Open Product/Process CR PC050707-1 Detail |
Title: Removal of AIN PCAT | ||||||
CR Number |
Current Status Date |
Area Impacted | Products Impacted | |||
|
||||||
PC050707-1 |
Completed 8/15/2007 |
Ordering | AIN |
Originator: Buckmaster, Cindy |
Originator Company Name: Qwest Corporation |
Owner: Buckmaster, Cindy |
Director: |
CR PM: Stecklein, Lynn |
Description Of Change |
Removal of AIN PCAT due to inavailability of this UNE-P reliant product
|
Date | Action | Description |
5/7/2007 | CR Submitted | |
5/7/2007 | CR Acknowledged | |
5/16/2007 | Discussed at Monthly CMP Meeting | Discussed at the May CMP Meeting - See Attachment D in the Distribution Package |
5/18/2007 | Status Changed | Status changed to Presented |
5/7/2007 | Related Change Request | PC102704-1ES and PC102704-1ES2 |
6/5/2007 | Status Changed | Status changed to Development |
6/12/2007 | Communicator Issued | PROD.06.11.07.F.04733.TRRO_Elimination_of_AIN |
6/20/2007 | Discussed at Monthly CMP Meeting | Discussed at the June Product/Process CMP Meeting - See Attachment E in the Distribution Package |
7/18/2007 | Discussed at Monthly CMP Meeting | Discussed at the July CMP Product/Process Meeting - See Attachment D in the Distribution Package |
7/31/2007 | Status Changed | Status changed to CLEC Test |
8/15/2007 | Status Changed | Status changed to Completed |
8/15/2007 | Discussed at Monthly CMP Meeting | Discussed at the August Product/Process CMP Meeting - See Attachment D in the Distribution Package |
Project Meetings |
8/15/07 Product/Process CMP Meeting Mark Coyne-Qwest stated that the final notice was sent on 7/12/07 and was effective on 7/27/07. He said that this CR has been in CLEC Test and asked if there was any objection to closure of this CR. This CR is in Completed status. 7/17/07 Product/Process CMP Meeting Mark Coyne-Qwest stated that this CR is in Development status and that the final notice had gone out on July 11, with an effective date of July 26th. Mark then stated that Qwest would look to close this CR in the August CMP Meeting. 6/20/07 Product/Process CMP Meeting Mark Coyne-Qwest stated that the Level 4 notice was sent on 6/11/07 to become effective 7/26/07. He said that the request is in the comment cycle and Qwest will respond if appropriate. 5/16/07 Product/Process CMP Meeting Cindy Buckmaster-Qwest stated that for these 2 CRs,(see PC050907-1) Qwest would be removing the UNE-P PCAT and the Unbundled Switching PCAT. Cindy stated that there are no customers using these products and stated that the PCATs would be eliminated. Kim Isaacs-Eschelon stated that UNE-P is going to be removed and noted that it is governed under CMP. Kim then asked how QLSP and the Commercial PCATs would be treated and asked if they would be a notice and go. [Comment from Eschelon: Kim Isaacs-Eschelon stated that UNE-P is going to be removed and noted that it is governed under CMP. Kim then asked how updates to the QLSP and the Commercial PCATs would be treated and asked if they would be a notice and go.] Mark Coyne-Qwest stated that they would be cared for as non-CMP. Kim Isaacs-Eschelon asked if they would be notice and go. Mark Coyne-Qwest stated that was correct.
|
Information Current as of 1/11/2021