Archived System CR SCR020207-01IG Detail |
Title: CABS BOS Version 47 | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR020207-01IG |
Completed 12/12/2007 |
750 - 1500 | 11/ | Billing | NA |
Originator: Larson, Jami |
Originator Company Name: Qwest Corporation |
Owner: Larson, Jami |
Director: |
CR PM: Esquibel-Reed, Peggy |
Description Of Change |
Implementation of CABS BOS Version 47 for bill and CSR output for IABS system.
Expected Deliverable: November 10, 2007
|
Status History |
Date | Action | Description |
2/2/2007 | CR Submitted | |
2/2/2007 | CR Acknowledged | |
2/21/2007 | Discussed at Monthly CMP Meeting | Discussed at the February Systems CMP Monthly Meeting; please see the February Systems CMP Distribution Package, Attachment D |
3/21/2007 | Discussed at Monthly CMP Meeting | Discussed at the March Systems CMP Monthly Meeting; please see the March Systems CMP Distribution Package, Attachment I |
6/1/2007 | Communicator Issued | SYST.06.01.07.F.04725.IABS_Nov_Rel_Dft_BOS_v47 |
6/20/2007 | Discussed at Monthly CMP Meeting | Discussed at the June Systems CMP Monthly Meeting; please see the June Systems CMP Distribution Package, Attachment I |
6/29/2007 | Communicator Issued | SYST.06.29.07.F.004776.FNL_Rel_Notice_BOS_V47 |
10/17/2007 | Discussed at Monthly CMP Meeting | Discussed at the October Systems CMP Meeting - See Attachment K in the Distribution Package |
11/14/2007 | Status Changed | Status changed to CLEC Test |
11/14/2007 | Discussed at Monthly CMP Meeting | Discussed at the November Systems CMP Meeting - See Attachment K in the Distribution Package |
12/12/2007 | Discussed at Monthly CMP Meeting | Discussed at the December CMP Monthly Meeting - See Attachment G in the Distribution Package |
12/12/2007 | Status Changed | Status changed to Completed |
Project Meetings |
November 14, 2007 Systems CMP Meeting Discussion: Susan Lorence-Qwest stated that the implementation date for this CR is 11/10/07
-- October 17. 2007 Systems CMP Meeting Discussion: Mark Coyne-Qwest reviewed the following change requests and associated implementation dates. SCR020207-01IG CABS BOS Version 47 - Implementation Date - 11/10/07 -- June 20, 2007 Systems CMP Meeting Discussion: Mark Coyne-Qwest stated that the targeted implementation date for this CR is November 10, 2007.
- March 21, 2007 Systems CMP Meeting Discussion: Mark Coyne-Qwest stated that the LOE for this CR is 750 to 1500 hours.
- February 21, 2007 Systems CMP Meeting Discussion: Peggy Esquibel Reed-Qwest stated that this CR is for the standard upgrade for bill and CSR output in IABS and noted that it is targeted for the November timeframe. There were no questions or comments. This CR moves to Presented Status. February 13, 2007 Clarification There is no additional information for this CR.
|
CenturyLink Response |
DRAFT RESPONSE March 5, 2007 RE: SCR020207-01IG (CABS BOS Version 47) Qwest has reviewed the information submitted as part of Change Request SCR020207-01IG. Based upon the scope of this CR, Qwest is able to provide an estimated Level of Effort (LOE) of 750 to 1500 hours for this Wholesale Billing Interface Change Request. Qwest will review release schedules and development timetables for the scheduliong of this Change Request. Sincerely, Qwest Corporation
|
Information Current as of 1/11/2021