Archived System CR SCR040303-02IG Detail

 
Title: EXACT Upgrade ASOG 27
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR040303-02IG Completed
10/16/2003
-   6/ Billing SS7 Link, Switched, PLT
Originator: Veik, Gary
Originator Company Name: Qwest Corporation
Owner: Notarianni, Lynn
Director:
CR PM: Esquibel-Reed, Peggy
Description Of Change
In order to comply with national industry standards as directed by OBF, this CR seeks to implement ASOG 27 on September 15, 2003. All companies involved with the ASR process would need to convert to ASOG 27 on this date.

The EXACT application needs to be updated to support ASOG 27 changes. Telcordia manages the development effort.

The anticipated timeline to be followed for this CR can be found on the Qwest OSS Release Calendar at:

http://www.qwest.com/wholesale/cmp/osscalendar.html

The key anticipated dates are:

July 2, 2003 Draft Technical Specifications Issued

July 2, 2003 Comment cycle starts

July 20, 2003 Comment cycle ends

July 30, 2003 Final Technical Specifications Issued

August 14, 2003 Testing Available

September 13, 2003 Planned Release Production Date

Status History

Date Action Description
4/3/2003 CR Submitted  
4/3/2003 CR Acknowledged  
4/4/2003 Clarification Meeting Scheduled  
4/8/2003 Clarification Meeting Held  
5/19/2003 Status Changed Status changed to clarification 
5/22/2003 Discussed at Monthly CMP Meeting Discussed at the May Systems CMP Monthly meeting; please see May Systems CMP Distribution Package, Attachment D 
7/3/2003 Communicator Issued SYST.07.03.03.F.04340.ASR_Draft_Tech_Specs 
8/1/2003 Communicator Issued SYST.08.01.03.F.04354.ASRFinalTechSpec 
8/21/2003 Discussed at Monthly CMP Meeting Discussed at the August Systems CMP Monthly Meeting; please see August Systems CMP Distribution Package, Attachment L 
9/18/2003 Status Changed Status Changed to CLEC Test due to 9/15/03 Deployment. 
9/18/2003 Discussed at Monthly CMP Meeting Discussed at the September Systems CMP Monthly Meeting; please see September Systems CMP Distribution Package, Attachment L 
10/16/2003 Discussed at Monthly CMP Meeting Discussed at the October Systems CMP Monthly Meeting; please see October Systems CMP Distribution Package, Attachment G 

Project Meetings

October 16, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this effort deployed on September 15, 23003 and that Qwest was ready to close the CR. There were no questions or comments. This CR is Completed.

- September 18, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this request was implemented on 9/15/03 and that we have IXCs in production. The status will be changed to CLEC Test.

- August 21, 2003 Systems CMP Meeting Discussion: Lynn Notarianni/Qwest stated that this CR is targeted for September 15th deployment. There were no questions or comments.

- May 22, 2003 Systems CMP Meeting Discussion: Lynn Notarianni/Qwest stated that this is an ASOG standard release and is targeted for implementation on September 15, 2003. Lynn stated that it is on the OSS Release calendar and that it is being implemented according to OBF guidelines. Lynn stated that we are bringing this forward so everyone is aware of it. Lynn stated that she can provide more information if anyone is interested. Kit Thomte/Qwest asked if there were any questions. There were none brought forward.

April 8, 2003 Clarification: There were no questions or comments.

CenturyLink Response

Draft Response

April 22, 2003

This is a Telcordia development effort. Qwest will implement this change on September 15, 2003 to support the Industry Standards through OBF. Information is available on the OBF website (http://www.atis.org) for use by all interested parties.

Sincerely, Qwest