Archived System CR SCR031402-01 Detail |
Title: CEMR Feature Verification | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR031402-01 |
Completed 5/16/2002 |
200 - 750 | 5/ | Other |
Originator: Thompson, Jeff |
Originator Company Name: Qwest Corporation |
Owner: Thompson, Jeff |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
The Feature Verification function in CEMR needs to be expanded to allow for CSR filtering. Currently the expansive CSR data (for example, 100 pages in size) is returned and the User is required to scroll through to locate the requested Working Telephone Number (WTN) in question. Therefore, this system enhancement would improve the useability of this function.
Filtering will occur at the requested WTN level of the CSR data. The CEMR User's Guide and the CEMR training will be updated to reflect this increased functionality.
|
Status History |
Date | Action | Description |
3/14/2002 | CR Submitted | CR submitted |
3/14/2002 | CR Acknowledged | CR acknowledged |
3/15/2002 | Additional Information | CR will be presented at the March CMP meeting |
3/18/2002 | Status Changed | Status changed to clarification |
3/21/2002 | Discussed at Monthly CMP Meeting | SCR031402-01 discussed March Systems CMP Monthly meeting; please see Systems CMP Distribution Package March CMP - Attachment D |
3/22/2002 | Status Changed | Status updated from 'Clarification' to 'Development' |
4/18/2002 | Discussed at Monthly CMP Meeting | |
5/7/2002 | Status Changed | Deployed 5/5/02 Status changed to CLEC test |
5/16/2002 | Status Changed | Status changed to completed |
5/16/2002 | Discussed at Monthly CMP Meeting | SCR031402-01 discussed at May Systems CMP Monthly meeting; please see Systems CMP Distribution Package May CMP - Attachment F |
Project Meetings |
5/16/02 Systems CMP Meeting The CR was deployed in the 5/5/02 CEMR release. The status of this CR will be changed to completed. 4/18/02 - Dan Busetti/Qwest reviewed CR and stated that the change will only bring back information for the requested telephone number. 3/21/02 CMP Systems meeting Jeff Thompson/Qwest indicated that the requirements for this CR were worked out in a previous CMP meeting. This CR would allow CEMR to handle large CSRs as IMA does. Jeff indicated that Qwest would like to get this change into the May release. He asked if Qwest could get approval from the CLECs that were present to do this. The CLECs agreed.
|
CenturyLink Response |
The level of effort for this CR is 200-750 hours and the targeted implementation date is 5/5/02.
|