Open Product/Process CR PC100101-5ES Detail

 
Title: Clarification of Additional Testing Process
CR Number Current Status
Date
Area Impacted Products Impacted

PC100101-5ES Completed
7/12/2002
Repair EEL, UDIT, Unbundled Loop
Originator: Smith, Debra
Originator Company Name: Qwest Corporation
Owner: Augustson, Cathy
Director:
CR PM:

Description Of Change

Currently, CLECs’ are responsible for testing UNE’s prior to submitting a trouble report to Qwest. CLECs’ are to provide test diagnostics including specific evidence that the trouble is in the Qwest Network along with the associated Qwest circuit identification number. If the CLEC elects not to perform the necessary UNE testing, Qwest will offer to do such testing on CLECs’ behalf. If such testing is requested by the CLEC, Qwest will perform the additional testing and bill the CLEC the appropriate charges that are in their Interconnection agreement.

If the CLEC does not provide test diagnostics and elects not to have Qwest perform additional testing on their behalf, Qwest will not accept a trouble report. Additional Charges may apply when the testing determines the trouble is beyond the Loop Demarcation Point

This additional testing option is available on the Unbundled Loop Product Suite, Unbundled Dedicated Transport (UDIT), Enhanced Extended Loop (EEL) and Loop Mux.


Date Action Description
10/1/2001 CMP receives CR from Deb Smith, Qwest (Subject Matter Expert (SME)) 
10/1/2001 CMP CR status changed to 'Submitted.' 
10/1/2001 CMP forwards updated CR to Deb Smith, Qwest. 
10/17/2001 CMP Meeting: Qwest introduced "Description of Change" and agreed to provide detailed package for CLEC review. Walk through meeting to be scheduled by Qwest in the late October/early November 2001 time frame. 
10/26/2001 Notification forwarded to the CLEC community regarding presentation of CR in the 10/31/01 CMP Re-Design Meeting. 
10/31/2001 CR presented to the participating CLECs at the CMP Re-Design Meeting. CLECs were requested to provide comments. 
11/8/2001 Qwest Notification (Document No. PROD.11.08.R.00197.Mtce&Repair Language; Subject: Update to Product Information on Maintenance and Repair Language within EEL, UDIT, LMC and Unbundled Loop General) transmitted to CLEC community. 
11/8/2001 PCAT Documents posted to the Qwest Wholesale CMP Document Review WEB page [http://www.qwest.com/wholesale/cmp/review.html]. Comments from CLEC community due in 15 calendar days (11/23/01), as stated in 'Interim External Change Management Process for Qwest Initiated Product/Process Changes, Version 6, 11/26/01." 
11/12/2001 Qwest and Eschelon personnel met to review the information shared in the 10/31/01 CMP Re-Design meeting and to answer additional questions. 
11/13/2001 Notification prepared for transmittal to CLEC community regarding follow-up meeting scheduled for 11/26/01. 
11/14/2001 CMP Meeting - Qwest advised CLEC community that PCAT documents currently are available for comment. 
11/24/2001 No comments were received from the CLEC community regarding PCAT documents posted to the Qwest Wholesale CMP Document Review WEB page. 
11/26/2001 Qwest conducted a follow-up meeting with the CLEC community to discuss any technical issues with the CR (primarily operational and testing issues). Responses to questions were prepared for posting on the Qwest Wholesale WEB page. 
11/28/2001 Questions & Answers for Additional Testing 11/26/01 document posted to Qwest Wholesale WEB page [http://www.qwest.com/wholesale/cmp/changerequest.html]. 
11/28/2001 "Additional Testing Process Document - 11/09/01" and "Additional Testing Process Presentation - 11/09/01" posted to Qwest Wholesale WEB page [http://www.qwest.com/wholesale/cmp/changerequest.html]. These documents were previously posted in the Qwest Wholesale CMP Re-Design WEB page [http://www.qwest.com/wholesale/cmp/redesign.html]. 
11/30/2001 Qwest IT Wholesale Communicator, November 30, 2001, Document No. SYST.11.30.01.F.02444_CEMR_UG_Update, CEMR User’s Guide Update prepared for transmittal to Qwest Wholesale Customers 
12/5/2001 Formal Escalation received from Eschelon regarding implementation of CR. 
12/6/2001 Qwest response sent acknowledging receipt of Formal Escalation from Eschelon (PC100101-5-E01). 
12/7/2001 KMC Telecom notified Qwest to participate in the formal escalation initiated by Eschelon. 
12/7/2001 Qwest publishes "QWEST - INTERNAL NOTIFICATION; Announcement Date: December 7, 2001; Effective Date: December 21, 2001; Document Number: I.PROD.12.07.01.F.00603.Pending-_ULL_EEL_LMC_UDIT; Notification Category: Product Notification; Target Audience: CLECs, Resellers; Subject: Pending Updates to Unbundled Local Loop General, EEL, LMC and UDIT Product Catalogs; Change Request Number: CR PC100101-5" for distribution to CLEC community. Notice indicates an effective date of subject updates as December 21, 2001. A fifteen-(15) day notice is provided to the CLEC community. 
12/12/2001 CMP Meeting - Qwest advises CLEC community that a formal escalation has been received & that a formal escalation response is forthcoming. 
12/13/2001 Qwest transmitted formal escalation response (via e-mail) to the originating CLECs (i.e., Eschelon Telcom, Inc., Covad Communications, and Allegiance Telecom Inc.) [response posted in Qwest Wholesale CMP WEB page; http://qwest.com/wholesale/cmp/escalations.html ]. 
12/21/2001 Eschelon reply received responding to the Qwest formal escalation response (dated 12/13/01) [reply posted in Qwest Wholesale CMP WEB page; http://qwest.com/wholesale/cmp/escalations.html ]. 
1/16/2002 CMP Meeting - Qwest provided status update indicating that CR is in "Escalated" status, and that Qwest is reviewing Eschelon reply (received 12/21/01). 
2/20/2002 Qwest provided status update. CR remains in "Escalated" status. Meeting discussions will be set forth in the Product/Process Draft Meeting Minutes contained in the Product/Process CMP Meeting Distribution Package (03/20/02). 
3/20/2002 CMP Meeting - Qwest advised that the CR was still in an Escalated status. Meeting discussions will be set forth in the Product/Process Meeting Minutes to be posted on the CMP Web site. 
4/17/2002 CMP Meeting - Qwest advised that the CR was still in an Escalated status. 
5/15/2002 CMP Meeting - Qwest advised that the CR was still in an Escalated status. CLECs next step would be to go to Dispute Resolution. 
6/19/2002 CMP Meeting - Qwest advised that the CR was still in an Escalated status. 
7/8/2002 Per the agreement reached with the CLECs in Junes Product and Process CMP meeting, regarding escalated status this CR will carry the appropriate status prior to the escalation 

Project Meetings

10/31/01 - CR presented to the participating CLECs at the CMP Redesign Session. Meeting minutes to be incorporated when posted to Wholesale CMP Re-Design WEB page [ http://www.qwest.com/wholesale/cmp/redesign.html].