Archived System CR SCR022112-1IG Detail |
Title: Implementation of CABS BOS Version 52 for bill and CSR data output | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR022112-1IG |
Completed 12/12/2012 |
- | 11/ | Billing - CABS BOS |
Originator: Larson, Jami |
Originator Company Name: CenturyLink |
Owner: Larson, Jami |
Director: |
CR PM: Lorence, Susan |
Description Of Change |
Implementation of CABS BOS Version 52 (V52) for Bill and CSR data with IABS release 48.0 (11/17/12). In addition to the changes for V52, we are incorporating the changes that were made with CABS BOS Version 51.1(V51.1). That release cared for changes (i.e., data elements, records, phrase codes) necessary in order for companies to comply with FCC Order 11-161 for VoIP traffic The CABS BOS Differences List for V52 will be posted to the Wholesale website 6/1/12. It will contain the detail, item by item, for the changes being made with V52 and V51.1.
|
Status History |
Date | Action | Description |
2/21/2012 | CR Acknowledged | CR Acknowledged |
2/21/2012 | CR Submitted | CR Submitted |
3/21/2012 | Status Changed | Status changed to Presented |
3/21/2012 | Discussed at Monthly CMP Meeting | Discussed at the March Systems CMP Meeting - See Attachment D in the Distribution Package |
4/13/2012 | Status Changed | Status changed to Development |
6/1/2012 | Communicator Issued | See notice number SYST.CBOS.06.01.12.F.10201.CABS_BOS_Version_52 |
6/29/2012 | Communicator Issued | See notice number SYST.CBOS.06.29.12.F.10259.CABS_BOS_Version_52 |
11/14/2012 | Discussed at Monthly CMP Meeting | Discussed at November System CMP Meeting – See Attachment K in the Distribution package. |
11/17/2012 | Status Changed | Status changed to CLEC Test |
12/12/2012 | Status Changed | Status changed to Completed. |
12/12/2012 | Discussed at Monthly CMP Meeting | Discussed at the December Systems CMP Meeting - See Attachment G in the Distribution Package. |
Project Meetings |
12/12/12 System Monthly Meeting Mark Coyne – CenturyLink said the effective date was 11/17/2012. The CR is in CLEC Test and we would like to move it to Completed status. There were no objections. 11/14/12 System Monthly Meeting Mark Coyne – CenturyLink said there was one on the list, SCR022112-1IG that has an effective date of 11/17/12 and that it would be revisited in the December meeting. 3/21/12 System Monthly Meeting Jami Larson – CenturyLink stated that Implementation of CABS BOS Version 52 for Bill and CSR data with IABS is scheduled for November 17, 2012. The differences list will be updated and posted to the Web site by June 1, 2012. In addition, CenturyLink will be incorporating the changes that were made with CABS BOS Version 51.1.
|