Wholesale: Products & Services

Archived System CR SCR022503-01 Detail

 
Title: LSOG 7 Upgrade Field Numbering and Naming to Existing Qwest Forms & EDI Maps (FOUNDATION CANDIDATE)
CR Number Current Status
Date
Level of
Effort
Interface/
Release No.
Area
Impacted
Products
Impacted

SCR022503-01 Withdrawn
10/16/2003
5375 - 8975   3/15 Pre-Ordering, Ordering All
Originator: Winston, Connie
Originator Company Name: Qwest Corporation
Owner: Winston, Connie
Director:
CR PM: Esquibel-Reed, Peggy
Description Of Change
This Change Request is the "foundation" candidate for LSOG 7. This Change Request must be completed before all other LSOG 7 candidates.

Status History

Date Action Description
2/25/2003 CR Submitted  
2/25/2003 CR Acknowledged  
2/26/2003 Clarification Meeting Held  
3/13/2003 Qwest Response Issued  
3/20/2003 Discussed at Monthly CMP Meeting SCR022503-01 discussed at March Systems CMP Monthly meeting; please see Systems CMP Distribution Package March CMP. 
4/7/2003 Release Ranking 14.0 Prioritization- Ranked #42 out of 53 
4/17/2003 Discussed at Monthly CMP Meeting SCR022503-01 discussed at April Systems CMP Monthly meeting; please see April Systems CMP Distribution Package, Attachment N. 
4/29/2003 Release Ranking Rank changed due to Late Adders- Ranked #43 
5/30/2003 Release Ranking Rank changed due to Late Adders- Ranked #44 
7/9/2003 Status Changed Status changed to pending prioritization with release of I MA 14.0 Packaging. 
8/21/2003 Discussed at Monthly CMP Meeting Discussed at the August Systems CMP Monthly Meeting; please see August Systems CMP Distribution Package, Attachment P 
9/2/2003 Release Ranking 15.0 Prioritization- Ranked #56 out of 57 
9/29/2003 Release Ranking 15.0 Revised Prioritization, due to Late Adder - Ranked #57 out of 58 
10/16/2003 Discussed at Monthly CMP Meeting Discussed at the October Systems CMP Monthly Meeting; please see October Systems CMP Distribution Package, Attachment G 

Project Meetings

October 16, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that Qwest is withdrawing this request. There were no questions or comments. This CR is in Withdrawn Status.

- September 25, 2003: Connie Winston/Qwest requested withdrawal of her submitted CMP CR, SCR022503-01.

- August 21, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this CR was originally one of Qwest’s top choices, but that the Virtual CSR is now Qwest’s first choice. Liz Balvin/MCI recommended skipping LSOG 7, like SBC is doing, and recommended having the baseline candidate only. Connie Winston/Qwest stated that this could be discussed at September CMP.

- March 20, 2003 Systems CMP Meeting Discussion: Connie Winston/Qwest stated that this is the standard LSOG candidate. Connie stated that we firmly believe that if we don’t keep up with every LSOG issues, we at least keep up with the mapping. Connie stated that this CR doesn’t have to be in 14.0 but it will eventually be needed. Liz Balvin/WorldCom asked if this is the EDI upgrade. Connie Winston/Qwest stated yes, for LSOG7. Liz Balvin/WorldCom asked how this impacts LSOG 6, since Qwest is not compliant with LSOG 6. Connie Winston/Qwest stated that renumbering was done for LSOG 6, but that not all the LSOG 6 functionality has been done. Connie stated that when this gets voted in, Qwest will take into consideration when defining.

February 26, 2003 Clarification Meeting Attendees: Connie Winston/Qwest, Beth Foster/Qwest, Peggy Esquibel-Reed/Qwest CR Description: This Change Request is the "foundation" candidate for LSOG 7. This Change Request must be completed before all other LSOG 7 candidates. Impacted Interfaces: IMA EDI & GUI Impacted Products: All There were no questions or comments.

CenturyLink Response

DRAFT RESPONSE March 13, 2003

RE: SCR22503-01 LSOG 7 - Upgrade Field Numbering and Naming to Existing Qwest Forms & EDI Maps (FOUNDATION CANDIDATE)

Qwest has reviewed the information submitted as part of Change Request SCR22503-01. Based upon the scope of this CR as agreed to in the Clarification Meeting (held February 26, 2003) Qwest is able to provide an estimated Level of Effort (LOE) of 5375 to 8975 hours for this IMA Change Request and SATE impacts of 375 to 475 hours.

At the March Systems CMP Meeting, CMP participants will be given the opportunity to comment on this Change Request and provide additional clarifications. Any clarifications and/or modifications identified at that time will be incorporated into Qwest’s further evaluation of this Change Request.

This Change Request is eligible for the IMA 14.0 Prioritization.

Sincerely, Qwest

Information Current as of 1/11/2021