Archived System CR SCR021902-13 Detail |
Title: SATE Add EEL/UNE Combination | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR021902-13 |
Completed 11/21/2002 |
400 - 700 | 20/11 | EEL, UNE |
Originator: Green, Wendy |
Originator Company Name: Qwest Corporation |
Owner: Green, Wendy |
Director: |
CR PM: Esquibel-Reed, Peggy |
Description Of Change |
The Change Requests seeks to have SATE support EEL/UNE Combination and all its activities. Scenarios for EEL/UNE Combination should be added to the EDI SATE Data Document. For 2001, production volume for product was in the range of 100-1000. 2 CLECs are currently implementing this product in EDI.
EXPECTED DELIVARABLE: The ability to test EEL/UNE with SATE
|
Status History |
Date | Action | Description |
2/19/2002 | CR Submitted | |
2/19/2002 | CR Acknowledged | |
2/20/2002 | Clarification Meeting Held | |
2/25/2002 | Additional Information | SATE Ranking will be in the March 2002 CMP Meeting. |
2/25/2002 | Status Changed | SCR021902-13 status updated to 'Presented' after discussion at March Systems CMP Meeting |
2/27/2002 | Record Update | Revised CR received from Qwest. |
3/12/2002 | LOE Issued | LOE is Large (400 - 700) |
3/21/2002 | Discussed at Monthly CMP Meeting | SCR021902-13 discussed March Systems CMP Monthly meeting; please see Systems CMP Distribution Package March CMP - Attachment C |
4/1/2002 | Release Ranking | Ranking for SATE following the March 2002 Systems CMP Meeting. SCR021902-13 ranked number 05 |
6/7/2002 | Status Changed | SCR021902-13 status updated to 'Packaged' for SATE release associated with IMA 11.0 based upon outcome of Packaging Selection vote |
8/5/2002 | Status Changed | Status changed from 'Packaged' to 'Development', targeted implementation date is 10/19/02 |
8/22/2002 | Discussed at Monthly CMP Meeting | SCR021902-13 discussed at August Systems CMP Monthly meeting; please see Systems CMP Distribution Package August CMP -- Attachment R |
10/17/2002 | Discussed at Monthly CMP Meeting | SCR021902-13 discussed at October Systems CMP Monthly meeting; please see Systems CMP Distribution Package October CMP -- Attachment L |
10/29/2002 | Status Changed | Status changed to CLEC Test due to October 19th deployment. |
11/21/2002 | Discussed at Monthly CMP Meeting | SCR021902-13 discussed at November Systems CMP Monthly meeting; please see Systems CMP Distribution Package November CMP -- Attachment G |
Project Meetings |
November 21 Systems CMP Meeting Discussion: Wendy Green-Qwest stated that the CR could be closed. August Systems CMP Meeting Discussion: Attachment R = Change Requests Committed for IMA Release 11.0 Connie Winston/Qwest - we have one small issue requiring the Sup 2 (SCR013002-8 Flowthrough on Sup 2 Category Due Date) to be a spillover for 11.1. She explained why this will be a spillover into the point release. She noted that resale and UNE sup 2 due date change orders will flow through. The unbundled loop will drop out to the Center and will be updated by the Center until 11.1. Donna Osborne-Miller/AT&T - that’s line item #4 in the Attachment? Connie Winston/Qwest - yes. Michael Buck/Qwest - stated that the NOTE at the bottom of the page needs to be changed from 'In Definition' to 'Packaged'. Liz Balvin/WorldCom - asked how the 11.0 PO2 CR is different than the one in 12.0. Connie Winston/Qwest - they are just different edits. The edits are noted on each of the 2 CRs. Liz Balvin/WorldCom - with 12.0, would you say that any of the hours devoted to this would lower the 8,000 hours? Are you looking at that when you do the design? Connie Winston/Qwest - we always look at that, but the edits are different so I could expect a reduction in the LOEs. As we get further in design, we do update the LOE. Attachment R = Change Requests Committed for SATE Release 11.0 Connie Winston/Qwest - SATE has the same spillover candidate for 11.1, SCR013002-8 Sup 2. Michael Buck/Qwest - noted that items 3, 5, and 7 are SATE specific candidates. The others are IMA with SATE impacts. Wendy Green/Qwest - noted that the SATE side has a shorter list because of the GUI only impacting CRs going into IMA having no impact to SATE. Michael Buck/Qwest - any other questions in the room or on the bridge? None.
|
CenturyLink Response |
March 12, 2002: Level of Effort is 400-700 hours.
|
Information Current as of 1/11/2021