PC120303-3 Completed
4/21/2004
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Harlan, Cindy

Description Of Change

Excel spreadsheet of 1302 Interstate and SHNS USOCs being grandparented on 3/1/04. There are three types of elements being grandparented; ports, shelves and port to port connecting agreements.

-Ports with month to month rates are not being affected. We are grandparenting 1,2,3 and 5 year rated ports.

-Shelves are being replaced by a fully loaded node. The currently tariffed nodes will become these fully loaded nodes once shelves are grandfathered.

-If a customer would have ordered a port to port connecting agreement, once that is grandparented, they will be able to order the currently tariffed COCC (central office connecting channel).

Expected Deliverable: 03/01/2004


Date Action Description
12/3/2003 CR Submitted 
12/5/2003 CR Acknowledged 
12/8/2003 Contacted Janean VanDusen 
12/10/2003 Clarified CR 
12/17/2003 Dec CMP meeting notes will be posted to the database 
1/21/2003 Jan CMP meeting minutes will be posted to the database 
1/16/2004 PROD.01.16.04.F.01240.ResaleSST_SHNS level 4 implementation date March 1, 2004 
2/13/2004 PROD.02.12.04.F.01354.FNL_ResaleSST_SHNS 
2/18/2004 Feb CMP Meeting notes will be posted to the project meeting section 
3/5/2004 PROD.03.05.04.F.01451.Rev.FNL_Resale SST_SHNS 
3/17/2004 March CMP meeting notes will be posted to the project meeting section 
3/12/2004 PROD.03.12.04.F.01478.RevisedFNL_ResaleSST_SHNS Revised final notice 
3/24/2004 Revised final notice changing dates to April 8, 2004. PROD.03.25.04.F.01515.RevFNL_ResaleSST_SHNS 
4/21/2004 April CMP meeting notes will be posted to the project meeting section 

Project Meetings

April 21, 2004 CMP Meeting notes: Janean VanDusen – Qwest advised this CR was effective April 8. This CR will move to Completed Status.

March 17, 2004 CMP Meeting notes: Janean Van Dusen – Qwest advised that this CR will be implemented April 6. There were delays in the tariff filing. This CR will remain in CLEC Test Status.

February 18, 2004 CMP Meeting notes: Janean Van Dusen – Qwest provided status. The final notification went out February 13. There are two effective dates with this CR. One is March 12 and the other is March 24. This CR will move to CLEC Test Status.

January 21, 2004 CMP Meeting notes: Janean Van Dusen – Qwest advised this CR is effective March 1, 2004. The USOC list is on the customer notification web site. It was noticed on January 16, 2004. This CR will move to Development Status.

December 17, 2003 CMP Meeting notes: Janean Van Dusen – Qwest reported that this is a new CR that is grandfathering USOCs related to these services. The intent is to streamline the number of USOCs associated to this product. There is a spreadsheet with 1302 USOCs on it. This spreadsheet is too large to include as part of the CR but it will be sent out with the Notification. This CR will move to Presented status.