Archived System CR SCR022703-11 Detail |
Title: Support Flowthrough Testing combined withh VICKI response | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR022703-11 |
Completed 2/19/2004 |
600 - 700 | 20/14 | Pre-ordering, ordering | All |
Originator: Osborne-Miller, Donna |
Originator Company Name: AT&T |
Owner: Winston, Connie |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
Currently if a CLEC opts for FLOWTHROUGH Testing all subsequent activity after the FOC is manually generated. AT&T is requesting that Qwest support Flowthrough testing with the option of automatically system generated response by VICKI following the FOC.
|
Status History |
Date | Action | Description |
2/27/2003 | CR Submitted | |
2/28/2003 | CR Acknowledged | |
3/4/2003 | Clarification Meeting Scheduled | |
3/12/2003 | Clarification Meeting Held | |
3/12/2003 | Status Changed | Status changed to clarification |
3/13/2003 | Draft Response Issued | |
3/20/2003 | Discussed at Monthly CMP Meeting | CMP March Meeting, see meeting minutes |
4/17/2003 | Discussed at Monthly CMP Meeting | SCR277303-11 Discussed at April Systems CMP Monthly meeting; please see Systems CMP Distribution Package April |
4/28/2003 | Release Ranking | CR Ranking- SATE 14.0 Ranked #1 out of 6 |
7/9/2003 | Status Changed | Status changed to Packaged. Packaging released in July CMP Meeting. |
10/16/2003 | Discussed at Monthly CMP Meeting | Discussed at the October CMP Systems Meeting - See attachment I |
11/12/2003 | Status Changed | Status changed to CLEC Test |
11/20/2003 | Discussed at Monthly CMP Meeting | Discussed at the November CMP Systems Meeting - See attachment G |
12/17/2003 | Discussed at Monthly CMP Meeting | Discussed at the December CMP Meeting - See attachment G |
1/23/2004 | Discussed at Monthly CMP Meeting | Discussed at the January CMP Systems Meeting - See Attachment G |
2/19/2004 | Status Changed | Status changed to completed |
2/19/2004 | Discussed at Monthly CMP Meeting | Discussed at the February CMP Systems Meeting - See Attachment G |
Project Meetings |
2/19/04 CMP Systems Meeting Phyllis Burt/AT&T stated that this CR could be closed. 1/22/04 CMP Systems Meeting Donna Osborne-Miller/AT&T stated that she would like to keep this CR open until the February CMP Systems Meeting. 12/17/03 CMP Systems Meeting Donna Osborne-Miller/AT&T said that they were still testing and would like this CR to remain open. 11/20/03 CMP Systems Meeting Phyllis Burt/AT&T said that they are not there yet and Liz Balvin/MCI said that they have not reviewed yet either. This CR will remain in CLEC Test. Phyllis Burt/AT&T said that they are not there yet and Liz Balvin/MCI said that they have not reviewed yet either. This CR will remain in CLEC Test. 6/03 CMP Systems Meeting Connie Winston/Qwest stated that this CR will be deploying on November 8, 2003. 4/17/03 CMP Systems Meeting Phyllis Burt/AT&T reviewed the CR description and stated that VICKI is automated and that AT&T is requesting a combined automated process. Liz Balvin/MCI stated that MCI also sees a need for this since they have flowthrough capability in production. Liz asked if 600 – 700 hours is considered to be a big effort in SATE. Sue Stott/Qwest stated that it is a good size piece of work for SATE but doable. Kit Thomte/Qwest reviewed the prioritization instruction, included in the package. Kit stated that Qwest will distribute the Prioritization Form by 5 p.m. MT on April 22, 2003, the completed Prioritization forms are to be sent to cmpcr@qwest.com by 5 p.m. MT on April 25, 2003, and that Qwest would provide the Initial Prioritization List by 5 p.m. MT on April 29, 2003. Kit Thomte/Qwest asked if there were any questions regarding SATE prioritization. There were none. 3/20/03 CMP Systems Meeting Donna Osborne-Miller/AT&T reviewed this change request. Phyllis Burt/AT&T asked if this was the Change Request that Qwest referred to in the SATE discussion. Wendy Green/AT&T said that yes it is. She reviewed the change request and stated that the LOE is 600 to 700 hours and would be eligible for the 14.0 prioritization next month. Kit Thomte/Qwest said that the status will be changed to pending prioritization. 3/12/03 Clarification Call Introduction of Attendees Donna Osborne-Miller- AT&T, Phyllis Bert-AT&T, Regina Mosley-AT&T, Carla Pardee-AT&T, Diane Burt-AT&T, John Blaszczyk- AT&T, Peggy Esquible-Reed-Qwest, Lynn Stecklein-Qwest, John Gallegos-Qwest, Wendy Green-Qwest, Berkley Loggie-Qwest, Monica Martin-Qwest, Jan Martin-Qwest, Denise Martinez-Qwest, Shelley Mason-Qwest, Rob Mitchell-Qwest, Laurel Nolan-Qwest, Shonna Pasionek-Qwest, Mallory Paxton-Qwest, Joan Pfeffer-Qwest, Deb Roth-Qwest, Carl Sear-Qwest, Kerri Waldner-Qwest, Scott Carne-Qwest Review Requested Description of Change AT&T is requesting that Qwest support flowthrough testing with the option of automatically system generated response by VICKI following the FOC. Confirm Right Personnel Involved All appropriate SMEs and personnel were involved in the clarification call. Identify/Confirm CLECs Expectation AT&T is requesting that Qwest support flowthrough testing with the option of automatically system generated response by VICKI following the FOC. The interface was changed from IMA Common to SATE and the Products impacted changed to ALL. Identify any Dependent Systems Change Requests NA Establish Action Plan AT&T will present this change request in the March 20, 2003.
|
CenturyLink Response |
DRAFT RESPONSE March 13, 2003 RE: SCR022703-11 Qwest has reviewed the information submitted as part of Change Request SCR022703-11. Based upon the scope of this CR as agreed to in the Clarification Meeting (held March 12, 2003) Qwest is able to provide an estimated Level of Effort (LOE) of 600 to 700 hours for this SATE Change Request. At the March Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request. This Change Request is eligible for the 14.0 Prioritization. Sincerely, Qwest
|
Information Current as of 1/11/2021