Wholesale: Products & Services

Open Product/Process CR PC040907-1 Detail

 
Title: Qwest Procured Equipment Bay for Cageless Collocation
CR Number Current Status
Date
Area Impacted Products Impacted

PC040907-1 Completed
11/14/2007
Ordering Cageless Collocation
Originator: Schwartze, Cindy
Originator Company Name: Qwest Corporation
Owner: Schwartze, Cindy
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

This change is to offer CLECs with the optional feature of having Qwest procure and install the Equipment Bay and associated support infrastructure for the CLEC’s Cageless collocation request. Currently the CLEC is responsible for delivery and installation of the Equipment Bay. This new feature will be available on the existing Collocation form as another option.

Expected Deliverable:

A new feature associated with Cageless Collocation will be available and documented for the Wholesale customer. Qwest would update the Cageless Collocation PCAT, Application Form, and Technical Publications to include this optional feature.


Date Action Description
4/9/2007 CR Submitted  
4/9/2007 CR Acknowledged  
5/16/2007 Discussed at Monthly CMP Meeting Discussed in the May Monthly Product Process CMP Meeting 
6/20/2007 Discussed at Monthly CMP Meeting Discussed in the June Monthly Product Process CMP Meeting 
7/18/2007 Discussed at Monthly CMP Meeting Discussed in the July Monthly Product Process CMP Meeting 
8/15/2007 Discussed at Monthly CMP Meeting Discussed in the August Monthly Product Process CMP Meeting 
9/25/2007 Communicator Issued NETW.09.25.07.F.04876.Tech_Pub_77386_CglssCollo (Level 3) 
9/25/2007 Communicator Issued PROD.09.25.07.F.04928.Collo_Equip_Bay (Level 4) 
9/19/2007 Discussed at Monthly CMP Meeting Discussed in the September Monthly Product Process CMP Meeting 
10/17/2007 Discussed at Monthly CMP Meeting Discussed at the October CMP Monthly Meeting - See Attachment D in the Distribution Package 
11/8/2007 Status Changed Status changed to CLEC Test 
11/8/2007 Communicator Issued PROD.10.25.07.F.04998.FNL_Collo_Equip_Bay 
11/14/2007 Discussed at Monthly CMP Meeting Discussed at the November Systems CMP Meeting - See Attachment K in the Distribution Package 
11/14/2007 Status Changed Status changed to Completed 

Project Meetings

November 14, 2007 Product Process CMP Meeting Discussion:

Susan Lorence-Qwest stated that the effective date for this change was 11/09/07 and that we were looking to close. There was no objection to the closure of this CR.

--

October 17, 2007 Product Process CMP Meeting Discussion:

Mark Coyne-Qwest stated that the Final Notice is due on October 25th and the effective date will be November 9th. Mark stated that we will look at closing this CR in the November CMP Meeting.

September 19, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this was presented last month and noted that we are still working on the documentation updates. Mark then stated that we are looking for the notice to be sent at the end of this month.

August 15, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this CR had been discussed last month and noted that Qwest is still working on the Level 4 changes to the documentation and is targeting the notice to go out at the end of the month. Mark then noted that the changes would probably be effective mid October. This CR is in Presented Status.

July18, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this CR has been presented and noted that Qwest is working on the associated updates. Mark stated that we are looking for the notice to go out in early August and stated that the CR would then move to Development status.

June 20, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this CR was presented in May and noted that there is no update regarding the effective date. Mark stated that we are targeting the notice to go out in early July.

- May 16, 2007 Product Process CMP Meeting Discussion: Cindy Schwartze-Qwest reviewed the CRs Description and Expected Deliverable and asked if there were any questions. Kim Isaacs-Eschelon asked if this would truly be an optional feature and asked to confirm that a CLEC can still procure and install the equipment or they can choose Qwest procure and install it. Cindy Schwartze-Qwest stated that was correct. Cindy then asked if there were any other questions. There were none. Mark Coyne-Qwest stated that this CR moves to Presented Status and noted that Qwest is working on the documentation changes.


Information Current as of 1/11/2021