Description Of Change |
Eliminate the current process of issuing manual FBDL requests via email. Allow the CLECs to issue LSRs with complete fields and using the Manual Indicator field. Corrective action will be taken and a mechanized LR (previously DSRED) will be generated. (CR Description REVISED 03-20-14)
Original Description -- Eliminate the current process of issuing manual FBDL requests via email. Allow the CLECs to issue LSRs with complete fields and using the Manual Indicator field. Corrective action will be taken and a mechanized DSRED will be generated.
|
Status History |
Date | Action | Description |
3/5/2014 | CR Submitted | CR Submitted. |
3/7/2014 | CR Acknowledged | CR Acknowledged. |
3/19/2014 | Status Changed | CR Status changed to Presented. |
3/19/2014 | Discussed at Monthly CMP Meeting | Discussed at the March Systems CMP Meeting - See Attachment C in the Distribution Package. |
3/20/2014 | Record Update | CR Description revised at request of originator - per discussion at monthly CMP meeting. |
4/11/2014 | Status Changed | Status changed to Packaged. |
4/11/2014 | LOE Issued | LOE issued of 1400-1600 hours. |
4/16/2014 | Discussed at Monthly CMP Meeting | Discussed at the April Systems CMP Meeting - See Attachment I in the Distribution Package. |
8/8/2014 | Communicator Issued | See notice number SYST.IMAS.08.08.14.F.12561.IMAXML37.0DraftTechSpecs. |
8/8/2014 | Status Changed | Status changed to Development. |
8/13/2014 | Communicator Issued | See notice number CMPR.CMPP.08.13.14.F.12595.DrftJobAidReviewSCR022814. |
9/5/2014 | Communicator Issued | See notice number SYST.IMAS.09.05.14.F.12562.IMAXML37.0FinalTechSpecs. |
9/22/2014 | Communicator Issued | See notice number SYST.IMAS.09.22.14.F.12712.IMAGUI_Rel37.0_DraftDocs. |
9/29/2014 | Communicator Issued | See notice number SYST.IMAS.09.29.14.F.12713.IMAGUIRel37.0Fnl_RelNotes. |
10/15/2014 | Discussed at Monthly CMP Meeting | Discussed at the October Systems CMP Meeting - See Attachment K in the Distribution Package. |
10/20/2014 | Status Changed | Status changed to CLEC Test. |
11/19/2014 | Discussed at Monthly CMP Meeting | Discussed at the November Systems CMP Meeting - See Attachment G in the Distribution Package. |
12/17/2014 | Status Changed | Status changed to Completed. |
12/17/2014 | Discussed at Monthly CMP Meeting | Discussed at the December Systems CMP Meeting - See Attachment G in the Distribution Package. |
Project Meetings |
12/17/2014 Monthly Systems CMP Meeting SCR022814-1 Allow FT for converting or changing from stand alone services (HSI/Broadband) to POTS or vice versa SCR030514-1 Activate the LSR.MANUALINDICATOR field for FBDL Mark Coyne – CenturyLink said these two CRs are associated with IMA Release 37.0 which was implemented October 20, 2014. Two CLECs migrated to the release on November 22, 2014. Mark said we are not aware of any concerns and asked if the CRs could be moved to a Completed Status. There were no objections. 11/19/2014 Monthly Systems CMP Meeting Mark Coyne – CenturyLink relayed these CRs deployed in IMA Release 37.0 which was implemented October 20, 2014. There are currently two CLECs tentatively scheduled to migrate to this IMA release on November 22, 2014. Mark said the next migration dates are January 24, 2015 and March 21, 2015. We will revisit closing these CRs in December. 10/15/2014 Monthly Systems CMP Meeting Mark Coyne – CenturyLink said for both of these CRs associated with IMA Release 37.0, the application to application testing was available via SATE as of September 20, 2014. This IMA release has a deployment date of October 20, 2014. 4/16/2014 Monthly Systems CMP Meeting Mark Coyne – CenturyLink relayed the CR was revised per discussion in the March CMP meeting. The Description was updated to indicate the LR form was previously DSRED. Mark Coyne – CenturyLink asked if there were any questions. There were none. 3/19/2014 Monthly Systems CMP Meeting Denise Martinez – CenturyLink presented this new CR associated with IMA. Denise said the change to eliminate email. Kim Isaacs – Integra asked if it would be called DSRED after the release. Lee Gomez – CenturyLink said it will be called Local Response. Denise Martinez – CenturyLink said the CR would be updated to reflect that. Denise asked if there were any questions. There were none.
|