Description Of Change |
The TELIS application needs to be updated to support ASOG 27 changes as managed by OBF. The ASOG 27 release is scheduled forSeptember 15, 2003. Changes are not product specific and encompass a number of screen and field changes.
Qwest is not deviating from the industry guidelines.
Details of this release can be found at: http://www.atis.org/atis/clc/obf/obfhom.htm
The anticipated timeline to be followed for this CR can be found on the Qwest OSS Release Calendar at:
http://www.qwest.com/wholesale/cmp/osscalendar.html
The key anticipated dates are: August 16, 2003 Draft Release Notes Issued August 16, 2003 Comment cycle starts August 19, 2003 Comment cycle ends August 23, 2003 Final Release Notes Issued September 13, 2003 Planned Release Production Date
|
Status History |
Date | Action | Description |
4/3/2003 | CR Submitted | |
4/3/2003 | CR Acknowledged | |
4/4/2003 | Clarification Meeting Scheduled | |
4/8/2003 | Clarification Meeting Held | |
4/28/2003 | Status Changed | Status changed to clarification |
5/22/2003 | Discussed at Monthly CMP Meeting | SCR040303-01IG Discussed at May Monthly Systems Meeting - See Distribution Package May - Attach D |
5/23/2003 | Status Changed | Status changed to presented |
7/17/2003 | Status Changed | Status changed to development |
10/7/2003 | Status Changed to CLEC Test due to 9/18/03 Deployment. | |
10/16/2003 | Discussed at Monthly CMP Meeting | Discussed at the Oct CMP Systems Meeting - See Attachment G |
10/17/2003 | Status Changed | Status changed to completed |
Project Meetings |
10/16/03 CMP Systems Meeting Connie Winston/Qwest stated that this CR was implemented 9/15/03 and that Qwest is ok to close. 9/18/03 CMP Systems Meeting Connie Winston/Qwest stated that this request was implemented on 9/15/03 and that we have IXCs in production. The status will be changed to CLEC Test. 8/21/03 CMP Systems Meeting Lynn Notarianni/Qwest stated that this CR is targeted for September 15th deployment. There were no questions or comments. 5/22/03 CMP Systems Meeting Lynn Notarianni/Qwest reviewed the description of the CR and stated that this is an ASOG standard releases. September 15th, 2003 is the targeted implementation date and is noted on the OSS Release calendar. Kit Thomte/Qwest asked if there were any questions or comments. There were no questions.
|
CenturyLink Response |
Draft Response April 22, 2003 This is a Telcordia development effort. Qwest will implement this change on September 15, 2003 to support the Industry Standards through OBF. Information is available on the OBF website (http://www.atis.org) for use by all interested parties. Sincerely, Qwest
|