Open Product/Process CR PC060517-1 Detail |
Title: Grandfather CenturyLink Home Phone Package | ||||||
CR Number |
Current Status Date |
Area Impacted | Products Impacted | |||
|
||||||
PC060517-1 |
Completed 9/20/2017 |
Resale |
Originator: Brummett , Lee |
Originator Company Name: CenturyLink |
Owner: Brummett , Lee |
Director: |
CR PM: Hansen, John |
Description Of Change |
Effective August 18, 2017, CenturyLink will grandfather CenturyLink Home Phone Package. USOC PGOQW
08-11-17 update: Per CR originator, the effective date has been changed to September 16, 2017.
|
Date | Action | Description |
6/5/2017 | CR Submitted | CR Submitted. |
6/5/2017 | CR Acknowledged | CR Acknowledged. |
6/21/2017 | Discussed at Monthly CMP Meeting | Discussed in the June Product/Process CMP Meeting - See Attachment D in the Distribution Package. |
6/21/2017 | Status Changed | Status changed to Presented. |
7/5/2017 | Communicator Issued | See notification number PROD.RESL.07.05.17.F.15690.Grandfather_Home_Phn_Pkg. |
6/30/2017 | Status Changed | Status changed to Development. |
7/19/2017 | Discussed at Monthly CMP Meeting | Discussed at the July Product/Process CMP Meeting - See Attachment D in the Distribution Package. |
8/3/2017 | Communicator Issued | See notification number PROD.RESL.08.03.17.F.15808.Fnl_Grndfthr_Home_Phn_Pkg. |
8/11/2017 | Communicator Issued | See notification number PROD.RESL.08.11.17.F.15854.REV_Fnl_Grndfthr_Home_Pkg - revised final notice that changed effective date. |
8/11/2017 | Record Update | Per CR originator, the effective date for this CR has been changed to September 16, 2017. |
8/16/2017 | Discussed at Monthly CMP Meeting | Discussed at the August Product/Process CMP Meeting - See Attachment D in the Distribution Package. |
9/16/2017 | Status Changed | Status changed to CLEC Test. |
9/20/2017 | Status Changed | Status changed to Completed. |
9/20/2017 | Discussed at Monthly CMP Meeting | Discussed at the September Product/Process CMP Meeting - See Attachment D in the Distribution Package. |
Project Meetings |
9/20/17 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this CR has been in CLEC Test as of September 16, 2017. It is associated with grandfathering the CenturyLink Home Phone Package, USOC PGOQW. The effective date was originally planned for August 18, 2017 but on August 11, 2017, an update to the CR was submitted to delay the planned effective date to September 16, 2017. A revised final notification was distributed on that date to communicate the effective date change for all of the Legacy Qwest states. On September 15, 2017, CenturyLink distributed a Level 1 Product notification PROD.RESL.09.15.17.F.15716.HomePhoneExtraPkg that makes the replacement package available in the remaining Legacy Qwest states as of September 16. Effective as of July 15, 2017, the new replacement package was available in the states of Nebraska, Oregon, and Arizona. Mark stated that we would like to move this CR to a COMPLETED status and asked if there were any objections. There were none. 8/16/17 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this change request is associated with grandfathering the CenturyLink Home Phone Package, USOC PGOQW. The final notice was distributed August 3, 2017 with an effective date originally planned for August 18, 2017. No comments were received. On August 11, 2017, an update to the CR was submitted to delay the planned effective date to September 16, 2017. A revised final notice was distributed on that date to communicate the effective date change for all of the CenturyLink QC states. Effective as of July 15, 2017, the new replacement package is already available in the states of Nebraska, Oregon, and Arizona. The Home Phone Extra Package replacement will be available in the remaining CenturyLink QC states as of September 16 also. We will discuss this CR again next month. 7/19/17 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated this new CR was presented last month by Lee Brummett. The Level 4 initial notice was sent on July 5, 2017. The comment cycle closes July 20, 2017. The change has a planned effective date of August 18, 2017. In the June CMP meeting, Lee relayed that the replacement package will be announced on June 28, 2017 with an effective date of June 29, 2017. The Tariff notice was distributed June 22, 2017. CenturyLink sent a Level 1 notice on July 14, 2017 announcing the availability of the new package in the states of Nebraska, Oregon, and Arizona. We will be sending a Level 1 notification on August 11, 2017 to announce that replacement package with an effective date of August 12, 2017 for the rest of the CenturyLink QC region. Mark asked if there were any questions. There were none. 6/21/17 - Product/Process CMP Meeting Mark Coyne – CenturyLink stated that this was a new CR to be presented by Lee Brummett. Lee Brummett – CenturyLink said that, with the effective date of August 18, 2017 this package would be grandfathered in all CenturyLink QC states. Kim Isaacs – Allstream asked how the package grandfathering would be handled. If a call forward number needed to be changed, would it require removing the package code? Lee Brummett – CenturyLink stated that a replacement package would be available on July 15, 2017 in the states of Nebraska, Oregon, and Arizona and in the remaining states on August 12, 2017. A new document will be made available describing the new Home Phone Package. Janean Van Dusen- CenturyLink stated that changes to call forwarding numbers and PIC changes could be made to existing packages despite the grandfathering, but no addition or swapping of features would be allowed.
|