Archived System CR SCR031203-03 Detail

 
Title: CEMR Screen Updates
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR031203-03 Completed
12/17/2003
2000 - 3000   5/ Maintenance / Repair All
Originator: Busetti, Dan
Originator Company Name: Qwest Corporation
Owner: Notarianni, Lynn
Director:
CR PM: Esquibel-Reed, Peggy
Description Of Change
As functionality is migrated to the new platform, the CEMR screens will be developed to incorporate enhanced screen appearances and navigation. This effort will include an upgrade to Netscape 7.1. Either Netscape 7.1 or Internet Explorer will be able to be used for access to CEMR.

Status History

Date Action Description
3/12/2003 CR Submitted  
3/14/2003 CR Acknowledged  
3/14/2003 Clarification Meeting Held  
4/17/2003 Discussed at Monthly CMP Meeting SCR031203-03 discussed at April Systems CMP Monthly meeting; please see April Systems CMP Distribution Package, Attachment C. 
6/19/2003 Discussed at Monthly CMP Meeting Discussed at the June Systems CMP Monthly meeting; please see June Systems CMP Distribution Package, Attachment J 
7/17/2003 Discussed at Monthly CMP Meeting Discussed at July Systems CMP Monthly Meeting; please see July Systems CMP Distribution Package -- Attachment I 
10/16/2003 Discussed at Monthly CMP Meeting Discussed at the October Systems CMP Monthly Meeting; please see October Systems CMP Distribution Package, Attachment L 
10/17/2003 Communicator Issued SYST.10.17.03.F.04406.CEMR2DrftGUI 
10/24/2003 Communicator Issued SYST.10.24.03.F.04411.CEMRFinRlNotes 
11/14/2003 Communicator Issued PROS.11.14.03.F.01045.CEMR_UserGuide 
11/17/2003 Communicator Issued SYST.11.17.03.F.01061.CEMR2Rel_UpdateUseGuide 
11/17/2003 Status Changed Status Changed to CLEC Test Due to November 17, 2003 Deployment. 
11/20/2003 Discussed at Monthly CMP Meeting Discussed at the November Systems CMP Monthly Meeting; please see November Systems CMP Distribution Package, Attachment L 
12/17/2003 Discussed at Monthly CMP Meeting Discussed at the December Systems CMP Monthly Meeting; please see December Systems CMP Distribution Package, Attachment G. 

Project Meetings

December 17, 2003 Systems CMP Meeting Discussion: Lynn Notarianni/Qwest noted that this CR was implemented on November 17th and stated that there were no open trouble tickets on this CR. Lynn noted that Qwest was ok with closing this CR unless anyone had any questions or concerns with it. There were no questions or concerns brought forward. The status of this CR will move to Completed status.

- November 20, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR was deployed on November 17, 2003 and is now in CLEC Test.

-- October 16, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR is scheduled to deploy in the November 17th CEMR Release.

July 17, 2003 Systems CMP Meeting Discussion: Lynn Notarianni/Qwest stated that this effort is targeted for the November CEMR Release and will upgrade to Netscape 7.1. Lynn noted that the CR would be revised to indicate that the CLECs would be able to access CEMR with either Netscape 7.1 or with Internet Explorer. There were no questions or comments. This Action Item is Closed.

-- June 19, 2003 Systems CMP Meeting Discussion: Beth Foster/Qwest stated that CEMR CR’s, listed below, previously targeted for release in December, have moved up to a targeted date of November 17, 2003. SCR010203-01 CEMR Time to Reflect Either the Central, Mountain, or Pacific Time Zone (originated by Eschelon) SCR031203-03 CEMR Screen Updates (originated by Qwest) SCR031203-04 Simplify User Circuit Entry for Design Circuits in CEMR (originated by Qwest) SCR031203-05 Add Print Capability to CEMR (originated by Qwest) There were no questions or comments.

-- April 17, 2003 Systems CMP Meeting Discussion: Lynn Notarianni/Qwest presented this CR and stated that as we change to new architectural capabilities, CEMR will become more useful to the CLECs. Lynn stated that CEMR is going through platform changes and that this is the first of several CRs that Qwest is bringing forward to reflect those changes. Lynn then noted that the Level of Effort for this change request is 2000 to 3000 hours and we are targeting implementation in December. There were no questions or comments.

-- Clarification Meeting - March 14, 2003 Attendees: Dan Busetti/Qwest, Kathy Garcia/Qwest, and Peggy Esquibel-Reed/Qwest

Reviewed Description of Change: As functionality is migrated to the new platform, the CEMR screens will be developed to incorporate enhanced screen appearances and navigation

Confirmed Interface: CEMR

Confirmed Products: All

There were no questions or comments.

Action Plan: Qwest will present CR at the April Systems CMP Meeting scheduled for April 17, 2003.

CenturyLink Response

DRAFT RESPONSE

March 26, 2003

RE: SCR031203-03 (CEMR Screen Updates)

Qwest has reviewed the information submitted as part of Change Request SCR031203-03. Based upon the scope of this CR as agreed to in the Clarification Meeting (held March 14, 2003) Qwest is able to provide an estimated Level of Effort (LOE) of 2000 to 3000 hours for this CEMR Change Request and is currently targeting an implementation date of December 8, 2003

At the next Monthly Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request.

Sincerely, Qwest