Wholesale: Products & Services

Open Product/Process CR PC030507-1 Detail

 
Title: TRRO: Un UNE LIDB
CR Number Current Status
Date
Area Impacted Products Impacted

PC030507-1 Completed
7/18/2007
LIDB
Originator: Lewis, Don
Originator Company Name: Qwest Corporation
Owner: Lewis, Don
Director:
CR PM: Esquibel-Reed, Peggy

Description Of Change

Discontinue availability of LIDB as a UNE


Date Action Description
3/5/2007 CR Submitted  
3/5/2007 CR Acknowledged  
3/5/2007 Related Change Request PC102704-1ES and PC102704-1ES2 
3/21/2007 Discussed at Monthly CMP Meeting Discussed in the March Monthly Product Process CMP Meeting 
4/18/2007 Discussed at Monthly CMP Meeting Discussed in the April Monthly Product Process CMP Meeting 
5/21/2007 Communicator Issued PROD.05.21.07.F.04672.MultiplePCAT_TRRO (Level 4) 
5/16/2007 Discussed at Monthly CMP Meeting Discussed in the May Monthly Product Process CMP Meeting 
6/20/2007 Discussed at Monthly CMP Meeting Discussed in the June Monthly Product Process CMP Meeting 
7/5/2007 Status Changed Status Changed to CLEC Test Due To July 5, 2007 Implementation 
7/18/2007 Discussed at Monthly CMP Meeting Discussed in the July Monthly Product Process CMP Meeting 

Project Meetings

July18, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this CR was effective on July 5th and is currently in CLEC Test. Mark then asked if there was any objection to closure of the CR. There were no objections. This CR is in Completed Status.

June 20, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this CR was implemented on May 21st and is currently in the comment cycle with an effective date of July 5th. Mark then stated that this CR remains in Development status.

-- May 16, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this CR was presented last month and noted that the documentation is being updated. Mark then stated that the Level 4 Notice would be sent on May 21st and will have a July 5th effective date.

April 18, 2007 Product Process CMP Meeting Discussion: Mark Coyne-Qwest stated that this was presented in the April CMP Meeting and stated that the notification would be sent at the end of the month.

- March 23, 2007 Email Sent to Eschelon: Hi Bonnie, Your email was received. Will you please share with me your concern regarding the Level 2 Notification request for PC030507-1 and PC030507-2? Thank you, Peggy Esquibel-Reed Qwest Wholesale CMP

- March 23, 2007 Email Received from Eschelon: Eschelon will not agree to Qwest issuing the changes for PC0305207-1 and PC0305207-2 as level 2 changes. In addition, Changes regarding TRRO are considered change in law and should be handled via negotiations or in some type of forum, such as changes to the SGAT, where there is Commission oversight. Thanks, Bonnie Johnson Director Carrier Relations Eschelon Telecom Inc.

-- March 21, 2007 Product Process CMP Meeting: Don Lewis-Qwest presented the CR and stated that Qwest is discontinuing LIDB as a UNE. Don stated that the PCAT would be updated and noted that there would be no impact to CLEC operations. Don asked if there were any questions. Kim Isaacs-Eschelon stated that Eschelon could have a question later. Mark Coyne-Qwest stated that due to there being no customers, Qwest would like to send out a Level 2 Notice for this CR and asked if there were any objections to a Level 2 Notice. Kim Isaacs-Eschelon stated that she would check.


Information Current as of 1/11/2021