Archived System CR SCR021208-01IG Detail |
Title: Implementation of CAB BOS Version 48 for bill and Customer Service Record (CSR) data | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR021208-01IG |
Completed 11/19/2008 |
- | 11/ |
Originator: Larson, Jami |
Originator Company Name: Qwest Corporation |
Owner: Larson, Jami |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
Qwest will implement the record changes for bill and CSR data as specified in the CABS BOS Summary Version 48 document produced by Telcordia. Item by item detail will be available to customers via the Differences List for V48 which will be available on the Wholesale website http://www.qwest.com/wholesale/systems/billsystem.html 6/1/08.
Expected Deliverables/Proposed Implementation Date 10/18/2008
|
Status History |
Date | Action | Description |
2/12/2008 | CR Submitted | CR Submitted |
2/14/2008 | CR Acknowledged | CR Acknowledged |
2/20/2008 | Discussed at Monthly CMP Meeting | Discussed at the February CMP Meeting - See Attachment D in the Distribution Package |
2/20/2008 | Status Changed | Status changed to Presented |
3/20/2008 | Status Changed | Status changed to Development |
3/20/2008 | Discussed at Monthly CMP Meeting | Discussed at the March Systems CMP Meeting - See Attachment C in the Distribution Package |
5/30/2008 | Communicator Issued | SYST.05.30.08.F.05393.IABS_Oct_Rel_Drft_BOS_V48 |
6/27/2008 | Communicator Issued | SYST.06.27.08.F.05442.FNL_Rel_Notice_BOS_V48 |
10/15/2008 | Discussed at Monthly CMP Meeting | Discussed at the October CMP Meeting - See Attachment K in the Distribution Package |
10/18/2008 | Status Changed | Status changed to CLEC Test |
11/19/2008 | Discussed at Monthly CMP Meeting | Discussed at the November Systems CMP Meeting - See Attachment G in the Distribution Package |
11/19/2008 | Status Changed | Status changed to Completed |
Project Meetings |
11/19/08 Systems CMP Meeting Mark Coyne – Qwest said this CR deployed on October 18th and will be closed. 10/15/08 Systems CMP Meeting Mark Coyne – Qwest said this CR will deploy on October 18th. March 19, 2008 Systems CMP Meeting Mark Coyne-Qwest stated that this CR was presented last month as a walk on by Jami Larson (Qwest). He said that the targeted implementation date is 10/18/08 and will move to Development. February 20, 2008 Systems CMP Meeting Jami Larson-Qwest stated that Qwest will implement, in the 4th quarter, the record changes for bill and CSR data as specified in the CABS BOS Summary Version 48 document produced by Telcordia. She said that item by item detail will be available to customers via the Differences List for V48 which will be available on the Wholesale website at: http://www.qwest.com/wholesale/systems/billsystem.html 6/1/08. Bonnie Johnson-Eschelon asked if the documentation will include the changes that Qwest is making. Jami Larson-Qwest said yes. Bonnie Johnson-Eschelon asked if (Comment From Eschelon 2/27/08) in this change Qwest was going to include all circuit ids in the OC&C. Jami Larson-Qwest said that change is not part of CAB BOS Version 48.
|
CenturyLink Response |
|