Archived System CR SCR013002-3 Detail |
Title: IMA Pre Order Use CCNA to retrieve a Design Layout Report (DLR) | |||||
CR Number |
Current Status Date |
Level of Effort |
Interface/ Release No. |
Area Impacted |
Products Impacted |
|
|||||
SCR013002-3 |
Completed 12/19/2002 |
750 - 3000 | 3/11 |
Originator: Ecklund, Jon |
Originator Company Name: Qwest Corporation |
Owner: Winston, Connie |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
This change request seeks to allow IMA to retrieve a DLR for all Circuit ID Format Types using a different field to identify ownership.
Today, the DLR retrieval uses ACNA. This doesn't always work because the internal records use several different ownership codes. The proposed change is to establish a method that will retrieve the DLR using the inputted ownership via IMA and other ownerships that will provide the best opportunity to receive back the DLR. This change would require the CCNA to be used rather than the ACNA. The change would better utilize several of the owner identifiers, rather than just the single owership identifier on the request.
|
Status History |
Date | Action | Description |
1/30/2002 | CR Submitted | CR submitted |
1/30/2002 | Clarification Meeting Held | Clarified this CR with Jon Ecklund. |
1/31/2002 | CR Acknowledged | CR Acknowledged |
2/11/2002 | LOE Issued | LOE assigned is medium |
2/14/2002 | Draft Response Issued | Initial response was issued to the originator. |
2/21/2002 | Discussed at Monthly CMP Meeting | This CR was presented and discussed at the Feb CMP meeting.CR is eligible for IMA 11.0 prioritization. |
2/21/2002 | Additional Information | As a result of the discussion at the Feb CMP meeting, this request has been updated to show the FAXed report as optional. |
2/21/2002 | Discussed at Monthly CMP Meeting | SCR013002-3 discussed during 'New Qwest CR' portion of February Systems CMP Monthly meeting; Attachment C for February Distribution Package |
2/21/2002 | Discussed at Monthly CMP Meeting | SCR013002-3 discussed during 'Review of 11.0 Prioritization Eligible CRs' portion of February Systems CMP Monthly meeting; please see Attachment I of February Systems CMP Distribution Package |
3/1/2002 | Release Ranking | Ranking for Release 11.0 following the February 2002 Systems CMP Meeting. SCR013002-3 ranked number 5 |
3/1/2002 | Status Changed | Status updated to 'Prioritized' from 'Presented' |
6/7/2002 | Status Changed | SCR013002-3 status updated to 'Packaged' for IMA 11.0 based upon outcome of Packaging Selection vote |
8/5/2002 | Status Changed | Status updated to Development |
8/22/2002 | Discussed at Monthly CMP Meeting | SCR013002-3 discussed at August Systems CMP Monthly meeting; please see Systems CMP Distribution Package August CMP -- Attachment R |
9/19/2002 | Discussed at Monthly CMP Meeting | SCR013002-3 discussed at September Systems CMP Monthly meeting; please see Systems CMP Distribution Package November CMP -- Attachment L |
9/19/2002 | Discussed at Monthly CMP Meeting | SCR013002-3 discussed at September Systems CMP Monthly meeting; please see Systems CMP Distribution Package November CMP -- Attachment L |
11/27/2002 | Status Changed | Status changed to CLEC test |
12/19/2002 | Discussed at Monthly CMP Meeting | SCR013002-3 discussed at December Systems CMP Monthly meeting; please see Systems CMP Distribution Package December CMP -- Attachment G |
Project Meetings |
12/19/02 December Systems CMP Meeting This CR was completed with 11.0 and is ok to close.
|
CenturyLink Response |
UR 2989 has been opened for this work. The Level of Effort on this is Medium. It is elligable for the IMA 11.0 prioritization.
|