Open Product/Process CR PC050812-2X Detail

 
Title: Informed Firm Order Commitment (FOC) with Detailed Build Interval Information in REMARKS(Crossover CR from SCR050812 2X)
CR Number Current Status
Date
Area Impacted Products Impacted

PC050812-2X Completed
9/19/2012
DS1, DS3, and OCn
Originator: Warner, Chad
Originator Company Name: Verizon
Owner: Robberson, Anne
Director:
CR PM: Lorence, Susan

Description Of Change

3. Request that CenturyLink provide an informed FOC and identify delivery intervals where a build is required within 9 business days for DS1, DS3, and OCn (Ethernet and fEmabarq/CT scheduled in later phase(s)) with details in the REMARKS field of the FOC. This goes along with using the Network Facility Requirement (NFR) field on the FOC. In addition, provide details in the REMARKS field for minor builds when the interval is longer than the standard interval. This will help Verizon set the appropriate interval expectation with our customer when a build is required by CenturyLink.


Date Action Description
6/20/2012 Discussed at Monthly CMP Meeting Discussed at June System CMP Meeting – See Attachment E in the System Distribution package. CR will be crossed over to a Product Process CR. For additional information, see SCR050812-2X, CenturyLink Response. 
5/8/2012 CR Submitted CR originated as a System CR. See SCR050812-2 for history.  
6/25/2012 Status Changed Status changed ot Development 
7/18/2012 Discussed at Monthly CMP Meeting Discussed at July System CMP Meeting – See Attachment C of the Product/Process package. 
7/17/2012 Communicator Issued See notice number PROS.PROV.07.17.12.F.10296.Prov_Instl_V144 
8/16/2012 Communicator Issued See notice number PROS.PROV.08.16.12.F.10391.FNL_RESP_Prov_Instl_V144 
8/15/2012 Discussed at Monthly CMP Meeting Discussed at August System CMP Meeting – See Attachment C of the Product/Process package. 
8/31/2012 Status Changed Status changed to CLEC Test. 
9/19/2012 Status Changed Status changed to Completed 
9/19/2012 Discussed at Monthly CMP Meeting Discussed at September CMP Meeting – See Attachment C of the Product/Process package. 

Project Meetings

September 19, 2012 Product/Process CMP Meeting Mark Coyne - CenturyLink relayed a level 3 initial notification was sent on 7/17/12. The final notice and response to CLEC comments were sent 8/16/12 with an effective date of 8/31/12. Mark relayed the CR is in CLEC Test and we would like to move the CR to completed. Mark asked if there were any objections. There were no objections.

August 15, 2012 Product/Process CMP Meeting Mark Coyne - CenturyLink relayed a level 3 initial notification was sent on 7/17/12 providing the change in process. The final notice and response to CLEC comments are due 8/16/12 with an effective date of 8/31/12.

July 18, 2012 Product/Process CMP Meeting Mark Coyne - CenturyLink recapped the Change Request and explained that it had been opened as a Systems Change Request but had been transferred to a Product/Process Cross-Over Change Request. A Level 3 Product Process notification was sent out on July 17, 2012 with an effective date of August 31, 2012.

Kim Isaacs – Integra stated that a download associated with the change was missing from the review site.

Susan Lorence – CenturyLink stated that CenturyLink would investigate and correct.

Chad Warner – Verizon asked about adding Ethernet at a later date and stated that it was not detailed in the products listed in the Change Request. He asked if it needed to be added to be considered.

Mark Coyne – CenturyLink indicated that it was planned for a future roll out of this enhancement.

Chad Warner – Verizon pointed out that there was a list of products impacted and that Ethernet was not in the list.

Mark Coyne – CenturyLink indicated that in the definition, Ethernet was identified.

Susan Lorence – CenturyLink added that CenturyLink can revise the Change Request to include it and asked Chad if he felt documents on the review site should be updated. She added that the final notice could include information.

Chad Warner – Verizon indicated that he just wanted to make sure it did not get lost along the way since it was part of the request.

Susan Lorence – CenturyLink stated that Anne Robberson from CenturyLink was on the call and asked if she had any updates.

Anne Robberson – CenturyLink stated that the spreadsheet missing from the review site provided timelines. The Phase 1 piece is scheduled to into effect on August 31, 2012. The Ethernet piece requires internal process changes and hopes for an end of year deployment.

Liz Tierney – Megapath Inc. asked if the LSR/ASR request would generate an FOC and then someone would manually provide the information.

Anne Robberson – CenturyLink stated that the FOCs would remain manually processed.

Kim Isaacs – Integra asked for clarification that this process was for ASR only.

Anne Robberson – CenturyLink confirmed that was correct.

June 20, 2012 System CMP Meeting Mark Coyne – CenturyLink stated that this CR was presented in the May meeting. On June 13, 2012, CenturyLink provided the CenturyLink response to Verizon that identified that during evaluation it was determined that the best solution would be a Product/Process change. CenturyLink proposed that the CR be crossed over from Systems to Product/Process. Mark asked if Chad had anything to add.

Chad Warner – Verizon stated there had been some email exchanges regarding Ethernet being included in a Phase 2 and wanted confirmation.

Mark Coyne – CenturyLink stated that was true.

Susan Lorence – CenturyLink added that no revisions were required to the CR.


CenturyLink Response

CenturyLink DRAFT Response

June 13, 2012 Chad Warner, Verizon Tom Priday, Verizon

SUBJECT: CR # SCR050812-2 Informed Firm Order Commitment (FOC) with Detailed Build Interval Information in REMARKS

This letter is in response to Verizon’s Change Request (CR) SCR050812-2, Informed Firm Order Commitment (FOC) with Detailed Build Interval Information in REMARKS.

This CR requests that CenturyLink provide an informed FOC and identify delivery intervals where a build is required within nine business days for DS1, DS3, and OCn services and to provide the details in the REMARKS field of the FOC.

CenturyLink is accepting this CR and is currently working on developing the solution. CenturyLink believes this CR will not require a system solution from a CLEC perspective and would like to cross this CR over to a Product Process change request during the June CMP meeting. As such, this CR SCR050812-2 will be closed and CenturyLink will open CR PC050812-2X on Verizon’s behalf with a reference to the original system CR.

Based upon CenturyLink’s understanding of the scope of this CR, CenturyLink views the implementation of this CR as a Level 3, “change in process” and will follow that timeline to implement the solution. CenturyLink is considering a phased implementation for this change request with DS1, DS3, and OCn services provided in a Phase 1 roll-out with Metro Ethernet services roll-out during Phase 2 at a later date. CenturyLink proposes that Verizon modify their CR to include Metro Ethernet services.

CenturyLink will seek concurrence for this approach at the June Monthly Product & Process CMP meeting.

Sincerely, Susan Lorence CenturyLink CR Project Manager