Wholesale: Products & Services

Archived System CR SCR022703-15 Detail

 
Title: Resolve Production Issue with BA field
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR022703-15 Withdrawn
2/27/2003
2450 - 4075   3/ Pre-order UNE-P POTS
Originator: Osborne-Miller, Donna
Originator Company Name: AT&T
Owner: Winston, Connie
Director:
CR PM: Nolan, Laurel
Description Of Change
QWEST currently does not have a method of adding and deleting blocking on one order using the current BA and BLOCK fields. QWEST supports the following BLOCK ACTIVITY (BA) field values: A (ADD), D (DELETE), N (NO CHANGE) and Z (REMOVE ALL BLOCKING).

AT&T is requesting that QWEST support a valid value of E (END STATE) allowing us to indicate the end state of on subsequent change orders. This will allows us to add and delete blocking within one order (BA = E) instead of sending two orders - one to specify the deletion (BA = D) and another to specify the addition (BA = A). The new BA value of E will in fact behave like a combination of Z (remove all blocking) and A(add) all on one order.

Expected Deliverables/Proposed Implementation Date (if applicable): To be compatible with 14.0.

Status History

Date Action Description
2/27/2003 CR Submitted  
2/28/2003 CR Acknowledged  
3/3/2003 CR Posted to Web  
3/3/2003 Info Received From CLEC  
3/6/2003 Clarification Meeting Scheduled  
3/12/2003 Clarification Meeting Held  
3/20/2003 Status Changed CR withdrawn by AT&T 
3/20/2003 Discussed at Monthly CMP Meeting CMP March Meeting, see meeting minutes 

Project Meetings

Clarification Meeting March 12, 2003 9:00-11:00 AM

Attendees: Donna Osborne-Miller- AT&T, Phyllis Bert-AT&T, Regina Mosley-AT&T, Carla Pardee-AT&T, Diane Burt-AT&T, John Blaszczyk- AT&T, Peggy Esquible-Reed-Qwest, Lynn Stecklein-Qwest, John Gallegos-Qwest, Wendy Green-Qwest, Berkley Loggie-Qwest, Monica Martin-Qwest, Jan Martin-Qwest, Denise Martinez-Qwest, Shelley Mason-Qwest, Rob Mitchell-Qwest, Laurel Nolan-Qwest, Shonna Pasionek-Qwest, Mallory Paxton-Qwest, Joan Pfeffer-Qwest, Deb Roth-Qwest, Carl Sear-Qwest, Kerri Waldner-Qwest, Scott Carne-Qwest

Esquible-Reed-Qwest reviewed the CR title and the Description of Change. She asked if there were any additions, changes or questions. Paxton-Qwest stated that the team could analyze if this CR could be incorporated into the Qwest CR. She stated that there might be a manual work around that could be used, but not as the long term solution. Mosley-AT&T asked about the manual work around. Paxton-Qwest stated that Qwest was currently working on PCAT updates and that the appropriate notice would be distributed. Pardee-AT&T asked when the notification would come out. Paxton-Qwest stated that she thought it would be within the next week and that a Level 3 notice would be issued with a comment cycle. She continued that the Qwest CR provided a mechanized solution.

Esquible-Reed-Qwest asked if there were any changes to the CR. No changes or additions were given.

Clarification Call completed.

CenturyLink Response

DRAFT RESPONSE March 13, 2003

RE: SCR022703-15 Resolve Production Issue with BA field

Qwest has reviewed the information submitted as part of Change Request SCR022703-15. Based upon the scope of this CR as agreed to in the Clarification Meeting (held March 12, 2003) Qwest is able to provide an estimated Level of Effort (LOE) of 2450 to 4075 hours for this IMA Change Request.

At the March Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request.

This Change Request is eligible for the IMA 14.0 Prioritization.

Sincerely, Qwest

Information Current as of 1/11/2021