Archived System CR SCR030711-1 Detail |
Title: Modify Subsequent DSRED & Re DSRED to include LOC Contact Info in REMARKS field. | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR030711-1 |
Completed 12/14/2011 |
600 - 800 | 3/31 |
Originator: Gomez, Lee |
Originator Company Name: Qwest Corporation |
Owner: Gomez, Lee |
Director: |
CR PM: Lorence, Susan |
Description Of Change |
Modify IMA to include the LOC OS contact information in the REMARKS section of the DSRED, from their IMA Accouont Profile. This would include the Name, TN, email address and fax # and would be provided on all Subsequent DSREDs & ReDSREDs.
An Initial Directory Service Error & Confirmation (DSRED) is provided for every FBDL IMA order processed and subsequent DSREDs are required for various DSRED statuses. Frequently, the CLEC has questions ror requires clarification regarding the DSRED remarks or comments entered by the Listing Operations Center (LOC) Order Specialist (OS) but doesn't know who to contact. Automating this process will ensure LOC contact information is always included on the appropriate DSREDs.
|
Status History |
Date | Action | Description |
3/7/2011 | CR Submitted | CR Submitted |
3/9/2011 | CR Acknowledged | CR Acknowledged |
3/16/2011 | Status Changed | Status changed to Presented |
3/16/2011 | Discussed at Monthly CMP Meeting | Discussed at the March System CMP Meeting - See Attachment F in the Distribution Package |
4/15/2011 | Status Changed | Status changed to Packaged |
4/20/2011 | Discussed at Monthly CMP Meeting | Discussed at the April System CMP Meeting - See Attachment J in the Distribution Package |
5/18/2011 | Discussed at Monthly CMP Meeting | Discussed at the May System CMP Meeting - See Attachment J in the Distribution Package |
5/18/2011 | LOE Issued | LOE received from IT of 600-800 hours. |
8/5/2011 | Communicator Issued | See notice number SYST.IMAS.08.05.11.F.09327.IMAXML_31.0DrftTechSpecs |
9/2/2011 | Communicator Issued | See notice number SYST.IMAS.09.02.11.F.09449.IMAXML31.0FinalTechSpecs |
9/19/2011 | Communicator Issued | See notice number SYST.IMAS.09.19.11.F.09491.IMAGUI_Rel31.0_DraftDocs |
9/26/2011 | Communicator Issued | See notice number SYST.IMAS.09.26.11.F.09522.IMAGUIRel31.0Fnl_RelNotes |
10/17/2011 | Status Changed | Status changed to CLEC Test |
11/16/2011 | Discussed at Monthly CMP Meeting | Discussed at the November System CMP Meeting - See Attachment G in the Distribution Package |
12/14/2011 | Status Changed | Status changed to Completed. |
12/14/2011 | Status Changed | Discussed at the December System CMP Meeting - See Attachment G in the Distribution Package |
Project Meetings |
12/14/11 Systems CMP Meeting Mark Coyne – CenturyLink identified that there was a list of CRs to be considered for closure. He said the CRs were included in the IMA Release on 10/17/11 and were in CLEC test. Mark said there was a mid cycle conversion on November 19 and asked that all of these CRs be considered for closure. There were no objections. 11/16/11 Systems CMP Meeting Mark Coyne – CenturyLink said all of these relate to IMA Release 31 that went in on 10/17/11. Steph Prull – Integra asked that the following be left open: SCR012511-1, SCR012511-2, SCR012511-3, and SCR083010-1. PAETEC is moving to IMA 31.0 Release this weekend. Mark Coyne – CenturyLink said we would likely leave all of the CRs open. 5/18/11 Systems CMP Meeting Mark Coyne – Qwest relayed that the LOE for this CR had been received and it is 600-800 hours. 4/20/11 Systems CMP Meeting Mark Coyne – Qwest referred to the CRs that were packaged for IMA Release 31.0 for October 3/16/11 System CMP Meeting Lee Gomez – Qwest presented the CR for FBDL customers to automate providing the Listing Operations Center (LOC) contact information which is done manually today. Qwest has found that the information is sometimes not provided and so when the CLEC receives the Directory Service Error & Confirmation (DSRED), they do not know whom to call. This CR will take the IMA user profile and always provide that information so the customer has it available. Lee asked if there were any questions and there were none. The walk-on CR just presented by Lee Gomez would be considered a candidate as well. Mark said we will not likely need to go through the prioritization process unless the LOE for the new walk-on CR came back high.
|
CenturyLink Response |
|
Information Current as of 1/11/2021