/MCI asked if Qwest will look at the volume or will Qwest look to see if they can accommodate with this CR. Connie Winston/Qwest stated that this request would be treated the same as previous SATE CRs and will look to see if we can incorporate into 16.0.

This CR is in a Clarification Status.

4/26/04 Clarification Meeting

Introduction of Attendees:

Regina Mosley - AT&T, Liz Balvin - MCI, Cim Chambers - Qwest, Woldey Assefa - Qwest, Lynn Stecklein - Qwest

Review Description of Change Lynn Stecklein/Qwest reviewed the description of the CR. AT&T is requesting that Trunk Products (i.e. UNE-P PBX Designed Trunks and UNE-P PBX DID In Only Trunks ) be added into SATE. AT&T Business will be introducing UNE-P Trunks later this year and would like to test this product in the same test environment as other Qwest Product testing. Trunk Products currently reside in the Interoperability Test Environment which would require AT&T to initiate testing efforts in 2 test environments. This would require that digital certificates and IP addresses be maintained in 2 separate environments rather than 1.

Confirm Areas and Products Impacted This interface impacted on this request is SATE. Regina Mosley/AT&T stated that the request is for Trunk Products but asked how other products would impact the LOE. Woldey Assefa/Qwest stated that including more products would impact the LOE. Regina Mosley/AT&T said that they would like this request to address trunk products only.

Discussion Woldey Assefa/Qwest said that these will be a new products in SATE and asked if AT&T would be looking at specific activities or all activies for these 2 products. Regina Mosely/AT&T stated that they would probably be testing both initially for all activity types. Cim Chambers/Qwest asked if AT&T would be using 15.0 or 16.0. Regina Mosely/AT&T said that they would use 16.0 going forward in SATE.

Establish Action Plan Regina Mosley/AT&T said that AT&T is requesting that this request be processed as a late adder in the 16.0 Release. Qwest will be scheduling the late adder vote meeting in the next couple of weeks.

CenturyLink Response

DRAFT Response

April 27, 2004

RE: SCR041604-01 Add Trunk Products to SATE (IMA 16.0)

Qwest has reviewed the information submitted as part of Change Request (SCR041604-01). Based upon the scope of this CR as agreed to in the Clarification Meeting (held April 26, 2004) Qwest is able to provide an estimated Level of Effort (LOE) of 500 to 600 hours for this SATE Change Request.

At the next Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest's further evaluation of this Change Request.

This Change Request is an eligible candidate for the SATE17.0 prioritization vote.

Sincerely, Qwest

Information Current as of 1/11/2021