Archived System CR SCR013102-06 Detail |
Title: LSOG 6 Issue 2010: Add new Construction Field to LSR | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR013102-06 |
Completed 4/17/2003 |
1550 - 2325 | 3/12 | Funtional Impact not product impact |
Originator: Zimmerman, Carol |
Originator Company Name: Qwest Corporation |
Owner: Winston, Connie |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
OBF issue 2010 will allow the CLEC to designate that the service address is 'new construction. Idenfitication of 'new construction' addresses may assist the Qwest Wholesale Service Centers in more efficiently processing LSR's in cases where a specific service address is designated as 'new construction'.
|
Status History |
Date | Action | Description |
1/31/2002 | CR Submitted | |
1/31/2002 | CR Acknowledged | |
2/7/2002 | Status Changed | Status changed to clarification. |
2/7/2002 | LOE Issued | The LOE is Medium. |
2/21/2002 | Discussed at Monthly CMP Meeting | SCR013102-06 discussed during 'New Qwest CR' portion of February Systems CMP Monthly meeting; Attachment C for February Distribution Package |
2/21/2002 | Discussed at Monthly CMP Meeting | SCR013102-06 discussed during 'Review of 11.0 Prioritization Eligible CRs' portion of February Systems CMP Monthly meeting; please see Attachment I of February Systems CMP Distribution Package |
2/22/2002 | Status Changed | Status changed to presented |
2/22/2002 | Status Changed | Status changed to presented |
3/1/2002 | Release Ranking | Ranking for Release 11.0 following the February 2002 Systems CMP Meeting. SCR013102-06 ranked number 11 |
3/1/2002 | Status Changed | Status updated to 'Prioritized' from 'Presented' |
4/1/2002 | Release Ranking | Ranking for SATE following the March 2002 Systems CMP Meeting. SCR013102-06 ranked number 10 |
6/7/2002 | Status Changed | SCR013102-06 status updated to 'Pending Prioritization' based upon outcome of IMA 11.0 Packaging Selection vote |
7/18/2002 | Discussed at Monthly CMP Meeting | SCR013102-06 discussed at July Systems CMP Monthly meeting; please see Systems CMP Distribution Package July CMP -- Attachment P |
7/26/2002 | Release Ranking | Ranking for Release 12.0 following the July 2002 Systems CMP Meeting. SCR013102-06 ranked number 09 |
10/30/2002 | Status Changed | SCR013102-06 status updated to 'Packaged' based upon outcome of release 12.0 packaging effort |
12/19/2002 | Discussed at Monthly CMP Meeting | SCR013102-06 discussed at December Systems CMP Monthly meeting; please see Systems CMP Distribution Package December CMP -- Attachments N and Q |
4/7/2003 | Status Changed | Status changed to CLEC Test due to IMA 12.0 deployment |
4/17/2003 | Discussed at Monthly CMP Meeting | SCR013102-06 discussed at April Systems CMP Monthly meeting; please see Systems CMP April Distribution Package CMP |
4/30/2003 | Status Changed | Status changed to completed |
Project Meetings |
4/17/03 CMP Systems Meeting No Comments. CR changed to Completed Status 2/21/02 CMP Systems Meeting Carol Zimmerman/Qwest presented this CR. OBF issue 2010 will allow the CLEC to designate that the service address is ‘new construction’. Identification of ‘new construction’ addresses may assist the Qwest Wholesale Service Centers in more efficiently processing LSRs in cases where a specific service address is designated as ‘new construction’. The level of effort is medium. The status will be changed to presented.
|
CenturyLink Response |
2/21/02 CMP Systems Meeting Carol Zimmerman/Qwest presented this CR. OBF issue 2010 will allow the CLEC to designate that the service address is ‘new construction’. Identification of ‘new construction’ addresses may assist the Qwest Wholesale Service Centers in more efficiently processing LSRs in cases where a specific service address is designated as ‘new construction’. The status will be changed to presented. 2/7/02 - The LOE is 1925 to 3225 hours.
|
Information Current as of 1/11/2021