SCR041212-1 |
Completed 3/20/2013 |
1366 - | 3/33 | Ordering |
Originator: Martinez, Denise |
Originator Company Name: CenturyLink |
Owner: Martinez, Denise |
Director: |
CR PM: Lorence, Susan |
Description Of Change |
Remove the edit and rule specific to dropping requests to manual for IMA when the NPI field is populated. This will improve flow through of these requests and ensure accurate service orders are generated.
|
Status History |
Date | Action | Description |
4/12/2012 | CR Acknowledged | CR Acknowledged |
4/12/2012 | CR Submitted | CR Submitted |
4/18/2012 | Status Changed | Status changed to Presented. |
5/16/2012 | Discussed at Monthly CMP Meeting | Discussed at May Sys CMP Meeting – See Attachment I in the Distribution package |
5/16/2012 | LOE Issued | LOE issued - 1366 hours |
7/13/2012 | Action Item Created | Status changed to Packaged - IMA R33.0 |
12/10/2012 | Status Changed | Status changed to CLEC Test. |
1/16/2013 | Discussed at Monthly CMP Meeting | Discussed at the January Systems CMP Meeting - See Attachment G in the Distribution Package |
2/20/2013 | Discussed at Monthly CMP Meeting | Discussed at the February Systems CMP Meeting - See Attachment G in the Distribution Package. |
3/20/2013 | Status Changed | Status changed to Completed. |
3/20/2013 | Discussed at Monthly CMP Meeting | Discussed at the March Systems CMP Meeting - See Attachment G in the Distribution Package. |
Project Meetings |
3/20/13 System Monthly Meeting Mark Coyne - CenturyLink said these CRs are associated with IMA Release 33 which was implemented on December 10, 2012. Mark we discussed these in February and were OK to close then but asked if there were any questions. There were none. 2/20/13 System Monthly Meeting Mark Coyne - CenturyLink said we would like to close these six IMA CRs that are associated with IMA Release 33 which was implemented on December 10, 2012. Mark asked if there were any objections to moving them to Completed status. Kim Isaacs – Integra asked if any XML companies had migrated to the release and if there were some customers migrated, were there any problems. Carrie Bousfield – CenturyLink said there were two customers on the release as of January 19 and said there were quite a number migrating on March 23. Carrie said there were no problems. Kim Isaacs – Integra said based on that, she did not have any concerns with closing the CRs. 01/16/13 Systems CMP Meeting Mark Coyne - CenturyLink said these six IMA CRs were associated with IMA Release 33 which was implemented on December 10, 2012. He said we would consider them in February for closure. 05/16/12 Systems CMP Meeting Mark Coyne – CenturyLink relayed the LOEs for the following CR: SCR041212-1 Improve Processing on Port In Requests, LOE - 1366 hours Mark relayed these CRs will all be considered for upcoming releases. 4/18/12 Systems CMP Meeting Denise Martinez – CenturyLink reviewed the Description of Change as noted in the change request. She asked if there were any questions. There were none.
|
CenturyLink Response |
|