Wholesale: Products & Services

Archived System CR SCR040403-02 Detail

 
Title: Support Custom Ringing Service via the LSR fields
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR040403-02 Completed
11/16/2005
1500 - 2500   3/18 Ordering All Resale and All UNE-P
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Winston, Connie
Director:
CR PM: Esquibel-Reed, Peggy
Description Of Change
Currently the PCAT provides Ordering Instructions for all of the UNEP Features stated in the UNE-P Features Matrix (http://www.qwest.com/wholesale/clecs/features/unepfeatures.html).

Based on the current PCAT for Custom Ringing Service (last updated: September 10, 2002) a CLEC should be able to order Custom Ringing Service using the FA (Feature Activity), FEATURE and FEATURE DETAIL fields. However, during testing we received the following error messages :"RESALE Form:Service Details Section 1:Features Section: Can not convert or change USOC(s) not already on the account: RGGxx not on the account". We were instructed that this was not a defect, and this is how the system works for this particular item.

AT&T is requesting the support of Custom Ringing Service using the Feature Activity, Feature and Feature Detail fields.

Expected Deliverable:

That Qwest support Custom Ringing Service using the Feature Activity, Feature and Feature Detail fields

Status History

Date Action Description
4/4/2003 CR Submitted  
4/7/2003 CR Acknowledged  
4/7/2003 Info Requested from CLEC Email sent to Donna O-M for Clarification Meeting Availability. 
4/8/2003 CLEC Provided Information Received AT&T Availability for Clarification Meeting. 
4/9/2003 Clarification Meeting Scheduled Clarification Meeting scheduled for April 10, 2003 
4/10/2003 Clarification Meeting Held See Project Meetings Section for Meeting Minutes. 
5/6/2003 Draft Response Issued  
5/22/2003 Discussed at Monthly CMP Meeting Discussed at the May Systems CMP Monthly meeting; please see May Systems CMP Distribution Package, Attachment B 
8/21/2003 Discussed at Monthly CMP Meeting Discussed at the August Systems CMP Monthly Meeting; please see August Systems CMP Distribution Package, Attachment P 
9/2/2003 Release Ranking 15.0 Prioritization- Ranked #30 out of 57 
9/29/2003 Release Ranking 15.0 Revised Prioritization, due to Late Adder - Ranked #31 out of 58 
11/5/2003 Status Changed Status changed to pending prioritization 
1/22/2004 Discussed at Monthly CMP Meeting Discussed at the January Systems CMP Monthly Meeting; please see January Systems CMP Distribution Package, Attachment P 
2/4/2004 Release Ranking 16.0 Prioritization- Ranked #23 out of 50 
2/19/2004 Discussed at Monthly CMP Meeting Discussed at the February Systems CMP Monthly Meeting; please see the February Systems CMP Distribution Package, Attachments H & J 
3/1/2004 Release Ranking IMA 16.0 Revised Prioritization, Late Adder Ranking - #24 out of 51 
7/22/2004 Discussed at Monthly CMP Meeting Discussed at the July Systems CMP Monthly Meeting; please see July Systems CMP Distribution Package, Attachment N 
8/3/2004 Release Ranking 17.0 Prioritization- Ranked #22 out of 41 
2/16/2005 Discussed at Monthly CMP Meeting Discussed at the February Systems CMP Monthly Meeting; please see February Systems CMP Distribution Package, Attachment M 
2/28/2005 Release Ranking 18.0 Prioritization- Ranked #5 out of 34 
4/19/2005 General Meeting Held Additional Dsicussion Needed with CR Originator. See Project Meetings Section for Meeting Minutes. 
5/18/2005 Discussed at Monthly CMP Meeting Discussed at the May Systems CMP Monthly Meeting; please see the May Systems CMP Distribution Package, Attachment M 
7/5/2005 Additional Information QPP will benefit with the implementation of this CR 
9/21/2005 Discussed at Monthly CMP Meeting Discussed at the September Systems CMP Monthly Meeting; please see the September Systems CMP Distribution Package, Attachment K 
9/29/2005 Communicator Issued SYST.09.29.05.F.03330.IMA18.0ChgDeployDate 
10/17/2005 Status Changed Status Changed to CLEC Test Due to 10/17/05 Deployment 
10/19/2005 Discussed at Monthly CMP Meeting Discussed at the October Systems CMP Monthly Meeting; please see the October Systems CMP Distribution Package, Attachment G 
11/16/2005 Discussed at Monthly CMP Meeting Discussed at the November Systems CMP Monthly Meeting; please see the November Systems CMP Distribution Package, Attachment G 

Project Meetings

November 16, 2005 Systems CMP Meeting Discussion: Jill Martain/Qwest stated that this CR deployed on October 17th and asked if it was ready to close. Sharon Van Meter/AT&T asked that the CR remain open for validation. This CR remains in CLEC Test.

October 19, 2005 Systems CMP Meeting Discussion: This CR deployed on 10/17/05 and will remain in CLEC Test

September 21, 2005 Systems CMP Meeting Discussion: This CR will deploy on 10/10/05. Jill Martain/Qwest stated that she was notified late last night that there could be potential issues with the October releases and that since we were all meeting today she wanted to let everyone know that there was the potential that the release dates could slip. Jill advised that Qwest would send the appropriate system notifications if it is determined that the release date needed to change.

-- August 10, 2005 EXCERPT from the 18.0 Release Qwest/CLEC Overview and the Combined Overview & IMA EDI Disclosure Documentation Walkthrough for IMA EDI Release 18.0 Walkthrough Attendees Anders Ingemarson-Qwest, Angela Stewart-Qwest, Angie Thompson-Wizor, Anne Robberson-Qwest, Brian Caywood-Qwest, Chris Terrell-AT&T, Chuck Anderson-Qwest, Cim Chambers-Qwest, Dave Schleicher-Qwest, Denise Martinez-Qwest, Diane Burt-AT&T, Dianne Friend-Time Warner, Gary Berroa-Qwest, John Sanclaria-Qwest, Judy DeRosier-Qwest, Lynn Stecklein-Qwest, Mark Coyne-Qwest, Mark Haynes-Qwest, Michael Lopez-Qwest, Michelle Thacker-Qwest, Pat Bratetic-Qwest, Russ Urevig-Qwest, Sandie Tekavec-Qwest, Shon Higer-Qwest, Stephanie Prull-Eschelon Introductions: Kyle Kirves began the meeting by taking attendance and announcing the meeting purpose. The meeting notice included copies of the agenda and the candidate overview document. Kyle explained that the walkthrough would cover the candidates, the candidate impacts to the associated documentation, and the IMA EDI Disclosure Documentation overview.

Functional Overview extracted from Notice: This SCR will allow IMA to recognize Custom Ringing USOCs RGG1A RGG1+, RGG2+, RGG3+, DRS1+, DRS2+, DRS3+, NLQ1+, NLQ2+, NLQ3+ as features associated to a Primary Number (PN), or as features associated to the main TN of an account if there is only one line on the CSR. IMA will use feature rules to allow Custom Ringing USOCs to be converted to another Product or Provider. Custom Ringing USOCs will be allowed to be entered in the Feature and Feature Detail Section of the Product Specific form following the standard feature rules for FA. Form Impacts: NA Products: Resale POTs, UNE-P POTs, Resale CTX 21, UNE-P CTX 21, Resale CTX, UNE-P CTX Activities: ACT V, Z, N, T FA of V, C, T, N, D

Walkthrough Discussion: Kyle Kirves reviewed the information provided in the candidate overview document circulated with the meeting agenda and the meeting notification announcement. Kyle opened the floor to Questions. Stephanie Prull asked if the candidate applied to QPP as well. Chuck Anderson confirmed that, yes, the candidate is applicable to QPP. Kyle asked about PCAT updates. Gary Berroa covered the changes to the Ordering PCAT.

- May 18, 2005 Systems CMP Meeting Discussion: Jill Martain-Qwest asked if there were any questions or comments regarding the IMA 18.0 Packaging, in attachment M. There were questions or comments brought forward.

April 19, 2005 Meeting Minutes Attendees: Sharon Van Meter-AT&T, Leo Dimitriadis-AT&T, Bishan Agrawal-AT&T, Susie Wells-Qwest, Peggy Esquibel Reed-Qwest, Carol McKenzie-Qwest, Anders Ingemarson-Qwest, Pam Harlan-Qwest

Peggy Esquibel Reed-Qwest stated that this meeting was requested to discuss this CR and see what AT&T was currently experiencing with this issue. Leo Dimitriadis-AT&T stated that this CR was submitted for multi-distinct ring features, which is currently supported via the Remarks field. Leo noted that this CR is asking to handle features with a USOC. Leo stated that AT&T is not currently experiencing this problem due to a special case. Sharon Van Meter-AT&T stated that AT&T does no currently have this problem due to a workaround. Sharon stated that they need this enhancement so that the information would no longer need to be place in Remarks. Pam Harlan-Qwest asked what AT&T was putting in the Remarks field for Feature Activity. Anders Ingemarson-Qwest asked for a current example or scenario. Sharon Van Meter-AT&T stated that she does have a recent LSR example and will send it to Peggy (Esquibel Reed-Qwest). Susie Wells-Qwest asked to confirm if AT&T was requesting to be able to do an FA of N for new. Leo Dimitriadis-AT&T stated that they want similar to any other feature. Susie Wells-Qwest asked if the workaround could be bypassed in order to issue a Custom Ringing LSR. Leo Dimitriadis-AT&T stated that in order to bypass the workaround; AT&T would need coding on their side. Leo stated that Custom Ringing is automatically handled via the Remarks field. Susie Wells-Qwest asked if the workaround was hard coded in their EDI process and cannot manually be bypassed. Leo Dimitriadis-AT&T said that was correct. Leo then asked for the status of this CR. Carol McKenzie-Qwest stated that this CR is the #5 ranked CR, as a result of the 18.0 Prioritization. Leo Dimitriadis-AT&T stated that AT&T was moving to IMA 18.0 in November/December. Sharon Van Meter-AT&T asked that when this CR is implemented, if it would work as requested. Anders Ingemarson-Qwest stated yes There were no additional questions or comments.

- February 16, 2005 Systems CMP Meeting Discussion: Sharon Van Meter-AT&T stated that AT&T rates this CR as medium. Jill Martain-Qwest said that Qwest rates this CR as high. Bonnie Johnson-Eschelon said that Eschelon rates this CR as high.

-- July 22, 2004 Systems CMP Meeting Discussion: Jill Martain/Qwest stated that Qwest would distribute the ballot on July 27th, it is due back to Qwest on July 30th, and Qwest would email the initial prioritization list to the CLECs on August 3rd. There were no questions. Donna Osborne-Miller/AT&T stated that this was low for AT&T.

- February 19, 2004 Systems CMP Meeting Discussion Excerpt (Attachments H & J): Judy Schultz/Qwest stated that she wanted to provide an update to the funding approval process that was discussed in the January CMP Systems Meeting. Judy referred everyone to Attachment J in the Distribution Package. She stated that all CRs are being re-evaluated and must be approved. Judy said that CRs could not be scheduled without approval. Judy stated that the CRs with an impact to the IMA interface would follow the existing prioritization process. Judy noted that the funding for IMA 15.0 and IMA 16.0 has been approved, as well as funding to begin work on IMA 17.0.

- January Systems CMP Meeting Discussion: Donna Osborne-Miller/AT&T stated that this is a low priority for AT&T Consumer and a high priority for AT&T business.

August 21, 2003 Systems CMP Meeting Discussion: Phyllis Burt/AT&T stated that their interest was moderate.

May 22, 2003 Systems CMP Meeting Discussion: Donna Osborne-Miller/AT&T reviewed the CR description. Kit Thomte/Qwest asked if there were any question for this CR. Bonnie Johnson/Eschelon stated that she strongly supports this CR and requested to expand the Products to include all Resale and all UNE-P. Mallory Paxton/Qwest stated that she would also like to have the products expanded. Kit Thomte/Qwest stated that this CR would move to Presented status. (The Level of Effort for this request is 1500 to 2500 hours with no SATE impacts)

CLARIFICATION MEETING - APRIL 10, 2003 ATTENDEES: Donna Osborne-Miller/AT&T, Phyllis Burt/AT&T, Peggy Esquibel-Reed/Qwest, Lynn Stecklein/Qwest, Laurel Nolan/Qwest, Mark Early/Qwest, John Gallegos/Qwest, Lee Gomez/Qwest, Wendy Green/Qwest, Terri Kilker/Qwest, Berkley Loggie/Qwest, Shonna Pasionek/Qwest, Anne Robberson/Qwest, Phyllis Sunins/Qwest, Jo Wees/Qwest REVIEW REQUESTED DESCRIPTION OF CHANGE: Peggy Esquibel-Reed/Qwest reviewed the CR description: Currently the PCAT provides Ordering Instructions for all of the UNEP Features stated in the UNE-P Features Matrix (http://www.qwest.com/wholesale/clecs/features/unepfeatures.html). Based on the current PCAT for Custom Ringing Service (last updated: September 10, 2002) a CLEC should be able to order Custom Ringing Service using the FA (Feature Activity), FEATURE and FEATURE DETAIL fields. However, during testing we received the following error messages :"RESALE Form:Service Details Section 1:Features Section: Can not convert or change USOC(s) not already on the account: RGGxx not on the account". We were instructed that this was not a defect, and this is how the system works for this particular item. AT&T is requesting the support of Custom Ringing Service using the Feature Activity, Feature and Feature Detail fields. Peggy Esquibel-Reed/Qwest asked AT&T if they had information or additional clarification. Donna Osborne-Miller and Phyllis Burt/AT&T stated that they had no additional information regarding the request. CONFIRMATION OF IMPACTED INTERFACE: Peggy Esquibel-Reed/Qwest asked if this request is for IMA EDI only. It was stated that the interface should reflect IMA Common. CONFIRMATION OF IMPACTED PRODUCTS: Peggy Esquibel-Reed/Qwest asked if the product was only UNE-P. Phyllis Burt/AT&T stated that the product is UNE-P POTS. Donna Osborne-Miller/AT&T stated that the CLEC Community, at the Monthly CMP Meeting, may ask for this to be for all products. CR DISCUSSION: Peggy Esquibel-Reed/Qwest asked the Qwest participants if there were any questions for this request. Jo Wees/Qwest stated that she had no questions. John Gallegos/Qwest stated that he had no questions. ACTION PLAN: Peggy Esquibel-Reed/Qwest stated that AT&T will present this CR at the May Systems CMP Meeting. There were no additional question or comments. Tha call was concluded.

CenturyLink Response

DRAFT RESPONSE

May 6, 2003

RE: SCR040403-02 Support Custom Ringing Service via the LSR fields

Qwest has reviewed the information submitted as part of Change Request SCR040403-02.. Based upon the scope of this CR as agreed to in the Clarification Meeting (held April 10, 2003) Qwest is able to provide an estimated Level of Effort (LOE) of 1500 to 2500 hours for this IMA Change Request with no SATE impacts..

At the May Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request.

This Change Request is eligible for the IMA 15.0 Prioritization.

Sincerely, Qwest

Information Current as of 1/11/2021