Description Of Change |
Update IABS to provide CABS BOS BDT (Bill Data Tape) records in Version 51 for bill/CSR data
Expected Proposed Implementation Date: Provide Bill/CSR BDT records standard with CABS BOS Version 51 (exceptions noted in Differences List)/ 9/17/11
|
Status History |
Date | Action | Description |
2/11/2011 | CR Submitted | CR Submitted |
2/15/2011 | CR Acknowledged | CR Acknowledged |
3/16/2011 | Status Changed | Status changed to Presented |
3/16/2011 | Action Item Created | Discussed at the March Prod/Proc CMP Meeting - See Attachment D in the Distribution Package |
5/1/2011 | Status Changed | Status changed to Development |
6/1/2011 | Communicator Issued | See notice number SYST.CBOS.06.01.11.F.09173.CABS_BOS_Version_51 |
6/29/2011 | Communicator Issued | See notice number SYST.CBOS.06.29.11.F.09260.CABS_BOS_Version_51 |
8/17/2011 | Discussed at Monthly CMP Meeting | Discussed at the August System CMP Meeting - See Attachment K in the Distribution Package |
9/17/2011 | Status Changed | Status changed to CLEC Test |
10/19/2011 | Status Changed | Status changed to Completed |
10/19/2011 | Discussed at Monthly CMP Meeting | Discussed at the October System CMP Meeting - See Attachment G in the Distribution Package |
Project Meetings |
10/19/11 Product Process CMP Meeting SCR021111-1IG Implementation of CABS BOS Version 51 for Bill/CSR data output. Mark asked if it was OK to close. There were no objections. 8/17/11 Product Process CMP Meeting Mark Coyne – CenturyLink said that the final release notice was sent on 6/29. Testing is available on 8/18 with a release date of 9/17. Although the package displayed a date of 9/7, he felt the date was 9/17. Susan Lorence – CenturyLink confirmed that it was a typo and the correct date was 9/17. 3/16/11 Product Process CMP Meeting Jami Larson – Qwest presented the new Industry Guideline CR associated with CABS BOS Version 51 which will be implemented with the Release 44 which is scheduled for September 17, 2011. Jami said the Differences List will be posted June 1, 2011 and test tapes will be available on August 17, 2011. Jami asked if there were any questions and there were none.
|