Open Product/Process CR PC072310-1 Detail

 
Title: Grandfather Centrex 21, Qwest Business Line Plus (QBLP) and Utility Line in Idaho North REVISED 08/18/10 Grandfather Centrex 21, Qwest Line Business Plus and Utility Line in Idaho North
CR Number Current Status
Date
Area Impacted Products Impacted

PC072310-1 Completed
10/20/2010
Resale
Originator: Schwartze, Cindy
Originator Company Name: Qwest Corporation
Owner: Schwartze, Cindy
Director:
CR PM: Lorence, Susan

Description Of Change

Qwest will be grandfathering Centrex 21 (RXB, RSX, EPB, R4V,XRW, WRS, R4X, R6X ), Qwest Line Business Plus (NLUDE, NLUDD, NLUDG, NLUDY, NLUDZ, NLUDL), and Utility Line (AWL) in Idaho-North. There are currently wholesale/resale customers with these products.

The proposed implementation date is 9/20/10.


Date Action Description
7/23/2010 CR Submitted CR Submitted 
7/23/2010 CR Acknowledged CR Acknowledged 
9/3/2010 Communicator Issued See level 4 notice number PROD.RESL.09.03.10.F.08247.FNL_Resale_CTX21_V32_ID. 
8/18/2010 Communicator Issued See level 4 notice number PROD.RESL.08.18.10.F.08120.ResaleCentrex21_V32_Id. 
8/18/2010 Discussed at Monthly CMP Meeting Discussed at the August Prod/Proc CMP Meeting - See Attachment D in the Distribution Package 
8/18/2010 Status Changed Status changed to Development 
9/15/2010 Discussed at Monthly CMP Meeting Discussed at the September Prod/Proc CMP Meeting - See Attachment D in the Distribution Package 
10/4/2010 Status Changed Status changed to CLEC Test 
10/20/2010 Status Changed Status Changed to Completed 
10/20/2010 Discussed at Monthly CMP Meeting Discussed at the October Prod/Proc CMP Meeting - See Attachment D in the Distribution Package 

Project Meetings

10/20/10 Product Process CMP Meeting Mark Coyne – Qwest indicated that final Level 4 notice went out on September 3, 2010. The effective date was September 20, 2010. Qwest would like to change this to Completed. There were no objections.

09/15/10 Product Process CMP Meeting Mark Coyne – Qwest indicated that there was a Level 4 notice sent out on August 18, 2010 on this. The final Level 4 notice was sent out on September 3, 2010 with an effective date of September 20, 2010.

08/18/10 Product Process CMP Meeting Cindy Schwartze – Qwest indicated that this should be Grandfather Centrex 21, Qwest Business Line Plus (QBLP) and Utility Line in Idaho-North. The plan is to grandfather these with an effective date of September 20, 2010. There are wholesale and retail customers with these products. Cindy relayed the Level 4 notice will be sent out today to meet the required lead time.

Kim Isaacs – Integra asked when you grandfather this service if the customer is already on an RXB, is this for QLSP or Resale and Retail as well.

Cindy Schwartze – Qwest indicated that it is just for Resale and Retail, not for QLSP.