Archived System CR SCR031203-05 Detail |
Title: Add Print Capability for Feature Verification in CEMR. | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR031203-05 |
Completed 12/17/2003 |
500 - 1500 | 5/ | Maintenance / Repair | All |
Originator: Busetti, Dan |
Originator Company Name: Qwest Corporation |
Owner: Notarianni, Lynn |
Director: |
CR PM: Esquibel-Reed, Peggy |
Description Of Change |
Currently, in order for CLECs to print data from CEMR in the Feature Verification Screens, they must print from their browsers. This CR will provide application print capability for Feature Verification.
|
Status History |
Date | Action | Description |
3/12/2003 | CR Submitted | |
3/14/2003 | CR Acknowledged | |
3/14/2003 | Clarification Meeting Held | |
4/17/2003 | Discussed at Monthly CMP Meeting | SCR031203-05 discussed at April Systems CMP Monthly meeting; please see April Systems CMP Distribution Package, Attachment C. |
6/19/2003 | Discussed at Monthly CMP Meeting | Discussed at the June Systems CMP Monthly meeting; please see June Systems CMP Distribution Package, Attachment J |
8/21/2003 | Discussed at Monthly CMP Meeting | Discussed at the August Systems CMP Monthly Meeting; please see August Systems CMP Distribution Package, Attachment I |
10/16/2003 | Discussed at Monthly CMP Meeting | Discussed at the October Systems CMP Monthly Meeting; please see October Systems CMP Distribution Package, Attachment L |
10/17/2003 | Communicator Issued | SYST.10.17.03.F.04406.CEMR2DrftGUI |
10/24/2003 | Communicator Issued | SYST.10.24.03.F.04411.CEMRFinRlNotes |
11/14/2003 | Communicator Issued | PROS.11.14.03.F.01045.CEMR_UserGuide |
11/17/2003 | Communicator Issued | SYST.11.17.03.F.01061.CEMR2Rel_UpdateUseGuide |
11/17/2003 | Status Changed | Status Changed to CLEC Test Due to November 17, 2003 Deployment. |
11/20/2003 | Discussed at Monthly CMP Meeting | Discussed at the November Systems CMP Monthly Meeting; please see November Systems CMP Distribution Package, Attachment L |
12/17/2003 | Discussed at Monthly CMP Meeting | Discussed at the December Systems CMP Monthly Meeting; please see December Systems CMP Distribution Package, Attachment G. |
Project Meetings |
December 17, 2003 Systems CMP Meeting Discussion: Lynn Notarianni/Qwest noted that this CR was implemented on November 17th and stated that there were no open trouble tickets on this CR. Lynn noted that Qwest was ok with closing this CR unless anyone had any questions or concerns with it. There were no questions or concerns brought forward. The status of this CR will move to Completed status.
November 20, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR was deployed on November 17, 2003 and is now in CLEC Test.
-- October 16, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR is scheduled to deploy in the November 17th CEMR Release.
- August 21, 2003 Systems CMP Meeting Discussion Lynn Notarianni/Qwest stated that this Action Item is to communicate the revision to the Title and description. Lynn noted that this CR is specific for the feature verification part of CEMR. There were no questions or comments.
- June 19, 2003 Systems CMP Meeting Discussion: Beth Foster/Qwest stated that CEMR CR’s, listed below, previously targeted for release in December, have moved up to a targeted date of November 17, 2003. SCR010203-01 CEMR Time to Reflect Either the Central, Mountain, or Pacific Time Zone (originated by Eschelon) SCR031203-03 CEMR Screen Updates (originated by Qwest) SCR031203-04 Simplify User Circuit Entry for Design Circuits in CEMR (originated by Qwest) SCR031203-05 Add Print Capability to CEMR (originated by Qwest) There were no questions or comments.
April 17, 2003 Systems CMP Meeting Discussion: Lynn Notarianni/Qwest reviewed the CR description and noted that the Level of Effort is 500 – 1500 hours. Lynn stated that this CR is targeted for December implementation. Dan Busetti/Qwest stated that currently when you print out of CEMR, you get a print of the entire browser window. Dan stated that this CR would allow you to print what is showing in CEMR, not the entire browser window. Lynn Notarianni/Qwest stated that due to the complexity of these changes, they won’t happen until later in the year, but we wanted to get these in front of you, so you would know that they are coming. There were no questions or comments.
Clarification Meeting - March 14, 2003 Attendees: Dan Busetti/Qwest, Kathy Garcia/Qwest, and Peggy Esquibel-Reed/Qwest Reviewed Description of Change: Currently to print data from CEMR, CLECs must print from their browsers. This CR will allow application print instead of browser print. Confirmed Interface: CEMR Confirmed Products: All There were no questions or comments. Action Plan: Qwest will present CR at the April Systems CMP Meeting scheduled for April 17, 2003.
|
CenturyLink Response |
DRAFT RESPONSE March 26, 2003 RE: SCR031203-05 (Add Print Capability to CEMR) Qwest has reviewed the information submitted as part of Change Request SCR031203-05. Based upon the scope of this CR as agreed to in the Clarification Meeting (held March 14, 2003) Qwest is able to provide an estimated Level of Effort (LOE) of 500 to 1500 hours for this CEMR Change Request and is currently targeting an implementation date of December 8, 2003 At the next Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request. Sincerely, Qwest
|
Information Current as of 1/11/2021