Wholesale: Products & Services

Open Product/Process CR PC102704-2 Detail

 
Title: Eliminate DS1 Radio
CR Number Current Status
Date
Area Impacted Products Impacted

PC102704-2 Completed
8/17/2005
Resale
Originator: Van Dusen, Janean
Originator Company Name: Qwest Corporation
Owner: Van Dusen, Janean
Director:
CR PM: Stecklein, Lynn

Description Of Change

DS1 Radio equipment is obsolete and no longer available. DS1 Radio service offering will be removed from the tariff – FCC 1 Section 7.11.1.A

Expected Deliverable: 1/15/05

1/13/05 Expected Deliverable changed to 7/16/05


Date Action Description
10/27/2004 CR Submitted 
10/27/2004 Acknowledgement sent 
10/27/2004 Spoke with originator and clarified CR 
11/5/2004 changed CR # to reflect PC102704-2 
11/17/2004 November CMP Meeting minutes will be posted to the database 
12/15/2004 December meeting minutes will be posted to the database 
1/13/2005 PROD.01.13.05.F02469.REV_FNL_Elmnat_DS-1_Radio Product Notification 
1/19/2005 Discussed in the January Product/Process Meeting - See Attachment E in the Distribution Package 
2/16/2005 Discussed in the February Product/Process Meeting - See Attachment E in the Distribution Package 
3/16/2005 Discussed in the March Product/Process Meeting - See Attachment E in the Distribution Package 
3/31/2005 PROD.03.31.05.F.02764.REV_FNL_Elmnat_DS-1_Radio 
4/20/2005 Discussed in the April Product/Process Meeting - See Attachment E in the Distribution Package 
5/18/2005 Discussed in the MayProduct/Process Meeting - See Attachment E in the Distribution Package 
5/27/2005 PROD.05.26.05.F.02941.REV_FNL_Elmnat_DS-1_Radio 
6/15/2005 Discussed in the June Product/Process Meeting - See Attachment E in the Distribution Package 
7/20/2005 Discussed in the July Product/Process CMP Meeting - See attachment E in the Distribution Package 
7/20/2005 Status changed to CLEC Test 
8/17/2005 Discussed in the August Product/process CMP Meeting - See Attachment in the Distribution Package 
8/17/2005 Status changed to Completed 

Project Meetings

7/20/05 Product/Process CMP Meeting Lynn Stecklein - Qwest said that this request deployed on July 16th and will move to CLEC Test.

6/15/05 Product/Process CMP Meeting

Jill Martain - Qwest stated that this CR is still on target for 7/16/05 and will remain in Development.

5/18/05 Product/Process CMP Meeting

Jill Martain - Qwest stated that the tariff effective date was moved from 8/1/05 to 7/16/05 and will remain in Development.

4/20/05/ Product/Process CMP Meeting

Jan VanDusen - Qwest stated that the tariff effective date is 8/1/05 and that this CR will remain in Development.

3/16/05 Product/Process CMP Meeting

Janean Van Dusen - Qwest stated that there was a delay in the February 14th filing and will now be effective on May 1st. She also said that the tariff notification is not out yet for review.

2/16/05 Product/Process CMP Meeting

Janean Van Dusen - Qwest stated that this CR is still on target for April 1, 2005.

Jill Martain - Qwest stated that this CR will remain in Development Status.

1/19/05 Product/Process Meeting

Janean Van Dusen/Qwest stated that a notification was sent on January 13, 2005 advising that the effective date was changed to April 1, 2005. Jill Martain/Qwest stated that this CR will remain in Development.

1/13/05

PROD.01.13.05.F.02469.REVFNLElmnatDS-1Radio Product Notification

Notification sent to change effective date from January 15th to April 1, 2005.

December CMP Meeting Minutes Janean Van Dusen – Qwest advised this CR is effective January 15. There are not any customers using this service. The alternate service is to provide DS1 over copper or fiber facilities. This CR will move to Development Status.

11/17/04 November meeting minutes Cindy Macy – Qwest presented this CR for Janean VanDusen. This CR is effective January 15, 2005. We currently do not have any customers. Sharon Van Meter – ATT asked if there is a similar product offering that is available. Cindy advised she would check on this and provide information back in the meeting notes. This CR will move to Presented Status. Janean VanDusen – Qwest provided additional information after the meeting that she is verifying the customer impact as there may be a limited number of existing customers. Additional information will be provided at the December CMP meeting.


Information Current as of 1/11/2021