Open Product/Process CR PC032807-1 Detail |
| Title: TRRO: Un UNE 8XX Database Queries | ||||||
| CR Number |
Current Status Date |
Area Impacted | Products Impacted | |||
|
|
||||||
| PC032807-1 |
Completed 7/18/2007 |
8XX | ||||
| Originator: Lewis, Don |
| Originator Company Name: Qwest Corporation |
| Owner: Lewis, Don |
| Director: |
| CR PM: Esquibel-Reed, Peggy |
Description Of Change |
|
Discontinue availability of 8XX Database Queries as a UNE, per TRRO.
Expected Deliverable: Change in PCAT for 8XX.
|
| Date | Action | Description |
| 3/28/2007 | CR Submitted | |
| 3/28/2007 | CR Acknowledged | |
| 3/28/2007 | Related Change Request | PC102704-1ES / PC102704-1ES2 |
| 4/18/2007 | Discussed at Monthly CMP Meeting | Discussed in the April Monthly Product Process CMP Meeting |
| 5/21/2007 | Communicator Issued | PROD.05.21.07.F.04672.MultiplePCAT_TRRO (Level 4) |
| 5/21/2007 | Status Changed | Status changed to Development |
| 5/16/2007 | Discussed at Monthly CMP Meeting | Discussed in the May Monthly Product Process CMP Meeting |
| 6/20/2007 | Discussed at Monthly CMP Meeting | Discussed in the June Monthly Product Process CMP Meeting |
| 7/5/2007 | Status Changed | Status Changed to CLEC Test Due To July 5, 2007 Implementation |
| 7/18/2007 | Discussed at Monthly CMP Meeting | Discussed in the July Monthly Product Process CMP Meeting |
Project Meetings |
| July18, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this change was also effective on July 5th and asked if there were any objections to close. There were no objections. This CR is in Completed Status. -- June 20, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that the Level 4 Notice had also been sent on May 21st and is currently in the comment cycle. Mark the noted that this change would become effective on July 5th.
- May 16, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that the Level 4 Notice would be sent on May 21st and will have an effective date of July 5th. -- April 18, 2007 Product Process CMP Meeting Discussion: Don Lewis-Qwest stated that this will be to un-UNE 8XX and ill be referring to the Federal and Access Tariffs. Don stated that the Level 4 Notification would be going out at the end of the month for this CR as well. Mark Coyne-Qwest asked if there were any questions. There were none.
|