Title: Grandfathering and eliminating certain USOCs in Norhtern & Southern Idaho and Iowa
CR Number Current Status
Date
Area Impacted Products Impacted

PC103108-01 Completed
2/18/2009
Resale
Originator: Schwartze, Cindy
Originator Company Name: Qwest Corporation
Owner: Schwartze, Cindy
Director:
CR PM: Stecklein, Lynn

Description Of Change

Qwest will be grandfathering JUF (Joint User Service) in Northern & Southern Idaho, JUP (Joint User Listing) in Southern Idaho and 7FB (Business Incoming Only Line) in Iowa.

Qwest will be eliminating FNH (Foreign Exchange Line) in Northern Idaho, JND (Joint User Listing) and S3L (Secretarial System) in Southern Idaho. There are no Wholesale Customers with these services.

Expected Deliverables/Proposed Implementation Date (if applicable):

The proposed implementation date is 2/9/09.


Date Action Description
10/31/2008 CR Submitted CR Submitted 
11/3/2008 CR Acknowledged CR Acknowledged 
11/19/2008 Status Changed Status changed to Presented 
11/19/2008 Discussed at Monthly CMP Meeting Discussed in the November Prod/Proc CMP Meeting - See Attachment D in the Distribution Package 
12/3/2008 Status Changed Status changed to Development 
12/17/2008 Discussed at Monthly CMP Meeting Discussed at the ProdProc CMP Meeting - See Attachment D in the Distribution Package 
1/19/2009 Communicator Issued PROD.01.19.09.F.05931.Grndfhr_Eliminat_ID_IA_USOCs 
1/21/2009 Discussed at Monthly CMP Meeting Discussed at the January Prod/Proc CMP Meeting - See Attachment D in the Distribution Package 
2/9/2009 Status Changed Status changed to CLEC Test 
2/18/2009 Discussed at Monthly CMP Meeting Discussed at the February Monthly CMP Meeting - See Attachment D in the Distribution Package 
2/18/2009 Status Changed Status changed to Completed 

Project Meetings

2/18/09 Product/Process CMP Meeting

Mark Coyne-Qwest said that the Level 2 notice was sent on 1/29/09, became effective on 2/9/09 and Qwest would like to close. There was no objection to closure.

1/21/09 Product/Process CMP Meeting

Mark Coyne-Qwest said that the Level 2 notice was sent on 1/29/09 to become effective on 2/9/09.

12/17/08 Product/Process CMP Meeting

Mark Coyne-Qwest said that we are working on preparing the notice and the effective date is pending.

11/19/08 Product/Process CMP Meeting

Cindy Schwartze-Qwest said that Qwest will be grandfathering JUF (Joint User Service) in Northern & Southern Idaho, JUP (Joint User Listing) in Southern Idaho and 7FB (Business Incoming Only Line) in Iowa. Qwest will be eliminating FNH (Foreign Exchange Line) in Northern Idaho, JND (Joint User Listing) and S3L (Secretarial System) in Southern Idaho. There are no Wholesale Customers with these services and that we are looking at a 2/9/09 implementation date. Cindy asked if there was any objection in reducing the notification to a Level 2. Bonnie Johnson-Integra said that (11/26/08 Comments to minutes received from Integra) if no CLECs have this service that they have no objection to the Level 2 notification. Julia Redman-Carter-McLeodUSA said that they have no objection as long as there are no Wholesale Customers.